Worthington Approves $390,000 for Active Transportation and Mobility Projects

Worthington City Council appropriates $390,000 for EMH&T to spearhead a five-part active transportation initiative pairing municipal funds with regional COTA LinkUS dollars.

Worthington City Council has approved legislation appropriating not to exceed Three-Hundred-Ninety-Thousand-Dollars ($390,000) to pay the cost of the 2026 Active Transportation and Mobility Services Project (Project No. 794-26) from the municipal Capital Improvements Fund unappropriated balance.

Council Passed: September 8, 2026 Ordinance No. 26-2026 (As Amended), authorizing City Manager Robyn Stewart to enter into an agreement with the firm of EMH&T for the provision of the aforementioned engineering and planning services. The contract carries the option, at the City’s discretion, to renew the contract for up to two (2) additional one (1) year terms beyond an initial three-year engagement. First introduced on July 20, 2026, the ordinance becomes Effective: September 30,2026.

The municipal action bundles five distinct mobility improvements under a single professional services contract. The overarching program objective is to advance the accessibility of Worthington’s bicycle, pedestrian, and transit network in alignment with the City’s 2019 Bicycle and Pedestrian Master Plan, according to procurement specifications in City Project No. 794-26 (documentRef a273dcfd-5dcb-3a25-afbc-0b59ea57de9e, page 2).

Program Funding and Regional LinkUS Alignment

The approved $390,000 expenditure is allocated to Account No. 308.8150.533526 within the Capital Improvements Fund (documentRef b5d1a3ee-4da5-3d00-8f6b-713d6bceee52, page 1). While the corridor study component is entirely city-financed, the larger program links local investments to regional transit improvements.

As detailed in municipal records (documentRef a273dcfd-5dcb-3a25-afbc-0b59ea57de9e, page 2), Several projects within the Program are funded through COTA’s LinkUS Transit Supportive Infrastructure (TSI) Program. The shared-use path, sidewalk gap elimination, and highway interchange improvements are scheduled in alignment with COTA requirements, with engineering authorizations phased alongside intergovernmental agreements.

Worthington-Galena Road Corridor Study

The first bundled project element focuses on an uncurbed roadway connecting US-23 (High Street) northeast to Schrock Road and East Wilson Bridge Road. Following traffic network reconfigurations that culminated with the completion of the Northeast Gateway project in 2022., overall vehicular volumes on Worthington-Galena Road dropped, but excessive driver speeds and student pedestrian and bicycle traffic to adjacent schools remain unaddressed (documentRef a273dcfd-5dcb-3a25-afbc-0b59ea57de9e, page 3).

The corridor study is expected to be locally funded. and will assess existing conditions, safety performance, and future demand. Fieldwork will Collect Turning Movement Count (TMC) data (including bicycles and pedestrians) at High Street, Schrock Road, Crandall Drive, and Highland Avenue (documentRef a273dcfd-5dcb-3a25-afbc-0b59ea57de9e, pages 3–4).

Engineers will explore three design alternatives, evaluate roundabout feasibility at intersections, and gather community feedback through public meetings and exhibits before presenting recommendations to the Worthington Bicycle and Pedestrian Advisory Board and City Council (documentRef a273dcfd-5dcb-3a25-afbc-0b59ea57de9e, page 4). The corridor study is scheduled to be Completed by the end of 2027 (documentRef a273dcfd-5dcb-3a25-afbc-0b59ea57de9e, page 5).

East Wilson Bridge Road Shared-Use Path

The second element advances detailed engineering for a 10-foot-wide multi-use path stretching 0.7 miles along East Wilson Bridge Road between High Street and Eastview Drive (documentRef a273dcfd-5dcb-3a25-afbc-0b59ea57de9e, page 5). The trail will establish a dedicated connection between the Olentangy Trail, the US-23 corridor, and the Worthington Community Center, incorporating the addition of street lighting, street trees, drainage infrastructure, and crosswalks..

Designers must interface with a separate study of the High Street and Wilson Bridge Road intersection, where analysis is scheduled to conclude in early 2027.. The path will be situated within public right-of-way wherever feasible, with legal descriptions and property exhibits prepared where easements prove necessary (documentRef a273dcfd-5dcb-3a25-afbc-0b59ea57de9e, pages 6–7).

Supported by COTA LinkUS TSI funding, the multi-year project timeline anticipates preliminary design completion in December 2026, detailed design and right-of-way plans in July 2027, land acquisition closure in February 2028, bidding in February 2029, and Construction: May 2029 (CACI) (documentRef a273dcfd-5dcb-3a25-afbc-0b59ea57de9e, page 8).

Sidewalk Gap Elimination Program

The third element targets missing pedestrian links across the community. The overall initiative will project will address up to 1.36 miles of sidewalk gaps, as identified in the City’s Bicycle and Pedestrian Master Plan (documentRef a273dcfd-5dcb-3a25-afbc-0b59ea57de9e, page 8).

Engineering consultants will categorize identified gaps into three tiers based on design complexity:

  • Category 1: No topo or RW needed (least complex, with no survey or right-of-way acquisition required)
  • Category 2: Topographic survey required without right-of-way acquisition
  • Category 3: Both topographic survey and property acquisition required

Work under the 2026 agreement advances Category 1 segments directly to detailed construction drawings, with Category 1 Plans complete: December 2026, contractor bidding in February 2027, and construction in April 2027 (documentRef a273dcfd-5dcb-3a25-afbc-0b59ea57de9e, page 9). More complex locations are anticipated to be funded with additional LinkUS TSI funding in 2027, 2028, and 2029..

SR 315 / SR 161 Interchange and Olentangy Trail Crossing

The fourth element tackles a long-standing active transportation obstacle where the Olentangy Trail meets state highway ramps. City records show the project will eliminate the existing spur and provide a new pedestrian crossing at the eastern ramp intersection of SR-161 and SR-315. (documentRef a273dcfd-5dcb-3a25-afbc-0b59ea57de9e, page 9).

Planned improvements include pedestrian signalization, crosswalk signage, pavement markings, guardrail, and ADA-compliant curb ramps. In addition, implemented along the northernmost lane of SR-161 in the vicinity of the crossing to create a buffer between moving traffic and pedestrians (documentRef a273dcfd-5dcb-3a25-afbc-0b59ea57de9e, page 9).

These measures stem from an engineering review where an and interchange operation study was conducted in 2025 to identify these countermeasures as acceptable improvements (documentRef a273dcfd-5dcb-3a25-afbc-0b59ea57de9e, page 10). Because the project occupies state-controlled land, Note: This project interacts with ODOT right-of-way and will require an ODOT right-of-way permit., along with city floodplain permits and Ohio EPA stormwater reviews (documentRef a273dcfd-5dcb-3a25-afbc-0b59ea57de9e, page 11). Design plans are due in February 2027, permits and bidding in March 2027, and contractor Construction: May 2027 (documentRef a273dcfd-5dcb-3a25-afbc-0b59ea57de9e, page 12).

General On-Call Mobility and Transportation Services

The fifth element establishes an ongoing on-call mobility mechanism under which EMH&T will provide support on a task-order basis. Under the contract, services will be task-based up to an annual allowance for which the Respondent shall provide an hourly billable rate schedule (documentRef a273dcfd-5dcb-3a25-afbc-0b59ea57de9e, page 12).

Services authorized under this element include future corridor studies, traffic modeling, concept and feasibility analyses, grant writing assistance, detailed design, and public engagement through the contract duration ending in 2029 and any subsequent renewal terms. Notice of the adopted legislation has been posted at the Municipal Administration Building, the Worthington Library, the Griswold Center and the Worthington Community Center (documentRef b5d1a3ee-4da5-3d00-8f6b-713d6bceee52, page 2).

How we know this

The sources and records behind this story, with the facts they support.

  1. Page 1

    www.worthington.org

    Accessed September 25, 2026

    Supporting evidence (2)
    • Worthington City Council has approved legislation appropriating not to exceed Three-Hundred-Ninety-Thousand-Dollars ($390,000) to pay the cost of the 2026 Active Transportation and Mobility Services Project (Project No. 794-26) from the municipal Capital Improvements Fund unappropriated balance.

      Read supporting passage
      not to exceed Three-Hundred-Ninety-Thousand-Dollars ($390,000) to pay the cost of the
    • Council Passed: September 8, 2026 Ordinance No. 26-2026 (As Amended), authorizing City Manager Robyn Stewart to enter into an agreement with the firm of EMH&T for the provision of the aforementioned engineering and planning services.

      Read supporting passage
      enter into an agreement with the firm of EMH&T for the provision of the aforementioned
  2. Page 2

    www.worthington.org

    Accessed September 25, 2026

    Supporting evidence (3)
    • Council Passed: September 8, 2026 Ordinance No. 26-2026 (As Amended), authorizing City Manager Robyn Stewart to enter into an agreement with the firm of EMH&T for the provision of the aforementioned engineering and planning services.

      Read supporting passage
      Passed: September 8, 2026
    • First introduced on July 20, 2026, the ordinance becomes Effective: September 30,2026.

      Read supporting passage
      Effective: September 30,2026
    • Notice of the adopted legislation has been posted at the Municipal Administration Building, the Worthington Library, the Griswold Center and the Worthington Community Center (documentRef b5d1a3ee-4da5-3d00-8f6b-713d6bceee52, page 2).

      Read supporting passage
      Municipal Administration Building, the Worthington Library, the Griswold Center and the
  3. Page 2

    worthington.org

    Accessed September 25, 2026

    Supporting evidence (3)
    • The contract carries the option, at the City’s discretion, to renew the contract for up to two (2) additional one (1) year terms beyond an initial three-year engagement.

      Read supporting passage
      the option, at the City’s discretion, to renew the contract for up to two (2) additional one (1) year terms
    • The overarching program objective is to advance the accessibility of Worthington’s bicycle, pedestrian, and transit network in alignment with the City’s 2019 Bicycle and Pedestrian Master Plan, according to procurement specifications in City Project No. 794-26 (documentRef a273dcfd-5dcb-3a25-afbc-0b59ea57de9e, page 2).

      Read supporting passage
      accessibility of Worthington’s bicycle, pedestrian, and transit network in alignment with the City’s 2019
    • As detailed in municipal records (documentRef a273dcfd-5dcb-3a25-afbc-0b59ea57de9e, page 2), Several projects within the Program are funded through COTA’s LinkUS Transit Supportive Infrastructure (TSI) Program.

      Read supporting passage
      Several projects within the Program are funded through COTA’s LinkUS Transit Supportive Infrastructure
  4. Page 3

    worthington.org

    Accessed September 25, 2026

    Supporting evidence (3)
    • Following traffic network reconfigurations that culminated with the completion of the Northeast Gateway project in 2022., overall vehicular volumes on Worthington-Galena Road dropped, but excessive driver speeds and student pedestrian and bicycle traffic to adjacent schools remain unaddressed (documentRef a273dcfd-5dcb-3a25-afbc-0b59ea57de9e, page 3).

      Read supporting passage
      with the completion of the Northeast Gateway project in 2022.
    • The corridor study is expected to be locally funded. and will assess existing conditions, safety performance, and future demand.

      Read supporting passage
      is expected to be locally funded.
    • Fieldwork will Collect Turning Movement Count (TMC) data (including bicycles and pedestrians) at High Street, Schrock Road, Crandall Drive, and Highland Avenue (documentRef a273dcfd-5dcb-3a25-afbc-0b59ea57de9e, pages 3–4).

      Read supporting passage
      Collect Turning Movement Count (TMC) data (including bicycles and pedestrians)
  5. Page 5

    worthington.org

    Accessed September 25, 2026

    Supporting evidence (3)
    • The corridor study is scheduled to be Completed by the end of 2027 (documentRef a273dcfd-5dcb-3a25-afbc-0b59ea57de9e, page 5).

      Read supporting passage
      Completed by the end of 2027
    • The trail will establish a dedicated connection between the Olentangy Trail, the US-23 corridor, and the Worthington Community Center, incorporating the addition of street lighting, street trees, drainage infrastructure, and crosswalks..

      Read supporting passage
      addition of street lighting, street trees, drainage infrastructure, and crosswalks.
    • Designers must interface with a separate study of the High Street and Wilson Bridge Road intersection, where analysis is scheduled to conclude in early 2027..

      Read supporting passage
      scheduled to conclude in early 2027.
  6. Page 8

    worthington.org

    Accessed September 25, 2026

    Supporting evidence (3)
    • Supported by COTA LinkUS TSI funding, the multi-year project timeline anticipates preliminary design completion in December 2026, detailed design and right-of-way plans in July 2027, land acquisition closure in February 2028, bidding in February 2029, and Construction: May 2029 (CACI) (documentRef a273dcfd-5dcb-3a25-afbc-0b59ea57de9e, page 8).

      Read supporting passage
      Construction: May 2029 (CACI)
    • The overall initiative will project will address up to 1.36 miles of sidewalk gaps, as identified in the City’s Bicycle and Pedestrian Master Plan (documentRef a273dcfd-5dcb-3a25-afbc-0b59ea57de9e, page 8).

      Read supporting passage
      project will address up to 1.36 miles of sidewalk gaps, as identified in the City’s Bicycle and Pedestrian
    • Category 1: No topo or RW needed (least complex, with no survey or right-of-way acquisition required)

      Read supporting passage
      Category 1: No topo or RW needed
  7. Page 9

    worthington.org

    Accessed September 25, 2026

    Supporting evidence (4)
    • Work under the 2026 agreement advances Category 1 segments directly to detailed construction drawings, with Category 1 Plans complete: December 2026, contractor bidding in February 2027, and construction in April 2027 (documentRef a273dcfd-5dcb-3a25-afbc-0b59ea57de9e, page 9).

      Read supporting passage
      Category 1 Plans complete: December 2026
    • More complex locations are anticipated to be funded with additional LinkUS TSI funding in 2027, 2028, and 2029..

      Read supporting passage
      anticipated to be funded with additional LinkUS TSI funding in 2027, 2028, and 2029.
    • City records show the project will eliminate the existing spur and provide a new pedestrian crossing at the eastern ramp intersection of SR-161 and SR-315.

      Read supporting passage
      eastern ramp intersection of SR-161 and SR-315.
    • In addition, implemented along the northernmost lane of SR-161 in the vicinity of the crossing to create a buffer between moving traffic and pedestrians (documentRef a273dcfd-5dcb-3a25-afbc-0b59ea57de9e, page 9).

      Read supporting passage
      implemented along the northernmost lane of SR-161 in the vicinity of the crossing to create a buffer
  8. Page 10

    worthington.org

    Accessed September 25, 2026

    Supporting evidence (2)
    • These measures stem from an engineering review where an and interchange operation study was conducted in 2025 to identify these countermeasures as acceptable improvements (documentRef a273dcfd-5dcb-3a25-afbc-0b59ea57de9e, page 10).

      Read supporting passage
      and interchange operation study was conducted in 2025 to identify these countermeasures as acceptable
    • Because the project occupies state-controlled land, Note: This project interacts with ODOT right-of-way and will require an ODOT right-of-way permit., along with city floodplain permits and Ohio EPA stormwater reviews (documentRef a273dcfd-5dcb-3a25-afbc-0b59ea57de9e, page 11).

      Read supporting passage
      Note: This project interacts with ODOT right-of-way and will require an ODOT right-of-way permit.
  9. Page 12

    worthington.org

    Accessed September 25, 2026

    Supporting evidence (2)
    • Design plans are due in February 2027, permits and bidding in March 2027, and contractor Construction: May 2027 (documentRef a273dcfd-5dcb-3a25-afbc-0b59ea57de9e, page 12).

      Read supporting passage
      Construction: May 2027
    • Under the contract, services will be task-based up to an annual allowance for which the Respondent shall provide an hourly billable rate schedule (documentRef a273dcfd-5dcb-3a25-afbc-0b59ea57de9e, page 12).

      Read supporting passage
      services will be task-based up to an annual allowance for which the Respondent shall provide an hourly