Columbus Planners Support NetJets Variances on Bridgeway Avenue
City planning staff supported the requested variances under the Columbus Growth Strategy while zoning officials outlined parcel and setback conditions.
The City of Columbus uploaded staff review results on Oct. 26, 2026, for Council Variance application CV26-095. The application was submitted for applicant NetJets Services, Inc. and owner Columbus Regional Airport Authority across 42.48 acres at 4111 Bridgeway Ave.
Under the proposal, known as Project Ascend, the company plans a multi-phase corporate headquarters campus expansion, including commercial parking and a multi-deck parking garage standing 59.167 feet tall.
Illustrative aerial rendering of the proposed NetJets campus expansion at 4111 Bridgeway Avenue looking southeast, featuring the proposed 59-foot parking garage and office buildings BW3 and BW4.
Credit: Pique AI visualization; source: Langan Engineering and Environmental Services, LLC · Generated from retained filed drawings · Unofficial conceptual rendering — based on filed plans; proposal may change.
Unofficial conceptual rendering — based on filed plans; proposal may change.
Municipal departments reviewed the application on Thursday, Oct. 15, 2026. In staff review comments, the Planning Division is supportive of the requested variances. Planning staff noted the proposal is consistent with the Columbus Growth Strategy recommended land use of Industrial & Warehouse. City records note that legislation took effect on Wednesday, February 25th, 2026.
While planners supported the requested variances, the Department of Building and Zoning Services outlined several technical conditions the applicant must address before the proposal advances. Zoning staff advised that parking areas are not allowed to cross or be divided by parcel lines, and a variance will be required if the parcels are not combined. Zoning comments ask the applicant to clarify if the proposed parking listed in the parking requirements table is the number of spaces added by each phase or the total number of provided spaces at the end of each phase. If spaces added reach 3,105 stalls, a variance will be necessary to allow the site to exceed its maximum parking allowance.
Zoning reviewers further directed the applicant to clarify garage versus surface stall counts to determine parking lot shade tree compliance. Reviewers also instructed the development team to dimension building and parking setbacks on the site plan to determine whether additional variances are required. In addition, Phase 2 of this development should be removed from the provided site plan if it is not included as part of this variance request.
Site engineering drawings for Project Ascend at 4111 Bridgeway Ave. were prepared by Langan Engineering and Environmental Services, Inc. The drawings outline a campus layout integrating existing corporate offices with proposed new office buildings and the parking garage. In supplemental documentation, project architect Vocon noted the applicant is requesting variances for phase 1 scope only, which is entirely south of the existing intersection of Bridgeway Avenue and Goshen Road.
Following the staff review, the applicant must resolve the technical zoning conditions before the proposal proceeds to the Columbus Development Commission for a public hearing and formal recommendation. Because the project involves land use modifications not permitted under standard zoning code, final legislative approval rests with the Columbus City Council.
Video Watch video 0:38
How we know this
The sources and records behind this story, with the facts they support.
CV26-095 · Council Variance — 4111 BRIDGEWAY AVE COLUMBUS OH
Supporting evidence (1)
The City of Columbus uploaded staff review results on Oct. 26, 2026, for Council Variance application CV26-095.
Read supporting passage
Document: Staff Review Results · CV26-095 Staff Review Results.pdf · attachment 5431902 · 2026-10-26T04:00:00Z
Supporting evidence (5)
The application was submitted for applicant NetJets Services, Inc. and owner Columbus Regional Airport Authority across 42.48 acres at 4111 Bridgeway Ave.
Read supporting passage
Location: 4111 BRIDGEWAY AVE. (43219), being 42.48± acres located on the south side of Bridgeway Avenue; at the southern terminus of Goshen Lane (010-254179 and five others; No Group). Existing Zoning: R, Rural District and M, Manufacturing District. Proposed Use: Accessory parking lot. Applicant(s): NetJets Services, Inc. c/o Elizabeth A. Seedorf, Atty.; 52 East Gay Street; Columbus, OH 43215. Owner(s): Columbus Regional Airport Authority c/o Susan Salisbury; 4600 International Gateway; Columbus, OH 43219.
Municipal departments reviewed the application on Thursday, Oct. 15, 2026.
Read supporting passage
City staff reviewed the above referenced Council Variance application on Thursday, October 15, 2026
Zoning comments ask the applicant to clarify if the proposed parking listed in the parking requirements table is the number of spaces added by each phase or the total number of provided spaces at the end of each phase.
Read supporting passage
Clarify if the proposed parking listed in the parking requirements table is the number of spaces added by each phase or the total number of provided spaces at the end of each phase.
Reviewers also instructed the development team to dimension building and parking setbacks on the site plan to determine whether additional variances are required.
Read supporting passage
Label and dimension the following on the provided site plan: building setbacks, parking setbacks, and the distance from each building to all property boundaries. If any setbacks are not met, additional variances will be necessary.
In addition, Phase 2 of this development should be removed from the provided site plan if it is not included as part of this variance request.
Read supporting passage
If Phase 2 of this development is not included as part of this variance request, it should be removed from the provided site plan.
Supporting evidence (6)
In staff review comments, the Planning Division is supportive of the requested variances.
Read supporting passage
Department of Development, Planning Division has the following comments: 1.) Planning is supportive of the requested variances.
Planning staff noted the proposal is consistent with the Columbus Growth Strategy recommended land use of Industrial & Warehouse.
Read supporting passage
Staff note the proposed use is consistent with the Columbus Growth Strategy (CGS) recommended land use, Industrial & Warehouse.
City records note that legislation took effect on Wednesday, February 25th, 2026.
Read supporting passage
That legislation took effect on Wednesday, February 25th, 2026.
Zoning staff advised that parking areas are not allowed to cross or be divided by parcel lines, and a variance will be required if the parcels are not combined.
Read supporting passage
Parking areas are not allowed to cross or be divided by parcel lines, and a variance will be required if the parcels are not combined.
If spaces added reach 3,105 stalls, a variance will be necessary to allow the site to exceed its maximum parking allowance.
Read supporting passage
(total 3,105 spaces), a variance will be necessary to allow the site to exceed its maximum parking allowance.
Zoning reviewers further directed the applicant to clarify garage versus surface stall counts to determine parking lot shade tree compliance.
Read supporting passage
Clarify how many parking spaces will be provided in the proposed parking garage and how many spaces will be provided on the exterior of the site. This is necessary to confirm if parking lot shade tree requirements are being met.