Columbus Considers $481,000 Inspection Deal for Clintonville Sewer and Lead Line Projects

A proposed municipal contract modification authorizes up to $481,465.80 for DLZ Ohio, Inc. for Clintonville utility projects listed on second reading.

Clintonville

Watch the video

Curb extension bioretention rain garden filled with purple flowers and ornamental grasses along a residential street curb in Clintonville.

A Blueprint Columbus curb-extension bioretention rain garden capturing stormwater on a residential Clintonville street in Columbus, Ohio.

Credit: Coldwater Consulting, LLC Image source

A proposed municipal contract modification authorizes up to $481,465.80 for DLZ Ohio, Inc. to perform construction administration and inspection services in Clintonville. City legislative records list Ordinance 3134-2026 with a status of Second Reading for the utility projects.

The pending agreement covers professional construction oversight for two coordinated neighborhood utility initiatives: the Blueprint Milford / Summit Area Integrated Solutions Improvements and the Milford / Summit Lead Line Replacements. According to city legislative records, the neighborhood projects are designed to reduce stormwater inflow and infiltration into municipal sewers, mitigating sanitary sewer overflows into basements and waterways while upgrading storm drainage.

Angled view of Columbus City Hall with a corner stone monument sign reading 'CITY HALL 90 W. BROAD STREET COLUMBUS, OHIO' in the foreground lawn.

Columbus City Hall at Broad and Front streets in downtown Columbus, where City Council advanced the Clintonville water infrastructure measure.

Credit: General Ization / Wikimedia Commons Image source

The current addition marks Modification #4 to the contract, bringing the total across all modifications to $3,161,940.73. Under the original authorizing legislation, DLZ Ohio received a $100,000 contract that is modified across a three-year period from 2026 through 2028 as capital projects go into construction. Contract records list Smoot Construction of Ohio in Columbus, Ohio, with MBE status.

Under the ordinance, the city authorizes appropriating $361,123.49 in the Sanitary Revolving Loan Fund and $120,342.31 in the Water - Fresh Water Market Rate Loan Fund. City records state that state sewer loan funding will be obtained through a loan from the Water Pollution Control Loan Fund, jointly administered by the Ohio Environmental Protection Agency and the Ohio Water Development Authority.

Filings show that lead line replacement funding will be obtained through a loan from the OWDA Fresh Water Program, and this ordinance is contingent upon both loans being approved by the OWDA Board. In addition, legislative filings note that both loans are expected to be approved at the December OWDA Board meeting.

The legislation also resolves a state loan compliance requirement. Although City Council approved borrowing authority in March 2026 that permitted utility directors to adjust project lists administratively, state lending guidelines require an ordinance specifically demonstrating council approval for each individual undertaking. Because Milford / Summit Lead Line Replacements was not listed in that ordinance, this ordinance will request that approval.

Previously, Pique Media reported on Oct. 5 that Columbus Council weighed a $12.6M Blueprint contract for Miller Kelton pavers and waterlines, and reported on Oct. 29 that Columbus authorized a state loan pipeline for 61 sewer and stormwater projects.

Video Watch video 0:39

More on this story

Pique’s reporting on the same events, newest first.

  1. Clintonville Latest You are reading

    Columbus Considers $481,000 Inspection Deal for Clintonville Sewer and Lead Line Projects

  2. Columbus

    Columbus Authorizes State Loan Pipeline for 61 Sewer and Stormwater Projects

    City Council approved low-interest borrowing backed by planned utility rate increases while granting administrative authority to adjust the capital roster.

  3. Near East

    Columbus Council Weighs $12.6M Blueprint Contract for Miller Kelton Pavers and Waterlines

    The $12.6 million infrastructure contract would install permeable pavement, storm sewers and new waterlines to mitigate sewer overflows into Alum Creek.

How we know this

The sources and records behind this story, with the facts they support.

  1. 3134-2026 · To authorize the Director of Columbus Water and Power to enter into a planned contract modification for Construction Administration and Inspection Services with DLZ Ohio, Inc. for the Blueprint Milford / Summit Area Integrated Solutions Improvements and Milford / Summit Lead Line Replace

    columbus · legislation

    Published · Accessed

    Supporting evidence (16)
    • A proposed municipal contract modification authorizes up to $481,465.80 for DLZ Ohio, Inc. to perform construction administration and inspection services in Clintonville.

      Read supporting passage
      This modification is for DLZ Ohio, Inc. to perform construction administration/ inspection services for Blueprint Milford / Summit Area Integrated Solutions Improvements and Milford / Summit Lead Line Replacements projects, CIP 650870-110165 & 690236-110005, in an amount up to $481,465.80. The Community Area for this ordinance will be 39 - Clintonville.
    • City legislative records list Ordinance 3134-2026 with a status of Second Reading for the utility projects.

      Read supporting passage
      {Body=Public Utilities & Sustainability Committee, Content type=Legislation, Document coverage=API text and document metadata; linked PDF bytes are not retained, File=3134-2026, Legislation type=Ordinance, Municipality=columbus, Status=Second Reading, Text version=1}
    • The pending agreement covers professional construction oversight for two coordinated neighborhood utility initiatives: the Blueprint Milford / Summit Area Integrated Solutions Improvements and the Milford / Summit Lead Line Replacements.

      Read supporting passage
      This modification is for DLZ Ohio, Inc. to perform construction administration/ inspection services for Blueprint Milford / Summit Area Integrated Solutions Improvements and Milford / Summit Lead Line Replacements projects, CIP 650870-110165 & 690236-110005, in an amount up to $481,465.80.
    • According to city legislative records, the neighborhood projects are designed to reduce stormwater inflow and infiltration into municipal sewers, mitigating sanitary sewer overflows into basements and waterways while upgrading storm drainage.

      Read supporting passage
      The majority of the projects will reduce inflow and infiltration to the City’s sanitary sewer system thus mitigating sanitary sewer overflows to basements and waterways. Other projects provide improvement to existing storm infrastructure to mitigate drainage/flooding issues.
    • The current addition marks Modification #4 to the contract, bringing the total across all modifications to $3,161,940.73.

      Read supporting passage
      Modification #4: $ 481,465.80 (current) Total $3,161,940.73
    • Under the original authorizing legislation, DLZ Ohio received a $100,000 contract that is modified across a three-year period from 2026 through 2028 as capital projects go into construction.

      Read supporting passage
      Original Contract: $ 100,000.00 (ORD 0380-2026, PO557906)
    • Under the original authorizing legislation, DLZ Ohio received a $100,000 contract that is modified across a three-year period from 2026 through 2028 as capital projects go into construction.

      Read supporting passage
      DLZ Ohio, Inc. will perform construction administration/inspection services for Columbus Water and Power Capital Improvement Projects that bid during the years 2026, 2027, and 2028. The contract will be modified as needed throughout the 3-year period to include these projects as they go into construction.
    • Contract records list Smoot Construction of Ohio in Columbus, Ohio, with MBE status.

      Read supporting passage
      Smoot Construction of Ohio Columbus, Ohio MBE
    • Under the ordinance, the city authorizes appropriating $361,123.49 in the Sanitary Revolving Loan Fund and $120,342.31 in the Water - Fresh Water Market Rate Loan Fund.

      Read supporting passage
      SECTION 2. That the appropriation of $361,123.49 or so much thereof as may be needed, is hereby authorized in the Sanitary Revolving Loan Fund, Fund 6111, the appropriation of $120,342.31 or so much thereof as may be needed, is hereby authorized in the Water - Fresh Water Market Rate Loan Fund, Fund 6014, per the accounting codes in the attachment to this ordinance.
    • City records state that state sewer loan funding will be obtained through a loan from the Water Pollution Control Loan Fund, jointly administered by the Ohio Environmental Protection Agency and the Ohio Water Development Authority.

      Read supporting passage
      Funding for the Blueprint Milford / Summit Area Integrated Solutions, CIP 650870-110165, portion of this contract will be obtained through a loan from the Water Pollution Control Loan Fund (WPCLF), jointly administered by the Ohio EPA's Division of Environmental and Financial Assistance and the Ohio Water Development Authority (OWDA). City Council authorized this loan application and acceptance of funding via Ordinance 3119-2025 passed by Council on 12/15/2025.
    • Filings show that lead line replacement funding will be obtained through a loan from the OWDA Fresh Water Program, and this ordinance is contingent upon both loans being approved by the OWDA Board.

      Read supporting passage
      Funding for the Milford / Summit Lead Line improvements portion of this contract will be obtained through a loan from the OWDA Fresh Water Program (OWDA Direct).
    • Filings show that lead line replacement funding will be obtained through a loan from the OWDA Fresh Water Program, and this ordinance is contingent upon both loans being approved by the OWDA Board.

      Read supporting passage
      This ordinance is contingent upon both loans being approved by the OWDA Board.
    • In addition, legislative filings note that both loans are expected to be approved at the December OWDA Board meeting.

      Read supporting passage
      WHEREAS, both loans are expected to be approved at the December OWDA Board meeting;
    • Although City Council approved borrowing authority in March 2026 that permitted utility directors to adjust project lists administratively, state lending guidelines require an ordinance specifically demonstrating council approval for each individual undertaking.

      Read supporting passage
      City Council authorized this loan application and acceptance of funding via Ordinance 0341-2026 passed by Council on 3/2/2026. Ordinance 0341-2026 also authorized the Director of Columbus Water and Power to add to or subtract from the anticipated loans listed in that ordinance.
    • Although City Council approved borrowing authority in March 2026 that permitted utility directors to adjust project lists administratively, state lending guidelines require an ordinance specifically demonstrating council approval for each individual undertaking.

      Read supporting passage
      Even though Ordinance 0341-2026 stated projects can be added to or subtracted from the list without further City Council approval, OWDA requires an ordinance specifically listing Council’s approval for each project. This ordinance will request that approval.
    • Because Milford / Summit Lead Line Replacements was not listed in that ordinance, this ordinance will request that approval.

      Read supporting passage
      Milford / Summit Lead Line Replacements, CIP 690236-110005 was not listed in that ordinance. Even though Ordinance 0341-2026 stated projects can be added to or subtracted from the list without further City Council approval, OWDA requires an ordinance specifically listing Council’s approval for each project. This ordinance will request that approval.
  2. Columbus Council Weighs $12.6M Blueprint Contract for Miller Kelton Pavers and Waterlines

    Published · Accessed

    Supporting evidence (1)
    • Previously, Pique Media reported on Oct. 5 that Columbus Council weighed a $12.6M Blueprint contract for Miller Kelton pavers and waterlines, and reported on Oct. 29 that Columbus authorized a state loan pipeline for 61 sewer and stormwater projects.

      Read supporting passage
      Columbus Council Weighs $12.6M Blueprint Contract for Miller Kelton Pavers and Waterlines
  3. Columbus Authorizes State Loan Pipeline for 61 Sewer and Stormwater Projects

    Published · Accessed

    Supporting evidence (1)
    • Previously, Pique Media reported on Oct. 5 that Columbus Council weighed a $12.6M Blueprint contract for Miller Kelton pavers and waterlines, and reported on Oct. 29 that Columbus authorized a state loan pipeline for 61 sewer and stormwater projects.

      Read supporting passage
      Columbus Authorizes State Loan Pipeline for 61 Sewer and Stormwater Projects

Take Pique with you

Your city. In your pocket.

Read local stories, watch the videos and explore the details in Pique.

QR code for Pique Media on the App Store

Get Pique for iPhone and iPad

Scan the code with your phone’s camera.

View on the App Store

Share this story