Columbus Considers $32.2 Million Contract for Jackson Pike Clarifier Upgrades
Legislation authorizing a sole-bid award to Kenmore Construction would modernize secondary clarifier electrical systems to protect river water quality.
Columbus City Council is scheduled to hold a regular meeting on Monday, Nov. 16. Under the proposed ordinance, the Director of Columbus Water & Power is authorized to enter into a $32,165,000 construction contract with Kenmore Construction Co., Inc. for the Jackson Pike A-Plant Secondary Clarifier Electrical Upgrades project. The measure also encumbers $2,000 for prevailing wage services, bringing total municipal expenditures to $32,167,000.
Aerial view of the Jackson Pike Wastewater Treatment Plant in Columbus, Ohio, showing the facility's clarifiers, treatment basins, and administrative structures.
Credit: David E. Lucas / Wikimedia Commons Image source
The capital project upgrades electrical equipment responsible for the secondary treatment process at the plant. According to city legislative filings, the secondary process is crucial in treating wastewater and keeping rivers clean by removing biological settleable solids, and equipment failure would halt solids collection in the secondary clarifiers, causing tanks to fill and overflow untreated solids into the plant's final effluent.
Contract work will rehabilitate an outdated system and address corrosion and odor associated with current secondary treatment operations. Municipal records state construction will take approximately three years, requiring substantial completion within 1,095 calendar days and final completion within 1,125 calendar days of a notice to proceed anticipated around January 2027, setting expected completion in early 2030.
The city advertised an invitation for bids on municipal websites from Aug. 10 through Sept. 30, receiving a single bid when proposals were opened on Sept. 30. Kenmore Construction submitted a bid of $32,165,000, which evaluators deemed the lowest, best, most responsive and responsible bid. According to city filings, the company's contract compliance certification was in good standing when the bid was awarded, but the certification expired on Nov. 4. Kenmore listed three subcontractors for the project: Howard Painting, Inc. of Defiance, Claypool Electric of Lancaster, and Koehring & Sons, Inc. of Beech Grove, Indiana.
Expenditures under the legislation are contingent on loan approval from the Ohio Water Development Authority board during its December meeting. The project is planned to be financed through a reimbursement loan from the state Water Pollution Control Loan Fund, following council authorization in December 2025.
Previously, Pique Media reported on Oct. 29 that Columbus enacted legislation approving a separate $20.6 million electrical power overhaul for the Jackson Pike Wastewater Plant. An interview request has been submitted to Columbus Water & Power Director Kristen Atha regarding the procurement process and facility safeguards.
How we know this
The sources and records behind this story, with the facts they support.
Supporting evidence (10)
Under the proposed ordinance, the Director of Columbus Water & Power is authorized to enter into a $32,165,000 construction contract with Kenmore Construction Co., Inc. for the Jackson Pike A-Plant Secondary Clarifier Electrical Upgrades project.
Read supporting passage
This ordinance authorizes the Director of Columbus Water & Power to enter into a construction contract with Kenmore Construction Co., Inc., for the Jackson Pike A-Plant Secondary Clarifier Electrical Upgrades project, CIP 650245-100002, in an amount up to $32,165,000.00;
The measure also encumbers $2,000 for prevailing wage services, bringing total municipal expenditures to $32,167,000.
Read supporting passage
and to encumber funds with the Department of Public Service for prevailing wage services in an amount up to $2,000.00, for a total expenditure of $32,167,000.00.
According to city legislative filings, the secondary process is crucial in treating wastewater and keeping rivers clean by removing biological settleable solids, and equipment failure would halt solids collection in the secondary clarifiers, causing tanks to fill and overflow untreated solids into the plant's final effluent.
Read supporting passage
The Secondary process is a crucial process in treating wastewater and keeping our community and rivers clean. This process is one of the final steps in the treatment process for the wet stream and removes biological settle-able solids to reduce harmful parameters in the plants final effluent. Failure of this equipment would cease collection of the settle-able solids in the secondary clarifiers, which would then fill with solids that would overflow from the secondary tanks and eventually end up in the effluent, ultimately resulting in a violation and potential hazards.
Contract work will rehabilitate an outdated system and address corrosion and odor associated with current secondary treatment operations.
Read supporting passage
This project will include improvements that will help address corrosion and odor associated with the current process, as well as upgrade equipment and overall rehabilitate an outdated system.
Municipal records state construction will take approximately three years, requiring substantial completion within 1,095 calendar days and final completion within 1,125 calendar days of a notice to proceed anticipated around January 2027, setting expected completion in early 2030.
Read supporting passage
TIMELINE: All work shall be substantially complete within 1095 calendar days of Notice to Proceed, with final completion to occur within 1125 calendar days. The City anticipates issuing a Notice to Proceed on or about January 2027.
The city advertised an invitation for bids on municipal websites from Aug. 10 through Sept. 30, receiving a single bid when proposals were opened on Sept. 30.
Read supporting passage
An Invitation for Bids for the Jackson Pike A-Plant Secondary Clarifier Electrical Upgrades project was advertised on the Vendor Services and Bid Express websites from August 10, 2026, through September 30, 2026. One bid was received for the project and opened on September 30, 2026.
Kenmore Construction submitted a bid of $32,165,000, which evaluators deemed the lowest, best, most responsive and responsible bid.
Read supporting passage
The following company submitted a bid: Name Bid Amount CC Number Exp. Date Status Kenmore Construction Co., Inc. $32,165,000.00 CC006456 11/4/2026 MAJ Kenmore Construction Co., Inc.’s bid was deemed the lowest, best, most responsive and responsible bid in the amount of $32,165,000.00.
According to city filings, the company's contract compliance certification was in good standing when the bid was awarded, but the certification expired on Nov. 4.
Read supporting passage
The certification of Kenmore Construction Co., Inc. was in good standing at the time the bid was awarded. 4. CONTRACT COMPLIANCE INFORMATION Kenmore Construction Co., Inc.’s contract compliance number is CC006456 and expires 11/4/2026.
Kenmore listed three subcontractors for the project: Howard Painting, Inc. of Defiance, Claypool Electric of Lancaster, and Koehring & Sons, Inc. of Beech Grove, Indiana.
Read supporting passage
Kenmore Construction Co., Inc. listed the following companies as subcontractors for this project: Company Name City/State ODI Certification Status Howard Painting, Inc. Defiance, Ohio MAJ Claypool Electric Lancaster, Ohio WBE Koehring & Sons, Inc Beech Grove, Indiana MAJ
Expenditures under the legislation are contingent on loan approval from the Ohio Water Development Authority board during its December meeting.
Read supporting passage
City Council authorized this loan application and acceptance of funding via Ordinance 3119-2025, passed by Council on 12/15/25. This loan is expected to be approved at the OWDA December Board meeting. This ordinance is contingent upon the loan being approved by OWDA.
Columbus Enacts $20.6 Million Electrical Overhaul for Jackson Pike Wastewater Plant
Supporting evidence (1)
Previously, Pique Media reported on Oct. 29 that Columbus enacted legislation approving a separate $20.6 million electrical power overhaul for the Jackson Pike Wastewater Plant.
Read supporting passage
Columbus Enacts $20.6 Million Electrical Overhaul for Jackson Pike Wastewater Plant