New Albany Considers $1.8 Million Early Start on Bevelhymer Park Pickleball Improvements
City Council will consider an early notice to proceed up to $1.8 million for pickleball restrooms and shade structures ahead of a master contract amendment.
New Albany City Council has scheduled a meeting for Tuesday, Dec. 1, at Village Hall.
The legislation, designated as Resolution R-59-2026, would authorize the city manager to execute a limited notice to proceed with Messer Construction Co. for pickleball restrooms, shade structures, and associated site improvements at Bevelhymer Park.
Under the proposed measure, the total authorization for the early work package cannot exceed $1.8 million, inclusive of a separate, city-controlled owner's contingency.
Pickleball players compete on outdoor courts at the Bevelhymer Park pickleball complex in New Albany, Ohio.
Credit: New Albany Parks & Recreation Image source
Cost breakdown and court amenities
Messer Construction Co.'s estimate of total charges for the limited work is an allowance of $1,797,953.
The budget exhibits include an $800,000 shade allowance for pickleball court shades. The bid categories allocate $143,400 for plumbing.
Site preparation and underground utility connections are budgeted at $135,000. Messer's trade estimates also allocate $90,100 for framing and $82,712 for masonry, along with $63,208 for electrical work, $40,000 for heating and ventilation, $32,200 for metal roofing, and a $35,000 allowance for winter conditions.
Additional line items in the trade package include $26,000 for general trades and $19,688 for general requirements.
The proposal also lists $89,757 for staff general conditions, a 2.75% construction manager fee of $48,120, and paired 3% allocations of $52,495 each for construction and owner contingencies.
Bridge to broader park contract
The city desires to authorize the work through a limited notice to proceed while final terms are finalized for Guaranteed Maximum Price Amendment No. 2.
Council previously approved Resolution R-11-2026 authorizing a construction management contract with Messer Construction Co. for the Bevelhymer Facilities Improvements Project.
The agreement provides for preliminary services and phased construction through Guaranteed Maximum Price amendments or prior written authorization for specified work.
According to the resolution, the work and costs authorized under the limited notice to proceed shall be folded into the master contract amendment, subject to separate council approval, without duplication of costs or payments.
The agreement authorizes Messer to perform the limited work upon execution by both parties and continuing through June 2027. Under the agreement terms, the city acknowledges that if the work cannot be completed by the end of June 2027 and the notice to proceed expires without extension or replacement, the project would pause unfinished.
Construction schedule and milestones
Project schedules list the bidding window from Oct. 26 to Nov. 13 for Bid Package #2, followed by bid review and award from Nov. 16 to Nov. 27.
The schedule allots a 15-day period from Nov. 30 through Dec. 18 for legislative authorization of the limited notice to proceed.
The project schedule sets mobilization and fencing from Dec. 21 to Jan. 15, 2027. Work on site utilities under the limited notice to proceed is scheduled from Dec. 28 through Jan. 8, 2027.
According to the schedule, crews are slated for foundations and masonry walls from Jan. 11 to Jan. 29, 2027, followed by roof trusses, metal roofing, and siding in February.
Subsequent stages include mechanical rough-ins and interior finishes in March, hardscape and final inspections in April and May, and closeout and punch list work through June 4, 2027.
Video Watch video 0:39
Pique’s reporting on the same events, newest first.
New Albany Latest You are reading
New Albany Considers $1.8 Million Early Start on Bevelhymer Park Pickleball Improvements
New Albany
New Albany Council Schedules Hearing on Johnstown Road Land Donation for Park Expansion
A proposed agreement with The New Albany Company would add Johnstown Road acreage to a planned municipal park while relocating school bus parking.
New Albany
New Albany schedules hearing on police tactical facility at Bevelhymer campus
Council is scheduled to consider a contract amendment authorizing up to $10.3 million with Messer Construction Co. for the facility.
How we know this
The sources and records behind this story, with the facts they support.
City Council · 2026-12-01 · agenda
Supporting evidence (2)
New Albany City Council has scheduled a meeting for Tuesday, Dec. 1, at Village Hall.
Read supporting passage
COUNCIL MEETING AGENDA Tuesday, December 1, 2026 6:30 p.m. Village Hall, 99 W. Main Street, New Albany, Ohio 43054
The legislation, designated as Resolution R-59-2026, would authorize the city manager to execute a limited notice to proceed with Messer Construction Co. for pickleball restrooms, shade structures, and associated site improvements at Bevelhymer Park.
Read supporting passage
RESOLUTION R-59-2026 A RESOLUTION TO AUTHORIZE THE CITY MANAGER TO EXECUTE A LIMITED NOTICE TO PROCEED WITH MESSER CONSTRUCTION CO. FOR THE PICKLEBALL RESTROOM, SHADE STRUCTURES, AND ASSOCIATED SITE IMPROVEMENTS PORTION OF THE BEVELHYMER FACILITIES IMPROVEMENTS PROJECT
Supporting evidence (5)
Under the proposed measure, the total authorization for the early work package cannot exceed $1.8 million, inclusive of a separate, city-controlled owner's contingency.
Read supporting passage
The total authorization shall not exceed $1,800,000, inclusive of a separate, city-controlled owner's contingency.
The city desires to authorize the work through a limited notice to proceed while final terms are finalized for Guaranteed Maximum Price Amendment No. 2.
Read supporting passage
WHEREAS, the city desires to authorize specified work for the pickleball restroom, shade structures, and associated site improvements through a Limited Notice to Proceed while Guaranteed Maximum Price Amendment No. 2 is finalized; and
Council previously approved Resolution R-11-2026 authorizing a construction management contract with Messer Construction Co. for the Bevelhymer Facilities Improvements Project.
Read supporting passage
WHEREAS, council approved Resolution R-11-2026 authorizing the city manager to enter into a Construction Manager at Risk contract with Messer Construction Co. for the New Albany Bevelhymer Facilities Improvements Project; and
The agreement provides for preliminary services and phased construction through Guaranteed Maximum Price amendments or prior written authorization for specified work.
Read supporting passage
WHEREAS, the city and Messer Construction Co. have entered into an agreement providing for pre- construction services and the subsequent authorization of construction through Guaranteed Maximum Price amendments or prior written authorization for specified work; and
According to the resolution, the work and costs authorized under the limited notice to proceed shall be folded into the master contract amendment, subject to separate council approval, without duplication of costs or payments.
Read supporting passage
The work and costs authorized under the Limited Notice to Proceed shall be incorporated into Guaranteed Maximum Price Amendment No. 2, subject to separate council approval, without duplication of costs or payments.
Supporting evidence (3)
s estimate of total charges for the limited work is an allowance of $1,797,953.
Read supporting passage
Construction Manager’s estimate of the total charges to the Owner for the Limited Work that Construction Manager expects to be able to accomplish under this Limited Notice to Proceed No. 1, is an allowance of $1,797,953.
The agreement authorizes Messer to perform the limited work upon execution by both parties and continuing through June 2027.
Read supporting passage
Owner hereby authorizes Construction Manager to proceed with performance of the Limited Work upon execution of this Limited Notice to Proceed #1 by both parties and continuing through June, 2027.
Under the agreement terms, the city acknowledges that if the work cannot be completed by the end of June 2027 and the notice to proceed expires without extension or replacement, the project would pause unfinished.
Read supporting passage
Owner acknowledges that if the Limited Work cannot be completed by the end of June, 2027, and if this Limited Notice to Proceed expires without being extended or replaced by agreements for the completion of the Limited Work, the Limited Work will be left in an incomplete state.
Supporting evidence (6)
The budget exhibits include an $800,000 shade allowance for pickleball court shades.
Read supporting passage
Allowance - Pickle Ball Court Shades | $ | 800,000
The bid categories allocate $143,400 for plumbing.
Read supporting passage
Bid Categories and Allowances BP#2 BC-00 General Requirements | $ | 19,688 BP#2 BC-01 General Trades | $ | 26,000 BP#2 BC-02 Site Work and Utilities | $ | 135,000 BP#2 BC-03 Building Concrete | $ | 34,000 BP#2 BC-04 Masonry | $ | 82,712 BP#2 BC-05 Framing | $ | 90,100 BP#2 BC-06 Metal Roofs | $ | 32,200 BP#2 BC-07 Painting | $ | 6,185 BP#2 BC-08 Plumbing | $ | 143,400
Site preparation and underground utility connections are budgeted at $135,000.
Read supporting passage
BP#2 BC-02 Site Work and Utilities | $ | 135,000
Messer's trade estimates also allocate $90,100 for framing and $82,712 for masonry, along with $63,208 for electrical work, $40,000 for heating and ventilation, $32,200 for metal roofing, and a $35,000 allowance for winter conditions.
Read supporting passage
BP#2 BC-04 Masonry | $ | 82,712 BP#2 BC-05 Framing | $ | 90,100 BP#2 BC-06 Metal Roofs | $ | 32,200 BP#2 BC-07 Painting | $ | 6,185 BP#2 BC-08 Plumbing | $ | 143,400 BP#2 BC-09 HVAC | $ | 40,000 BP#2 BC-10 Electrical | $ | 63,208 --- | --- | --- Allowance - Pickle Ball Court Shades | $ | 800,000 Allowance - Winter Conditions | $ | 35,000
Additional line items in the trade package include $26,000 for general trades and $19,688 for general requirements.
Read supporting passage
BP#2 BC-00 General Requirements | $ | 19,688 BP#2 BC-01 General Trades | $ | 26,000
The proposal also lists $89,757 for staff general conditions, a 2.75% construction manager fee of $48,120, and paired 3% allocations of $52,495 each for construction and owner contingencies.
Read supporting passage
General Conditions (CM Staff) | $ | 89,757 General Liability Insurance (0.649%) | $ | 11,669 Subcontractor Default Insurance (SDI) (1.26%) | $ | 18,746 Builder's Risk Insurance (0.0625% of contract value per year) | $ | 1,125 Payment & Performance Bonds (0.6%) | $ | 10,788 Corporate Activity Tax (CAT) (0.26%) | $ | 4,675 Carrying Charge (3% of GRs) | $ | 591 Construction Contingency (3%) | $ | 52,495 Owner Contingency (3%) | $ | 52,495 CM Fee (2.75%) | $ | 48,120
Supporting evidence (6)
Project schedules list the bidding window from Oct. 26 to Nov. 13 for Bid Package #2, followed by bid review and award from Nov. 16 to Nov. 27.
Read supporting passage
260 | Bid Package #2 Bid Period | 15 | 10/26/26 | 11/13/26 | Bid Package #2 Bid Period 270 | Bid Package #2 Bid Review & Award | 10 | 11/16/26 | 11/27/26 | Bid Package #2 Bid Review & Award
The schedule allots a 15-day period from Nov. 30 through Dec. 18 for legislative authorization of the limited notice to proceed.
Read supporting passage
280 | LNTP Approval | 15 | 11/30/26 | 12/18/26 | LNTP Approval
The project schedule sets mobilization and fencing from Dec. 21 to Jan. 15, 2027.
Read supporting passage
70 | Mobilization & Fencing | 20 | 12/21/26 | 01/15/27 | Mobilization & Fencing
Work on site utilities under the limited notice to proceed is scheduled from Dec. 28 through Jan. 8, 2027.
Read supporting passage
101 | Site Utilities - LNTP | 10 | 12/28/26 | 01/08/27 | Site Utilities - LNTP
According to the schedule, crews are slated for foundations and masonry walls from Jan. 11 to Jan. 29, 2027, followed by roof trusses, metal roofing, and siding in February.
Read supporting passage
105 | Foundations, Masonry Walls, and SOG | 15 | 01/11/27 | 01/29/27 | Foundations, Masonry Walls, and SOG 107 | Roof Trusses, Metal Roof, and Hardie Plank | 20 | 02/01/27 | 02/26/27 | Roof Trusses, Metal Roof, and Hardie Plank
Subsequent stages include mechanical rough-ins and interior finishes in March, hardscape and final inspections in April and May, and closeout and punch list work through June 4, 2027.
Read supporting passage
108 | MEP Rough-In | 10 | 03/01/27 | 03/12/27 | MEP Rough-In 109 | Interior Finishes | 15 | 03/15/27 | 04/02/27 | Interior Finishes 115 | Final Grading | 5 | 04/05/27 | 04/09/27 | Final Grading 117 | Hardscape and Landscape | 15 | 04/12/27 | 04/30/27 | Hardscape and Landscape 118 | Final Inspections | 5 | 05/03/27 | 05/07/27 | Final Inspections 119 | Closeout & Punch List | 20 | 05/10/27 | 06/04/27 | Closeout & Punch List