Delaware County approves road funding pact for Olentangy Hyatts High School
Delaware County commissioners approved an agreement with two townships and the Olentangy school district to widen Bunty Station Road for a new high school campus.
On Nov. 2, 2026, the Delaware County Board of Commissioners approved a cooperative project agreement with Liberty Township, Delaware Township, and the Board of Education of the Olentangy Local School District. The commissioners approved the agreement on a 3-0 vote. Under the project plans, the roadway work includes the widening and reconstruction of Bunty Station Road.
According to the agreement, the school district plans to construct a new high school at 2080 Bunty Station Road. Under the agreement, the parties seek to improve the safety and convenience of the traveling public by widening Bunty Station Road for turn lanes and other ancillary roadway and drainage improvements.
Aerial architectural site rendering of the campus layout for Olentangy Hyatts High School on Bunty Station Road.
Credit: Olentangy Local Schools / The Columbus Dispatch via Yahoo News · Illustration Image source
Illustrative rendering
Infrastructure funding and cost-sharing caps
The roadway work will follow county project plans that define the scope as the widening and reconstruction of Bunty Station Road. For construction, the agreement lists an application estimate of $2.5 million and a maximum participation amount of $3 million.
Liberty Township will serve as the project sponsor and applicant for state capital or transportation grants through the Ohio Public Works Commission to pay for up to $600,000 of construction costs. In the project financing schedule, the state grant is estimated at 22 percent of construction costs.
Under the agreement's cost schedule, Liberty and Delaware townships each take a 2 percent participation rate, with each township's share estimated at $50,000 and capped at a maximum of $50,000. Through its Roadway Grant Assistance Program, Delaware County will provide three dollars for each dollar paid by each township, up to a maximum contribution of $150,000 per township.
The Olentangy Local School District is responsible for design engineering and construction plans through an engineering consultant. The school district is also responsible for Right of Way Acquisition and Utility Relocation, with a maximum participation amount of $500,000.
The school district agreed to reimburse remaining construction costs after deducting costs paid by the other parties and grant funds obtained for the project. In the agreement's cost table, the school district has a 62 percent participation rate, with an application estimate of $1.5 million and a maximum participation amount of $2 million.
The county agreed to advertise and award a construction contract for the project. The county also agreed to provide and pay all costs associated with construction engineering, contract management and testing.
All commitments in the pact are contingent on securing the state public works grant and receiving a construction bid below $3 million. If either condition is not met on or before Sept. 1, 2028, the agreement becomes null and void.
Campus timeline and enrollment pressures
District leaders held a groundbreaking ceremony on June 1, 2026, for the high school on about 140 acres along the north side of Bunty Station Road. Delaware City Council unanimously approved annexing the site from Delaware Township on June 8, 2026.
The high school project is budgeted to cost $148 million. The Olentangy Local school board voted at an Oct. 8 meeting to select Olentangy Hyatts High School as the official designation for the campus. Construction began over the summer of 2026, and the building is scheduled to open in fall 2028.
The campus is intended to ease capacity constraints across the fast-growing district. Olentangy enrollment reached 24,568 students for the 2026–2027 school year, up 159 students from September 2025, and district planners project adding more than 2,000 students over the next decade. District records show middle schools are already operating at 104 percent capacity with enrollment growing.
District planners estimate that redistricting will impact approximately 12 percent of the district's K-12 enrollment. The district scheduled the announcement of the new boundaries at the Dec. 10 Board of Education meeting.
Previously, Pique Media reported on Delaware officials preparing to weigh an impact fee agreement for the high school and the district opening public forums on attendance boundary options.
Pique’s reporting on the same events, newest first.
Delaware Latest You are reading
Delaware County approves road funding pact for Olentangy Hyatts High School
Delaware
Olentangy Local Schools opens public forums on attendance boundary options
The district is gathering public feedback on three boundary scenarios to balance student enrollment before two new school facilities open.
Delaware
Delaware to weigh impact fee agreement for Olentangy Hyatts High School
Delaware City Council is scheduled to consider a conditional payment and security agreement for the $148 million campus along Sawmill Parkway.
How we know this
The sources and records behind this story, with the facts they support.
Board of Commissioners · 2026-11-02 · outcome
Supporting evidence (18)
On Nov. 2, 2026, the Delaware County Board of Commissioners approved a cooperative project agreement with Liberty Township, Delaware Township, and the Board of Education of the Olentangy Local School District.
Read supporting passage
MINUTES FROM REGULAR MEETING HELD NOVEMBER 2, 2026 694 Vote on Motion Mr. Merrell aye Mrs. Lewis aye Mr. Benton aye 11 RESOLUTION NO. 26-836 IN THE MATTER OF APPROVING A COOPERATIVE PROJECT AGREEMENT BETWEEN DELAWARE COUNTY, LIBERTY TOWNSHIP, DELAWARE TOWNSHIP, AND THE BOARD OF EDUCATION OF THE OLENTANGY LOCAL SCHOOL DISTRICT FOR THE PROJECT KNOWN AS BUNTY STATION ROAD IMPROVEMENTS 2026:
The commissioners approved the agreement on a 3-0 vote.
Read supporting passage
Vote on Motion Mr. Benton aye Mr. Merrell aye Mrs. Lewis aye
Under the project plans, the roadway work includes the widening and reconstruction of Bunty Station Road.
Read supporting passage
1.1 Project Definition. The “Project” shall include the roadway infrastructure improvements in general conformance with plans entitled Bunty Station Road Improvements 2026 (“Project Plans”) which include widening and reconstruction of Bunty Station Road.
According to the agreement, the school district plans to construct a new high school at 2080 Bunty Station Road.
Read supporting passage
WHEREAS, the Olentangy Local School District (OLSD) plans to construct a new high school (High School #5) located at 2080 Bunty Station Road; and
Under the agreement, the parties seek to improve the safety and convenience of the traveling public by widening Bunty Station Road for turn lanes and other ancillary roadway and drainage improvements.
Read supporting passage
WHEREAS, the Parties seek to jointly improve Bunty Station Road (Township Road 141) for the purpose of improving the safety and convenience of the traveling public by widening the road for turn lanes and other ancillary roadway and drainage improvements; and
The roadway work will follow county project plans that define the scope as the widening and reconstruction of Bunty Station Road.
Read supporting passage
1.1 Project Definition. The “Project” shall include the roadway infrastructure improvements in general conformance with plans entitled Bunty Station Road Improvements 2026 (“Project Plans”) which include widening and reconstruction of Bunty Station Road.
For construction, the agreement lists an application estimate of $2.5 million and a maximum participation amount of $3 million.
Read supporting passage
Participation Rate OPWC Application Estimate ($) Maximum Participation Amount ($) [b] Design Engineering 100% [a] [a] OLSD 100% [a] [a] Right of Way Acquisition and Utility Relocation 100% [a] 500,000 OLSD 100% [a] 500,000 Page 9 PAGE COMMISSIONERS JOURNAL NO. 84 - DELAWARE COUNTY MINUTES FROM REGULAR MEETING HELD NOVEMBER 2, 2026 697 Construction 100% 2,500,000 3,000,000
Liberty Township will serve as the project sponsor and applicant for state capital or transportation grants through the Ohio Public Works Commission to pay for up to $600,000 of construction costs.
Read supporting passage
2.1 OPWC Application. Liberty Township shall serve as the project sponsor and applicant for State Capital Improvement Program (SCIP) and/or Local Transportation Improvement Program (LTIP) grants through the Ohio Public Works Commission (OPWC) to pay for up to $600,000.00 of construction costs of the Project.
In the project financing schedule, the state grant is estimated at 22 percent of construction costs.
Read supporting passage
OPWC 22% 600,000 600,000
Under the agreement's cost schedule, Liberty and Delaware townships each take a 2 percent participation rate, with each township's share estimated at $50,000 and capped at a maximum of $50,000.
Read supporting passage
Liberty Township 2% 50,000 50,000 Delaware Township 2% 50,000 50,000
Through its Roadway Grant Assistance Program, Delaware County will provide three dollars for each dollar paid by each township, up to a maximum contribution of $150,000 per township.
Read supporting passage
5.4 Roadway Grant Assistance Program. The County, in accordance with its Roadway Grant Assistance Program (RGAP), shall provide funding equal to Three Dollars ($3) for each One Dollar ($1) paid by Liberty Township and Three Dollars ($3) for each One Dollar ($1) paid by Delaware Township, up to a maximum of One Hundred Fifty Thousand Dollars ($150,000) per township for this Project.
The Olentangy Local School District is responsible for design engineering and construction plans through an engineering consultant.
Read supporting passage
4.1 Right of Way and Construction Plans; Additional Services. OLSD shall provide, through a competent engineering and land surveying consultant, construction plans for the construction of the Project, and right of way plans for the acquisition of the necessary rights of way to construct and maintain the Project.
The school district is also responsible for Right of Way Acquisition and Utility Relocation, with a maximum participation amount of $500,000.
Read supporting passage
Right of Way Acquisition and Utility Relocation 100% [a] 500,000 OLSD 100% [a] 500,000
The school district agreed to reimburse remaining construction costs after deducting costs paid by the other parties and grant funds obtained for the project.
Read supporting passage
4.4 Payment of Construction Costs Remaining After Contribution of Other Parties. OLSD shall reimburse the County for any remaining Project construction costs, except for construction engineering and testing services which shall be paid by the County, after deducting costs paid by the other Parties as specified herein, and after deducting any grant funds obtained for the Project paid or credited.
In the agreement's cost table, the school district has a 62 percent participation rate, with an application estimate of $1.5 million and a maximum participation amount of $2 million.
Read supporting passage
Participation Rate OPWC Application Estimate ($) Maximum Participation Amount ($) [b] Design Engineering 100% [a] [a] OLSD 100% [a] [a] Right of Way Acquisition and Utility Relocation 100% [a] 500,000 OLSD 100% [a] 500,000 Page 9 PAGE COMMISSIONERS JOURNAL NO. 84 - DELAWARE COUNTY MINUTES FROM REGULAR MEETING HELD NOVEMBER 2, 2026 697 Construction 100% 2,500,000 3,000,000 OPWC 22% 600,000 600,000 Liberty Township 2% 50,000 50,000 Delaware Township 2% 50,000 50,000 Del. Co. RGAP (Liberty) 6% 150,000 150,000 Del. Co. RGAP (Delaware) 6% 150,000 150,000 Delaware County 0% 0 0 OLSD 62% 1,500,000 2,000,000
The county agreed to advertise and award a construction contract for the project.
Read supporting passage
5.2 Construction Contract. The County shall advertise and award a construction contract in accordance with governing Ohio Law for the Project and pay all costs associated with the construction contract, subject to reimbursement by the other Parties in accordance with Section 2.3, Section 3.1 and Article 4.
The county also agreed to provide and pay all costs associated with construction engineering, contract management and testing.
Read supporting passage
5.3 Construction Engineering. The County, acting by and through the County Engineer, shall provide and pay all costs associated with construction engineering, contract management and testing for the Project.
All commitments in the pact are contingent on securing the state public works grant and receiving a construction bid below $3 million.
Read supporting passage
7.1 Agreement Contingencies. This agreement, and all obligations stated herein, shall be contingent upon successful award of the OPWC grant and execution of the grant agreement referred to in Section 2.2, and a lowest and best bid received by the County Engineer for construction of the Project of less than Three Million Dollars ($3,000,000). This Agreement shall become null and void upon the failure to meet any of the contingences stated in this section on or before September 1, 2028.
Delaware to weigh impact fee agreement for Olentangy Hyatts High School
Supporting evidence (8)
District leaders held a groundbreaking ceremony on June 1, 2026, for the high school on about 140 acres along the north side of Bunty Station Road.
Read supporting passage
District leaders, board members and local officials held a groundbreaking ceremony on June 1 on about 140 acres along the north side of Bunty Station Road and west of Sawmill Parkway. Delaware City Council unanimously approved the site's annexation from Delaware Township during a June 8 meeting, granting it as an emergency measure so the district could proceed with construction.
Delaware City Council unanimously approved annexing the site from Delaware Township on June 8, 2026.
Read supporting passage
District leaders, board members and local officials held a groundbreaking ceremony on June 1 on about 140 acres along the north side of Bunty Station Road and west of Sawmill Parkway. Delaware City Council unanimously approved the site's annexation from Delaware Township during a June 8 meeting, granting it as an emergency measure so the district could proceed with construction.
The high school project is budgeted to cost $148 million.
The Olentangy Local school board voted at an Oct. 8 meeting to select Olentangy Hyatts High School as the official designation for the campus.
Read supporting passage
The Olentangy Local school board approved the name at an Oct. 8 meeting, selecting Olentangy Hyatts High School as the official designation for the campus.
Construction began over the summer of 2026, and the building is scheduled to open in fall 2028.
Read supporting passage
Construction on Hyatts High School began over the summer, and the building will open in fall 2028.
Olentangy enrollment reached 24,568 students for the 2026–2027 school year, up 159 students from September 2025, and district planners project adding more than 2,000 students over the next decade.
Read supporting passage
Olentangy's official enrollment reached 24,568 PK-12 students for the 2026–2027 academic year, representing an increase of 159 students over September 2025. District facilities planners project that Olentangy will add more than 2,000 students over the next ten years based on building permits, housing yields and grade advancement data.
District records show middle schools are already operating at 104 percent capacity with enrollment growing.
Read supporting passage
District middle schools are already operating at 104% capacity with enrollment growing, while elementary schools are projected to reach 100% capacity by the 2034–2035 school year even with Deer Haven open.
Previously, Pique Media reported on Delaware officials preparing to weigh an impact fee agreement for the high school and the district opening public forums on attendance boundary options.
Read supporting passage
Delaware to weigh impact fee agreement for Olentangy Hyatts High School
Olentangy Local Schools opens public forums on attendance boundary options
Supporting evidence (3)
District planners estimate that redistricting will impact approximately 12 percent of the district's K-12 enrollment.
The district scheduled the announcement of the new boundaries at the Dec. 10 Board of Education meeting.
Previously, Pique Media reported on Delaware officials preparing to weigh an impact fee agreement for the high school and the district opening public forums on attendance boundary options.
Read supporting passage
Olentangy Local Schools opens public forums on attendance boundary options