Columbus council authorizes $156,213 utility billing contract expansion through 2028
The emergency measure brings total costs for Columbus Water & Power's billing overhaul to $4.24 million as the city replaces legacy systems.
Columbus City Council meets in session inside City Council Chambers at Columbus City Hall.
Credit: WOSU Public Media Image source
Columbus City Council legislation authorizes a contract modification with Oracle America, Inc., adding $156,213 in licensing and cloud service fees through March 31, 2028.
The measure approved by City Council adds funding for Columbus Water & Power's customer information and integrated systems replacement project, bringing total contract funding to $4.24 million. The ordinance was declared an emergency measure because city officials requested emergency action to promptly execute the order and provide accelerated access to training subscriptions to prevent project disruptions.
Previously, Pique Media reported on council holding first reading on a one-year utility billing extension after a system delay.
Columbus Water & Power is in the process of replacing its current customer information systems platform, the Columbus Utility Billing System, also known as CUBS. The department is also replacing Hansen Banner software after finding it challenging to manage the lifecycle of meters across two separate systems. The city decided to consolidate operations by utilizing the entire Oracle Customer Cloud Service solution, including reporting and analytics tools.
The utility department is also replacing its mobile dispatching system, CGI's PragmaCAD, with Oracle Field Service. Columbus Water & Power initially deployed Oracle Customer Cloud Service in 2022 to manage meter data for the city's Enhanced Metering Project. Managing meters across two separate software platforms required numerous custom integrations to sync meter data between Oracle and Hansen Banner.
A residential water meter in Columbus, Ohio, installed as part of the city's Enhanced Meter Project.
Credit: WSYX / ABC 6 News Image source
The newly authorized modification funds additional threads and a training subscription, which city records describe as critical for upcoming testing and operational readiness. City officials noted that following Phase 1 implementation of the customer information system, the project team identified a significant volume of post-go-live optimization activities, including defect resolution, system enhancements and user-requested refinements. To support that work while maintaining system stability, earlier contract legislation authorized additional non-production environments to separate enhancement activities from production support and defect resolution.
The city originally authorized the contract from April 1, 2024 through Oct. 19, 2025, for $1.59 million. Council later approved a modification that combined department Oracle licenses held by the Division of Water and the Director's Office and extended the agreement through March 31, 2027.
Funding for the modification is split among four utility operating accounts covering electricity, water, sanitary sewer and stormwater services. City records show the department spent $299,695 under the contract in 2024 and $1.93 million in 2025.
Pique’s reporting on the same events, newest first.
Columbus Latest You are reading
Columbus council authorizes $156,213 utility billing contract expansion through 2028
Columbus
Columbus council holds first reading on one-year utility billing extension after system delay
A billing system delay is pushing Columbus Water & Power's transition to a new vendor into later in 2027, prompting a proposed bridge extension with Level One LLC through Jan. 31, 2028.
How we know this
The sources and records behind this story, with the facts they support.
Supporting evidence (21)
Columbus City Council legislation authorizes a contract modification with Oracle America, Inc., adding $156,213 in licensing and cloud service fees through March 31, 2028.
Read supporting passage
3010-2026 · To authorize the Director of Columbus Water & Power to modify the contract with Oracle America, Inc. for licensing and cloud service fees for the Department’s Customer Information Systems (CIS) and Integrated Systems Replacement Project; to authorize the transfer of $156,213.45 from within the Electricity, Water, Sanitary Sewer, and Stormwater Operating Funds; to authorize the expenditure of $156,213.45 split between the Electricity, Water, Sanitary Sewer, and Stormwater Operating Funds, and to declare an emergency. ($156,213.45)
Columbus City Council legislation authorizes a contract modification with Oracle America, Inc., adding $156,213 in licensing and cloud service fees through March 31, 2028.
Read supporting passage
SECTION 1. That the Director of Columbus Water & Power be and is hereby authorized to modify an existing agreement with Oracle America, Inc. for licensing and cloud service fees for the Department’s Customer Information Systems (CIS) and Integrated Systems Replacement Project and the Enhanced Meter Project up to and including March 31st, 2028. The modification amount being authorized by this ordinance is $156,213.45.
The measure approved by City Council adds funding for Columbus Water & Power's customer information and integrated systems replacement project, bringing total contract funding to $4.24 million.
Read supporting passage
BE IT ORDAINED BY THE COUNCIL OF THE CITY OF COLUMBUS:
The measure approved by City Council adds funding for Columbus Water & Power's customer information and integrated systems replacement project, bringing total contract funding to $4.24 million.
Read supporting passage
1. Amount of additional funds: The total amount of additional funds needed for this contract modification #4 is $156,213.45. Total contract amount including this modification is $4,240,764.17.
The ordinance was declared an emergency measure because city officials requested emergency action to promptly execute the order and provide accelerated access to training subscriptions to prevent project disruptions.
Read supporting passage
SECTION 7. That for the reasons stated in the preamble hereto, which is hereby made a part hereof, this ordinance is hereby declared to be an emergency measure and shall take effect and be in force from and after its passage and approval by the Mayor, or ten days after passage if the Mayor neither approves nor vetoes the same.
The ordinance was declared an emergency measure because city officials requested emergency action to promptly execute the order and provide accelerated access to training subscriptions to prevent project disruptions.
Read supporting passage
Emergency Justification: Emergency action is requested to ensure that CWP can promptly execute the required order associated with streamlining and combining our Oracle service systems into one unified platform to support the CUBE project. It is necessary to prevent disruption to project activities that rely on these expanded resources and will provide accelerated access to the learning and training subscriptions which are critical in preparing CWP for the upcoming implementation, testing, and operational readiness activities.
Columbus Water & Power is in the process of replacing its current customer information systems platform, the Columbus Utility Billing System, also known as CUBS.
Read supporting passage
Columbus Water and Power (CWP) is in the process of replacing its current customer information systems platform, the Columbus Utility Billing System, also known as CUBS.
The department is also replacing Hansen Banner software after finding it challenging to manage the lifecycle of meters across two separate systems.
Read supporting passage
Numerous custom integrations were created to sync meter data between Oracle’s CCS and Hansen Banner. It is challenging to manage the lifecycle of meters with two separate systems. Since CWP was already using Oracle CCS for meter data management and analyzed the functionality of the Customer Information Systems (CIS) side of Oracle CCS, CWP decided to utilize the entire Oracle CCS solution, including Oracle Reporting and Analytics tools. The merging of these systems into one platform reduced system complexity, increased data and billing accuracy, and made it easier for CWP to support the system into the future.
The city decided to consolidate operations by utilizing the entire Oracle Customer Cloud Service solution, including reporting and analytics tools.
Read supporting passage
Numerous custom integrations were created to sync meter data between Oracle’s CCS and Hansen Banner. It is challenging to manage the lifecycle of meters with two separate systems. Since CWP was already using Oracle CCS for meter data management and analyzed the functionality of the Customer Information Systems (CIS) side of Oracle CCS, CWP decided to utilize the entire Oracle CCS solution, including Oracle Reporting and Analytics tools. The merging of these systems into one platform reduced system complexity, increased data and billing accuracy, and made it easier for CWP to support the system into the future.
The utility department is also replacing its mobile dispatching system, CGI's PragmaCAD, with Oracle Field Service.
Read supporting passage
In addition, CWP gained similar benefits with the implementation of Oracle Field Service (OFS) for utilities, which is also developed by Oracle and built to integrate with Oracle CCS. OFS is replacing our current Mobile Dispatching System, CGI’s PragmaCAD.
Columbus Water & Power initially deployed Oracle Customer Cloud Service in 2022 to manage meter data for the city's Enhanced Metering Project.
Read supporting passage
CWP implemented Oracle’s Customer Cloud Service (CCS) for meter data management in 2022 as part of the Department's Enhanced Metering Project (EMP). Numerous custom integrations were created to sync meter data between Oracle’s CCS and Hansen Banner. It is challenging to manage the lifecycle of meters with two separate systems.
Managing meters across two separate software platforms required numerous custom integrations to sync meter data between Oracle and Hansen Banner.
Read supporting passage
CWP implemented Oracle’s Customer Cloud Service (CCS) for meter data management in 2022 as part of the Department's Enhanced Metering Project (EMP). Numerous custom integrations were created to sync meter data between Oracle’s CCS and Hansen Banner. It is challenging to manage the lifecycle of meters with two separate systems.
The newly authorized modification funds additional threads and a training subscription, which city records describe as critical for upcoming testing and operational readiness.
Read supporting passage
This ordinance authorizes the fourth modification of the contract, adding funding of $156,213.45 which will create additional threads and add a training subscription and is being submitted in accordance with the relevant provisions of Chapter 329 of City Code.
The newly authorized modification funds additional threads and a training subscription, which city records describe as critical for upcoming testing and operational readiness.
Read supporting passage
Emergency Justification: Emergency action is requested to ensure that CWP can promptly execute the required order associated with streamlining and combining our Oracle service systems into one unified platform to support the CUBE project. It is necessary to prevent disruption to project activities that rely on these expanded resources and will provide accelerated access to the learning and training subscriptions which are critical in preparing CWP for the upcoming implementation, testing, and operational readiness activities.
City officials noted that following Phase 1 implementation of the customer information system, the project team identified a significant volume of post-go-live optimization activities, including defect resolution, system enhancements and user-requested refinements.
Read supporting passage
Following the Phase 1 implementation of the Customer Information System (CIS) project, Columbus Water & Power (CWP) and the implementation team had identified a significant volume of post-go-live solution optimization activities, including system enhancements, process improvements, and user-requested refinements. To support this work while maintaining system stability, additional non-production environments were needed to separate enhancement activities from production support and defect resolution efforts and were authorized under modification #3. This approach helped reduce implementation risk, improve the efficiency of post-go-live improvements, and helped ensure that production issues can be addressed and tested in environments that closely mirror the live system.
To support that work while maintaining system stability, earlier contract legislation authorized additional non-production environments to separate enhancement activities from production support and defect resolution.
Read supporting passage
Following the Phase 1 implementation of the Customer Information System (CIS) project, Columbus Water & Power (CWP) and the implementation team had identified a significant volume of post-go-live solution optimization activities, including system enhancements, process improvements, and user-requested refinements. To support this work while maintaining system stability, additional non-production environments were needed to separate enhancement activities from production support and defect resolution efforts and were authorized under modification #3. This approach helped reduce implementation risk, improve the efficiency of post-go-live improvements, and helped ensure that production issues can be addressed and tested in environments that closely mirror the live system.
The city originally authorized the contract from April 1, 2024 through Oct. 19, 2025, for $1.59 million.
Read supporting passage
The original term of the contract was from April 1st, 2024 up to and including October 19th, 2025, authorized by Ordinance 2871-2023. The contract amount authorized was $1,592,636.40.
Council later approved a modification that combined department Oracle licenses held by the Division of Water and the Director's Office and extended the agreement through March 31, 2027.
Read supporting passage
Ordinance 0040-2026 authorized the second contract modification of the director’s office contract, adding funding of $1,742,060.37, combining the contracts for Oracle licenses held by both the Division of Water and the Director’s office, and extending the contract expiration date up to and including March 31, 2027.
Funding for the modification is split among four utility operating accounts covering electricity, water, sanitary sewer and stormwater services.
Read supporting passage
to authorize the expenditure of $156,213.45 split between the Electricity, Water, Sanitary Sewer, and Stormwater Operating Funds, and to declare an emergency. ($156,213.45)
City records show the department spent $299,695 under the contract in 2024 and $1.93 million in 2025.
Read supporting passage
$299,695.40 was spent in 2024
City records show the department spent $299,695 under the contract in 2024 and $1.93 million in 2025.
Read supporting passage
$1,926,061.16 was spent in 2025
Columbus council holds first reading on one-year utility billing extension after system delay
Supporting evidence (1)
Previously, Pique Media reported on council holding first reading on a one-year utility billing extension after a system delay.
Read supporting passage
Columbus council holds first reading on one-year utility billing extension after system delay