Gahanna Halves Income Tax Growth Forecast as Remote Work Squeezes Capital Plan

A projected $3.6 million reduction in capital resources across income-tax-supported funds leaves Creekside flood mitigation without municipal funding in 2027.

Gahanna

Red brick pedestrian plaza at Creekside Gahanna flanked by multi-story commercial buildings, stone monuments, and an information kiosk.

The public plaza at Creekside Gahanna featuring red brick paving, stone monuments, and mixed-use commercial buildings.

Credit: Sixflashphoto / Wikimedia Commons / CC BY-SA 4.0 Image source

Gahanna City Council is reviewing a trimmed five-year capital improvement program after municipal finance leaders halved projected annual income tax growth from 4% to 2%, citing persistent shifts to remote and hybrid employment.

The city introduced Ordinance ORD-0038-2026 on Oct. 5 to adopt the 2027–2031 capital plan. The growth downgrade lowers projected resources available for capital improvements by $3.6 million across all income-tax-supported funds, according to administrative presentations. The reduction removes approximately $1.1 million directly from the Capital Fund. The draft capital plan allocates no municipal funds in 2027 for a $23 million to $24 million flood mitigation and plaza improvement project at Creekside.

The fiscal retrenchment highlights how post-pandemic work arrangements continue to reshape municipal budgets throughout Central Ohio. Because Ohio municipal income taxes are tied to employee work locations, suburban communities that previously banked on steadily compounding payroll withholdings are recalibrating infrastructure programs to adjust to altered commuting habits and commercial office occupancy.

Previously, Pique reported that Worthington approved Ross Medical Education Center for Wilson Bridge Road space, and reported that Gahanna's mayor resisted a proposed salary increase as council weighed stagnant pay.

Gahanna Trims Projections and Delays Creekside

Senior Director of Operations Kevin Schultz outlined the capital outlook during a Sept. 28 Committee of the Whole meeting, explaining that Finance Director Joann Bury lowered the assumed annual income tax growth rate to 2% based on collections through 2026 and return-to-work changes.

The lower revenue trajectory forced immediate trade-offs in municipal capital spending. The draft 2027 capital budget requests approximately $22.1 million across all project categories, led by approximately $9.2 million for transportation and mobility improvements and $5.1 million for sanitary sewer projects, according to Schultz.

The most prominent casualty is the Creekside flood mitigation and plaza improvement project along Big Walnut Creek. The project carries an estimated total cost between $23 million and $24 million, but the draft 2027 capital plan allocates no municipal funds for it next year, Schultz said.

Schultz said administrators are assembling an outside funding package and pursuing pending grant applications to relieve pressure on local funds. Schultz stated that staff expects to return to City Council with additional information on Creekside during one of the first meetings in January 2027.

Regional Income Tax Pressures Across Central Ohio

Gahanna's budgetary caution mirrors broader vulnerabilities across Franklin County, where municipalities rely heavily on local earnings taxes to back debt service and direct capital outlays.

In neighboring Worthington, municipal records document an acute geographic reliance on traditional corporate employment. Municipal records indicate that the Wilson Bridge Road corridor produces 52% of all income revenue collection in Worthington.

In Columbus, City Council considered Ordinance 2243-2026 to authorize an appropriation of $1,000,000 from the Income Tax Set Aside Subfund for crisis response costs under an emergency declaration. Council referred the measure back to committee on Sept. 14 rather than granting emergency passage.

Next Steps for Gahanna's Capital Program

Gahanna's capital framework faces formal review across multiple municipal bodies throughout October and November.

Under the schedule Schultz presented, the CIP Advisory Committee was slated to meet on October 6, 2026. The measure went before the Committee of the Whole on Oct. 12. The ordinance adopting the 2027–2031 Capital Improvement Plan was recommended for substitution and adoption.

Gahanna City Council postponed its scheduled Oct. 19 adoption vote, returning the measure to committee. According to municipal agenda records, Ordinance ORD-0038-2026 is returning for further discussion with its second reading postponed to Nov. 2, 2026.

The Committee of the Whole is scheduled to revisit the capital plan on Monday, Oct. 26. The legislation before the committee adopts the capital improvement plan and provides for future sunset. Deliberations are slated to cover five-year capital allocations, project costs, and debt limits ahead of the final vote.

Adoption of the Capital Improvement Plan establishes multi-year priorities but does not formally appropriate dollars for the upcoming year. Municipal schedules identify a budget workshop on Nov. 2, 2026. Gahanna City Council is scheduled to take up the capital plan during the Nov. 2 session following the committee review.

More on this story

Pique’s reporting on the same events, newest first.

  1. Gahanna Latest

    Gahanna Schedules Public Hearings on 2027 Municipal Budget

    City Council opens legislative review of operating appropriations, setting resident hearings for Nov. 16 and Dec. 7 with internal transfer limits.

  2. Gahanna

    Gahanna Council Amends Five-Year Capital Plan Ahead of Nov. 2 Vote

    City Council substituted revised project tables to reconcile figures and scheduled final action alongside a budget workshop.

  3. Gahanna

    Gahanna Committee of the Whole to Review Federal Transit Grant for Senior and Disability Mobility

    A proposed resolution before the Committee of the Whole would authorize an application to MORPC for regional Section 5310 transit funding ahead of an Oct. 30 deadline.

  4. Gahanna

    Developer Cites $500,000 in Site Costs to Justify Gahanna Tax Abatement

    Leland Vogel presented retaining wall, stormwater, and wetland expenses to council as members scrutinized past tax incentive compliance in Marysville and Hilliard.

  5. Gahanna

    Gahanna Halves Income Tax Growth Outlook as Remote Work Squeezes Capital Plan

    Citing post-pandemic remote and hybrid work patterns, Gahanna officials cut projected municipal income tax growth from 4% to 2%, squeezing capital funds by $3.6 million. The shift leaves the $23M Creekside flood mitigation project unfunded in 2027 ahead of an Oct. 19 council vote.

  6. Gahanna You are reading

    Gahanna Halves Income Tax Growth Forecast as Remote Work Squeezes Capital Plan

  7. Gahanna

    Gahanna Mayor Resists Proposed Salary Increase as Council Weighs Stagnant Pay

    Laurie Jadwin calls public service a calling rather than a career, while council members argue 15 years of frozen compensation limits the candidate pool.

  8. Worthington

    Joya's Cafe Wins Approval for Old Worthington Expansion and Evening Hours

    Chef Avishar Barua plans dinner service and approximately 60 added seats after municipal boards clear an adjacent storefront buildout.

  9. Worthington

    Worthington Approves Ross Medical Education Center for Wilson Bridge Road Space

    The conditional use permit fills a multi-year vacancy at 350 W. Wilson Bridge Rd. as municipal records weigh space absorption against local tax yields.

How we know this

The sources and records behind this story, with the facts they support.

  1. City Council · 2026-10-05

    gahanna · agendas

    Published · Accessed

    Supporting evidence (1)
    • The city introduced Ordinance ORD-0038-2026 on Oct. 5 to adopt the 2027–2031 capital plan.

      Read supporting passage
      ORD-0038-2026 · AN ORDINANCE ADOPTING THE 2027-2031 CITY OF GAHANNA CAPITAL IMPROVEMENT PLAN, SUPERSEDING ALL PRIOR CAPITAL IMPROVEMENT PLANS, AND PROVIDING FOR FUTURE SUNSET
  2. Committee of the Whole · 2026-09-28

    gahanna · minutes

    Published · Accessed

    Supporting evidence (9)
    • The growth downgrade lowers projected resources available for capital improvements by $3.6 million across all income-tax-supported funds, according to administrative presentations.

      Read supporting passage
      Senior Director Schultz stated that the draft 2027 capital budget reflected reduced income tax growth projections. He explained that Director Bury reduced the assumed annual income tax growth rate from 4% to 2% based on 2026 performance, including the effects of return-to-work changes. He stated that this reduction lowered projected resources available for capital improvements by approximately $3.6 million across all income-tax-supported funds, including approximately $1.1 million within the Capital Fund.
    • The reduction removes approximately $1.1 million directly from the Capital Fund.

      Read supporting passage
      Senior Director Schultz stated that the draft 2027 capital budget reflected reduced income tax growth projections. He explained that Director Bury reduced the assumed annual income tax growth rate from 4% to 2% based on 2026 performance, including the effects of return-to-work changes. He stated that this reduction lowered projected resources available for capital improvements by approximately $3.6 million across all income-tax-supported funds, including approximately $1.1 million within the Capital Fund.
    • The draft capital plan allocates no municipal funds in 2027 for a $23 million to $24 million flood mitigation and plaza improvement project at Creekside.

      Read supporting passage
      Senior Director Schultz discussed the Creekside flood mitigation and plaza improvements project. He stated that the draft continued to show no 2027 allocation because the City was still developing the funding package, although the slide showed an estimated total project cost of approximately $23 million to $24 million. He stated that staff expected to return to City Council with additional information, likely during one of the first meetings in January 2027.
    • Senior Director of Operations Kevin Schultz outlined the capital outlook during a Sept. 28 Committee of the Whole meeting, explaining that Finance Director Joann Bury lowered the assumed annual income tax growth rate to 2% based on collections through 2026 and return-to-work changes.

      Read supporting passage
      Senior Director Schultz stated that the draft 2027 capital budget reflected reduced income tax growth projections. He explained that Director Bury reduced the assumed annual income tax growth rate from 4% to 2% based on 2026 performance, including the effects of return-to-work changes. He stated that this reduction lowered projected resources available for capital improvements by approximately $3.6 million across all income-tax-supported funds, including approximately $1.1 million within the Capital Fund.
    • The draft 2027 capital budget requests approximately $22.1 million across all project categories, led by approximately $9.2 million for transportation and mobility improvements and $5.1 million for sanitary sewer projects, according to Schultz.

      Read supporting passage
      Senior Director Schultz stated that the draft 2027 capital budget requested approximately $22.1 million across all project categories. He identified transportation and mobility as the largest category at approximately $9.2 million, including West Johnstown Road improvements, design work for the Stygler Road, Agler Road, and U.S. 62 improvements, and the annual street and sidewalk programs. He identified approximately $5.1 million for sanitary sewer projects, including pump station improvements.
    • The project carries an estimated total cost between $23 million and $24 million, but the draft 2027 capital plan allocates no municipal funds for it next year, Schultz said.

      Read supporting passage
      Senior Director Schultz discussed the Creekside flood mitigation and plaza improvements project. He stated that the draft continued to show no 2027 allocation because the City was still developing the funding package, although the slide showed an estimated total project cost of approximately $23 million to $24 million. He stated that staff expected to return to City Council with additional information, likely during one of the first meetings in January 2027.
    • Schultz stated that staff expects to return to City Council with additional information on Creekside during one of the first meetings in January 2027.

      Read supporting passage
      Senior Director Schultz discussed the Creekside flood mitigation and plaza improvements project. He stated that the draft continued to show no 2027 allocation because the City was still developing the funding package, although the slide showed an estimated total project cost of approximately $23 million to $24 million. He stated that staff expected to return to City Council with additional information, likely during one of the first meetings in January 2027.
    • Under the schedule Schultz presented, the CIP Advisory Committee was slated to meet on October 6, 2026.

      Read supporting passage
      He requested First Reading the following week and stated that the CIP Advisory Committee would meet on October 6, 2026.
    • Municipal schedules identify a budget workshop on Nov. 2, 2026.

      Read supporting passage
      He also identified the November 2, 2026, budget workshop on the schedule and invited questions.
  3. https://gahanna.legistar.com/MeetingDetail.aspx?ID=1454573&GUID=80501387-BACF-4772-AA54-0CB1636F2FAF&G=D520A30C-99FC-4126-A19A-CAC21101A677&Options=&Search=

    gahanna.legistar.com

    Accessed

    Supporting evidence (1)
    • The ordinance adopting the 2027–2031 Capital Improvement Plan was recommended for substitution and adoption.

      Read supporting passage
      AN ORDINANCE ADOPTING THE 2027-2031 CITY OF GAHANNA CAPITAL IMPROVEMENT PLAN, SUPERSEDING ALL PRIOR CAPITAL IMPROVEMENT PLANS, AND PROVIDING FOR FUTURE SUNSETRecommended for Substitution and Adoption
  4. Committee of the Whole · 2026-10-26

    gahanna · agendas

    Published · Accessed

    Supporting evidence (3)
    • According to municipal agenda records, Ordinance ORD-0038-2026 is returning for further discussion with its second reading postponed to Nov. 2, 2026.

      Read supporting passage
      ORD-0038-2026 · AN ORDINANCE ADOPTING THE 2027-2031 CITY OF GAHANNA CAPITAL IMPROVEMENT PLAN, SUPERSEDING ALL PRIOR CAPITAL IMPROVEMENT PLANS, AND PROVIDING FOR FUTURE SUNSET
    • According to municipal agenda records, Ordinance ORD-0038-2026 is returning for further discussion with its second reading postponed to Nov. 2, 2026.

      Read supporting passage
      Returning for further discussion (Second Reading Postponed to 11/2/2026):
    • The legislation before the committee adopts the capital improvement plan and provides for future sunset.

      Read supporting passage
      ORD-0038-2026 · AN ORDINANCE ADOPTING THE 2027-2031 CITY OF GAHANNA CAPITAL IMPROVEMENT PLAN, SUPERSEDING ALL PRIOR CAPITAL IMPROVEMENT PLANS, AND PROVIDING FOR FUTURE SUNSET
  5. ARB/MPC Minutes · September 10, 2026 · minutes

    www.worthington.org

    Accessed

    Supporting evidence (1)
    • Municipal records indicate that the Wilson Bridge Road corridor produces 52% of all income revenue collection in Worthington.

      Read supporting passage
      The Wilson Bridge Rd. Corridor produces 52% of all income revenue collection
  6. Columbus City Council · 2026-09-14

    columbus · minutes

    Published · Accessed

    Supporting evidence (1)
    • In Columbus, City Council considered Ordinance 2243-2026 to authorize an appropriation of $1,000,000 from the Income Tax Set Aside Subfund for crisis response costs under an emergency declaration.

      Read supporting passage
      2243-2026 · To authorize the appropriation of $1,000,000.00 from the unappropriated balance in the Income Tax Set Aside (ITSA) Subfund to support crisis response activity costs; and to declare an emergency. ($1,000,000.00)
  7. Gahanna Mayor Resists Proposed Salary Increase as Council Weighs Stagnant Pay

    Published · Accessed

    Supporting evidence (1)
    • Previously, Pique reported that Worthington approved Ross Medical Education Center for Wilson Bridge Road space, and reported that Gahanna's mayor resisted a proposed salary increase as council weighed stagnant pay.

      Read supporting passage
      Gahanna Mayor Resists Proposed Salary Increase as Council Weighs Stagnant Pay
  8. Worthington Approves Ross Medical Education Center for Wilson Bridge Road Space

    Published · Accessed

    Supporting evidence (1)
    • Previously, Pique reported that Worthington approved Ross Medical Education Center for Wilson Bridge Road space, and reported that Gahanna's mayor resisted a proposed salary increase as council weighed stagnant pay.

      Read supporting passage
      Worthington Approves Ross Medical Education Center for Wilson Bridge Road Space

Take Pique with you

Your city. In your pocket.

Read local stories, watch the videos and explore the details in Pique.

QR code for Pique Media on the App Store

Get Pique for iPhone and iPad

Scan the code with your phone’s camera.

View on the App Store

Share this story