Columbus Adds $750,000 for Avery Road Land Purchases as Appraisals Climb
Higher parcel appraisals increased right-of-way costs for reconstruction and a planned roundabout along Avery Road to $1.75 million.
The Columbus City Council ordained emergency legislation authorizing the city to expend up to $750,000 to acquire property rights for the Avery Road project.
The extra allocation brings total right-of-way acquisition funding for the project to $1.75 million, up from the $1 million authorized earlier this year. According to city legislative records, officials requested emergency action because active parcel appraisals came in higher than expected, and waiting through a standard 30-day legislative period would delay purchase offers and jeopardize construction schedules.
The money will be drawn from community authority assessments in the Hayden Run South tax increment financing fund and transferred into the project's capital fund. Under the measure, the City Attorney's Office real estate division will hire professional services, including surveys and appraisals, and negotiate with landowners to acquire fee simple titles and lesser property interests in the Hayden Run planning area.
A completed roundabout along Avery Road at Rings and Cara roads in northwest Franklin County. Columbus City Council approved emergency funding Monday to acquire property for a new roundabout and widening farther south along Avery Road at Avondale Woods Boulevard.
Credit: City of Dublin, Ohio Image source
The corridor improvements will reconstruct 1.02 miles of Avery Road from the railroad tracks just north of Hayden Run Road to Avery Run Road. The roadway project will include curb and gutter, a closed drainage system, street lighting and a roundabout at Avondale Woods Boulevard. The project also includes complete street upgrades, featuring a shared-use path and sidewalk along Avery Road, as well as lane reconfigurations by milling and overlaying pavement from 750 feet south of Hayden Run Road to the railroad tracks.
The legislation also authorizes the Department of Public Service to execute agreements with Benesch and CSX Transportation Inc. to coordinate construction and mitigate potential conflicts with rail operations along the corridor. If property acquisition expenses exceed the new budget, officials noted that additional legislation will be submitted to City Council to request further funding.
How we know this
The sources and records behind this story, with the facts they support.
Supporting evidence (10)
The Columbus City Council ordained emergency legislation authorizing the city to expend up to $750,000 to acquire property rights for the Avery Road project.
Read supporting passage
WHEREAS, this ordinance authorizes the City Attorney's Office Real Estate Division to expend $750,000.00, or so much thereof as may be necessary, to hire professional services and to negotiate with property owners to acquire the various property rights necessary to complete the Arterial Street Rehabilitation - Avery Road project; and WHEREAS, an emergency exists in the usual daily operation of the Department of Public Service in that acquisition that is already in progress had appraisals come in higher than expected and waiting thirty days or more would prevent the City from not being able to make all offers on the project, and not being able to keep the project on schedule within the construction season, thereby preserving the safety of the traveling public, all for the immediate preservation of the public health, peace, property, safety and welfare; and NOW, THEREFORE BE IT ORDAINED BY THE COUNCIL OF THE CITY OF COLUMBUS:
The extra allocation brings total right-of-way acquisition funding for the project to $1.75 million, up from the $1 million authorized earlier this year.
Read supporting passage
Ordinance No. 0820-2026 authorized the appropriation and expenditure of funding in the amount of up to $1,000,000.00 to acquire right-of-way needed to complete the project. This ordinance is authorizing an additional funds up to $750,000.00 to acquire the right-of-way needed to complete the project.
According to city legislative records, officials requested emergency action because active parcel appraisals came in higher than expected, and waiting through a standard 30-day legislative period would delay purchase offers and jeopardize construction schedules.
Read supporting passage
Emergency action is requested to complete acquisition that is already in progress, appraisals came in higher than expected and waiting thirty days or more would prevent the City from not being able to make all offers on the project, and not being able to keep the project on schedule within the construction season.
The money will be drawn from community authority assessments in the Hayden Run South tax increment financing fund and transferred into the project's capital fund.
Read supporting passage
Funding is available, through the Department of Development, with $750,000.00 from the community authority assessments in the Hayden Run South TIF Fund, Fund 4450; Funds will need to be appropriated in Fund 4450 and transferred to Fund 7767, the Hayden Run South TIF Capital Fund, and then appropriated in Fund 7767.
Under the measure, the City Attorney's Office real estate division will hire professional services, including surveys and appraisals, and negotiate with landowners to acquire fee simple titles and lesser property interests in the Hayden Run planning area.
Read supporting passage
The following ordinance authorizes the City Attorney's Office, Real Estate Division to hire professional services (e.g. surveys, title work, appraisals, etc.) and to negotiate with property owners to acquire the various property rights necessary to complete the Arterial Street Rehabilitation - Avery Road project in the Hayden Run Planning Area (30).
The corridor improvements will reconstruct 1.02 miles of Avery Road from the railroad tracks just north of Hayden Run Road to Avery Run Road.
Read supporting passage
along with improvements and reconstruction of 1.02 miles of Avery Road from the railroad track just north of Hayden Run Road to the intersection of Avery Run Road.
The roadway project will include curb and gutter, a closed drainage system, street lighting and a roundabout at Avondale Woods Boulevard.
Read supporting passage
The project will include the addition of curb and gutter, shared use path, sidewalk, a roundabout at Avondale Woods Boulevard, closed drainage system, and lighting.
The project also includes complete street upgrades, featuring a shared-use path and sidewalk along Avery Road, as well as lane reconfigurations by milling and overlaying pavement from 750 feet south of Hayden Run Road to the railroad tracks.
Read supporting passage
The project will also include complete street elements such as a shared use path and a sidewalk along Avery Road along with new lighting, storm sewer modifications, signal modifications, construction of a new roundabout, and signal installation. This project also includes lane reconfiguration by use of milling and overlay from 750 feet south of Hayden Road to the railroad tracks just north of Hayden Run Road
The legislation also authorizes the Department of Public Service to execute agreements with Benesch and CSX Transportation Inc. to coordinate construction and mitigate potential conflicts with rail operations along the corridor.
Read supporting passage
WHEREAS, the aforementioned project also requires the consent and cooperation of Benesch and CSX Transportation Inc., which operates within the project limits, to identify and mitigate potential conflicts between existing rail operations and the planned public improvements; and WHEREAS, this legislation seeks to authorize the execution of a construction contract, or a similar instrument, between the Department of Public Service and Benesch and between the Department of Public Service and CSX Transportation Inc. for that purpose;
If property acquisition expenses exceed the new budget, officials noted that additional legislation will be submitted to City Council to request further funding.
Read supporting passage
If the cost to acquire the needed right-of-way should exceed this estimate, additional legislation will be submitted to Council requesting the needed funding.