Columbus Approves $1.17 Million to Overhaul Lazelle Woods and Warner Woods Playgrounds
Emergency legislation funds wheelchair-accessible ramps, rubber surfacing and subsurface repairs ahead of summer 2027.
The Columbus City Council authorized an emergency $1,169,894 expenditure for the Lazelle and Warner Woods playground renovation project. The measure authorizes city recreation officials to enter into contract with Builderscape, Inc., which was selected as the lowest and most responsive bidder.
Lazelle Woods Community Center at Lazelle Woods Park in Columbus.
Credit: City of Columbus Recreation and Parks Department Image source
At Lazelle Woods Park, the project delivers a playground designed for universal accessibility. The upgraded site will feature wheelchair ramps and rubber surfacing, along with equipment tailored for children with diverse play needs and varying mobility.
An open-air picnic shelter and walkways at Warner Woods Park in Columbus.
Credit: City of Columbus Recreation and Parks Department Image source
At Warner Woods Park, the city is replacing a section of playground where subsurface conditions damaged the existing tile play surface. Crews will convert that area to engineered wood fiber surfacing and install a larger swing structure equipped with accessible swing seats.
The Columbus Recreation and Parks Department advertised competitive bids on Aug. 4 and received proposals on Aug. 25. Builderscape submitted a contract amount of $1,060,813 and was determined to be the lowest and most responsive bidder. The approved expenditure includes Builderscape's base contract, a $106,081.30 contingency and $3,000 for interdepartmental inspections and fees, funded through the Recreation and Parks Permanent Improvement Fund.
According to city records, community requests and area commission meetings sought updated playground equipment to accommodate increased accessibility and socialization. The legislation was declared an emergency measure to allow for a 16-week lead time for the playground equipment. The timeline is intended to keep construction on schedule for completion ahead of summer 2027.
Video Watch video 0:34
How we know this
The sources and records behind this story, with the facts they support.
Supporting evidence (18)
The Columbus City Council authorized an emergency $1,169,894 expenditure for the Lazelle and Warner Woods playground renovation project.
Read supporting passage
BE IT ORDAINED BY THE COUNCIL OF THE CITY OF COLUMBUS:
The Columbus City Council authorized an emergency $1,169,894 expenditure for the Lazelle and Warner Woods playground renovation project.
Read supporting passage
To authorize the Director of the Recreation and Parks Department to enter into contract with Builderscape, Inc. for the Playground Renovations 2025-2026 - Lazelle and Warner Woods Project; to authorize the appropriation of $372,108.01 within the Recreation and Parks Permanent Improvement Fund; to authorize the transfer of $1,169,894.30 within the Recreation and Parks Permanent Improvement Fund; to authorize the expenditure of $1,169,894.30 from the Recreation and Parks Permanent Improvement Fund; and to declare an emergency. ($1,169,894.30)
The measure authorizes city recreation officials to enter into contract with Builderscape, Inc., which was selected as the lowest and most responsive bidder.
Read supporting passage
This ordinance authorizes the Director of the Recreation and Parks Department to enter into contract with Builderscape, Inc. for the Playground Renovations 2025-2026 - Lazelle and Warner Woods Project.
The measure authorizes city recreation officials to enter into contract with Builderscape, Inc., which was selected as the lowest and most responsive bidder.
Read supporting passage
After reviewing the bids that were submitted, it was determined that Builderscape, Inc. was the lowest and most responsive bidder.
At Lazelle Woods Park, the project delivers a playground designed for universal accessibility.
Read supporting passage
For this project, Lazelle Woods will include a playground designed for universal accessibility.
The upgraded site will feature wheelchair ramps and rubber surfacing, along with equipment tailored for children with diverse play needs and varying mobility.
Read supporting passage
The playground will have ramps, rubber surfacing, and equipment for users with diverse play needs and varying levels of mobility.
At Warner Woods Park, the city is replacing a section of playground where subsurface conditions damaged the existing tile play surface.
Read supporting passage
A portion of the Warner Woods playground will be replaced due to subsurface conditions making the tile play surfacing inaccessible.
Crews will convert that area to engineered wood fiber surfacing and install a larger swing structure equipped with accessible swing seats.
Read supporting passage
This section will be converted to engineered wood fiber surfacing.
Crews will convert that area to engineered wood fiber surfacing and install a larger swing structure equipped with accessible swing seats.
Read supporting passage
The improved playground will also include a new larger swing structure with accessible swing seats.
The Columbus Recreation and Parks Department advertised competitive bids on Aug. 4 and received proposals on Aug. 25.
Read supporting passage
Bids were advertised through Vendor Services, in accordance with City Code Section 329, on August 4, 2026 and received by the Recreation and Parks Department on August 25, 2026.
Builderscape submitted a contract amount of $1,060,813 and was determined to be the lowest and most responsive bidder.
Read supporting passage
The contract amount is $1,060,813.00, with a contingency of $106,081.30, for a total of $1,166,894.30.
Builderscape submitted a contract amount of $1,060,813 and was determined to be the lowest and most responsive bidder.
Read supporting passage
After reviewing the bids that were submitted, it was determined that Builderscape, Inc. was the lowest and most responsive bidder.
The approved expenditure includes Builderscape's base contract, a $106,081.30 contingency and $3,000 for interdepartmental inspections and fees, funded through the Recreation and Parks Permanent Improvement Fund.
Read supporting passage
The contract amount is $1,060,813.00, with a contingency of $106,081.30, for a total of $1,166,894.30. An additional $3,000.00 is being authorized for interdepartmental inspections and fees for a total of $1,169,894.30 being authorized by this ordinance.
The approved expenditure includes Builderscape's base contract, a $106,081.30 contingency and $3,000 for interdepartmental inspections and fees, funded through the Recreation and Parks Permanent Improvement Fund.
Read supporting passage
Fiscal Impact: $1,169,894.30 is budgeted and available from within the Recreation and Parks Permanent Improvement Fund 7747 to meet the financial obligations of this expenditure.
According to city records, community requests and area commission meetings sought updated playground equipment to accommodate increased accessibility and socialization.
Read supporting passage
There have been community requests as well as area commission meetings intended to discuss playground improvements. The community has asked the department to provide more up to date playground equipment that will accommodate increased accessibility and socialization.
The legislation was declared an emergency measure to allow for a 16-week lead time for the playground equipment.
Read supporting passage
SECTION 8. That this ordinance, for the reasons stated in the preamble, which are made a part of this ordinance and fully incorporated for reference as if rewritten, is declared to be an emergency measure
The legislation was declared an emergency measure to allow for a 16-week lead time for the playground equipment.
Read supporting passage
Emergency Justification: Emergency action is requested in order to allow for the 16 week lead time for the playground equipment, staying on schedule for completion by summer 2027.
The timeline is intended to keep construction on schedule for completion ahead of summer 2027.