Columbus Approves $10.14 Million for Near East Storm Sewers and Waterline Upgrades
The contract with Danbert covers rain gardens, storm sewers, Gault Street waterlines and Driving Park improvements.
Columbus City Council on Monday, Nov. 16, approved legislation authorizing a construction contract with Danbert, Inc. for Blueprint Kent/Fairwood storm sewers, Gault Street waterline improvements and Driving Park improvements. The measure authorizes a total expenditure of up to $10,135,185.42 for the project, including construction and prevailing wage services.
The project covers neighborhood blocks in the Livingston Avenue Area and Near East planning areas, bounded by Main Street and Livingston Avenue on the north and south and between Rhoads Avenue and Miller Avenue on the east and west.
As part of the city's Blueprint Columbus program, the work includes constructing rain gardens and storm sewers within the right-of-way and on city-owned properties to treat surface runoff before it discharges into local waterways. The contract also entails relocating waterlines along Gault Street, restoring pavement and sidewalks, and completing Driving Park improvements.
Under the legislation, the construction contract award is set at up to $10,133,185.42, which includes a 10% contingency reserve for approved modifications. The measure also provides $2,000 for prevailing wage compliance services through the Department of Public Service.
Funding for the storm sewers will be obtained through a state water pollution loan, while the waterline improvements will be funded through a fresh water loan program. The legislation authorizes appropriations of $9,370,317.73 in the Sanitary Revolving Loan Fund and $700,238.66 in the Water - Fresh Water Market Rate Loan Fund. Another $62,629.03 from recreation bond funds will pay for the Driving Park improvements.
The contract remains contingent on state loan approvals by the Ohio Water Development Authority board. The state board is expected to approve the loans at its December 2026 meeting.
Danbert submitted the lowest and best bid among four proposals opened on Sept. 16, 2026. According to city records, Danbert listed nine subcontractors for the project, including eight firms based in Columbus and one in Hilliard. Work must be finished within 630 days of the city's notice to proceed.
Video Watch video 0:29
Pique’s reporting on the same events, newest first.
Near East Latest You are reading
Columbus Approves $10.14 Million for Near East Storm Sewers and Waterline Upgrades
Near East
Columbus Council Advances $10.1 Million Storm Sewer Contract for Near East Side
Legislation heading to a second reading would fund rain gardens, replace waterlines on Gault Street, and upgrade Driving Park.
How we know this
The sources and records behind this story, with the facts they support.
Supporting evidence (1)
Columbus City Council on Monday, Nov. 16, approved legislation authorizing a construction contract with Danbert, Inc. for Blueprint Kent/Fairwood storm sewers, Gault Street waterline improvements and Driving Park improvements.
Read supporting passage
Columbus City Council · 2843-2026 · To authorize the Director of Columbus Water and Power to enter into a construction contract with Danbert, Inc. for the Blueprint Kent/Fairwood Storm Sewers: Gault Street Waterline Improvements; and Driving Park Improvements projects; to authorize the appropriation and expenditure of up to $10,133,185.42 from the Water Pollution Control Loan Fund and the Water - Fresh Water Market Rate Loan Fund and to authorize the transfer of $62,629.03 within the Recreation and Parks Voted Bond Fund; to authorize the expenditure of $62,629.03 from the Recreation and Parks Voted Bond Fund for the contract; to make this ordinance contingent upon the Ohio Water Development Authority approving loans for the project; and to authorize the expenditure of up to $2,000.00 from the Sanitary Bond Fund to pay for prevailing wage services. ($10,135,185.42) Recorded action: Approved A motion was made by Christopher Wyche, seconded by Nancy Day-Achauer, that this Ordinance be Approved. The motion carried by the following vote: Result: Pass · Mover: Christopher Wyche · Seconder: Nancy Day-Achauer Nicholas Bankston: Affirmative Lourdes Barroso De Padilla: Affirmative Nancy Day-Achauer: Affirmative Rob Dorans: Affirmative Melissa Green: Affirmative Emmanuel V. Remy: Affirmative Tiara Ross: Affirmative Christopher Wyche: Affirmative Shannon G. Hardin: Affirmative {Body=Columbus City Council, Content type=Outcomes, Document coverage=API text and document metadata; linked PDF bytes are not retained, Local time=5:00 PM, Location=City Council Chambers, Rm 231, Meeting date=2026-11-16T00:00:00, Municipality=columbus}
Supporting evidence (20)
Columbus City Council on Monday, Nov. 16, approved legislation authorizing a construction contract with Danbert, Inc. for Blueprint Kent/Fairwood storm sewers, Gault Street waterline improvements and Driving Park improvements.
Read supporting passage
This ordinance authorizes the Director of Columbus Water and Power to enter into a construction contract through the City’s Invitation for Bid process with Danbert, Inc., for the CIP #650870-101202, 690236-100160, & 517018-100000; Blueprint Kent/Fairwood Storm Sewers: Gault Street Waterline Improvements; and Driving Park Improvements in an amount up to $10,133,185.42; and to encumber funds with the Department of Public Service for prevailing wage services in an amount up to $2,000.00; for a total expenditure of up to $10,135,185.42.
The measure authorizes a total expenditure of up to $10,135,185.42 for the project, including construction and prevailing wage services.
Read supporting passage
for a total expenditure of up to $10,135,185.42.
The project covers neighborhood blocks in the Livingston Avenue Area and Near East planning areas, bounded by Main Street and Livingston Avenue on the north and south and between Rhoads Avenue and Miller Avenue on the east and west.
Read supporting passage
Planning Area - 62 Livingston Avenue Area & 56 Near East.
The project covers neighborhood blocks in the Livingston Avenue Area and Near East planning areas, bounded by Main Street and Livingston Avenue on the north and south and between Rhoads Avenue and Miller Avenue on the east and west.
Read supporting passage
This project will construct rain gardens and storm sewers within the Right-of-Way and on City owned properties on within the project area bounded Main Street and Livingston Avenue on the north and south, and between Rhoads Avenue and Miller Avenue on the east and west.
As part of the city's Blueprint Columbus program, the work includes constructing rain gardens and storm sewers within the right-of-way and on city-owned properties to treat surface runoff before it discharges into local waterways.
Read supporting passage
This project is being completed as part of the City’s Blueprint Columbus program. This project will construct green infrastructure (GI) throughout the neighborhood which will provide a higher water quality within the region by treating the surface runoff before it discharges to the waterways.
As part of the city's Blueprint Columbus program, the work includes constructing rain gardens and storm sewers within the right-of-way and on city-owned properties to treat surface runoff before it discharges into local waterways.
Read supporting passage
This project will construct rain gardens and storm sewers within the Right-of-Way and on City owned properties on within the project area bounded Main Street and Livingston Avenue on the north and south, and between Rhoads Avenue and Miller Avenue on the east and west.
The contract also entails relocating waterlines along Gault Street, restoring pavement and sidewalks, and completing Driving Park improvements.
Read supporting passage
This work also includes the relocation of waterlines, pavement and sidewalk restoration, and other such work as may be necessary to complete the contract.
Under the legislation, the construction contract award is set at up to $10,133,185.42, which includes a 10% contingency reserve for approved modifications.
Read supporting passage
The bid amount and proposed award amount is $10,133,185.42, including a 10% construction contingency amount that will be utilized to fund needed and approved changes in the work.
The measure also provides $2,000 for prevailing wage compliance services through the Department of Public Service.
Read supporting passage
and to encumber funds with the Department of Public Service for prevailing wage services in an amount up to $2,000.00; for a total expenditure of up to $10,135,185.42.
Funding for the storm sewers will be obtained through a state water pollution loan, while the waterline improvements will be funded through a fresh water loan program.
Read supporting passage
Funding for the Blueprint Kent/Fairwood Storm Sewers portion of this contract will be obtained through a loan from the Water Pollution Control Loan Fund (WPCLF), jointly administered by the Ohio EPA's Division of Environmental and Financial Assistance and the Ohio Water Development Authority (OWDA).
Funding for the storm sewers will be obtained through a state water pollution loan, while the waterline improvements will be funded through a fresh water loan program.
Read supporting passage
Funding for the Gault Street Waterline Improvements portion of this contract will be obtained through a loan from the OWDA Fresh Water Program (OWDA Direct).
The legislation authorizes appropriations of $9,370,317.73 in the Sanitary Revolving Loan Fund and $700,238.66 in the Water - Fresh Water Market Rate Loan Fund.
Read supporting passage
SECTION 1. That the appropriation of $9,370,317.73, or so much thereof as may be needed, is hereby authorized in the Sanitary Revolving Loan Fund, Fund 6111
The legislation authorizes appropriations of $9,370,317.73 in the Sanitary Revolving Loan Fund and $700,238.66 in the Water - Fresh Water Market Rate Loan Fund.
Read supporting passage
the appropriation of $700,238.66, or so much thereof as may be needed, is hereby authorized in the Water - Fresh Water Market Rate Loan Fund, Fund 6014
Another $62,629.03 from recreation bond funds will pay for the Driving Park improvements.
Read supporting passage
to authorize the transfer of $62,629.03 within the Recreation and Parks Voted Bond Fund; to authorize the expenditure of $62,629.03 from the Recreation and Parks Voted Bond Fund for the contract;
The contract remains contingent on state loan approvals by the Ohio Water Development Authority board.
Read supporting passage
This ordinance is contingent upon both loans being approved by the OWDA Board. Columbus Water and Power will inform the Auditor’s Office when the loans are approved.
The state board is expected to approve the loans at its December 2026 meeting.
Read supporting passage
This loan is expected to be approved at the December 2026 OWDA Board meeting.
Danbert submitted the lowest and best bid among four proposals opened on Sept. 16, 2026.
Read supporting passage
The Danbert, Inc. bid was deemed the lowest, best, most responsive and responsible bid in the amount of $10,133,185.42.
Danbert submitted the lowest and best bid among four proposals opened on Sept. 16, 2026.
Read supporting passage
Four bids were received for the project and were opened on 9/16/2026.
According to city records, Danbert listed nine subcontractors for the project, including eight firms based in Columbus and one in Hilliard.
Read supporting passage
Danbert, Inc., listed the following companies as subcontractors for this project: Company Name City/State ODI Certification Status Strawser Paving Columbus, Ohio MAJ Oberlanders Columbus, Ohio MAJ Decker Construction Company Columbus, Ohio MAJ Danbert Electrical Columbus, Ohio MAJ 4K Landscape Hilliard, Ohio MAJ Paul Peterson Company Columbus, Ohio MAJ Griffin Pavement Striping Columbus, Ohio MAJ Garica Surveyors Columbus, Ohio MBE Hurt’s Trucking Columbus, Ohio MBE
Work must be finished within 630 days of the city's notice to proceed.
Read supporting passage
TIMELINE: Contract work is required to be completed in a manner acceptable to the City within 630 days of the date that a Notice To Proceed (NTP) is given by the City.