Video 0:55

Video

Columbus approves $10.4M Clintonville sewer lateral lining contract

Published

Read the full article

Columbus City Council voted 8-0 to approve a $10.4 million lateral lining contract with BLD Services for Blueprint Clintonville 3. Homeowners face zero direct costs for trenchless cured-in-place pipe lining, with construction pending December state loan approval.

How we know this

The sources and records behind this story, with the facts they support.

  1. Columbus City Council · 2913-2026 · To authorize the Director of Columbus Water and Power to enter into a construction contract with BLD Services, LLC, for the Later Lining - Blueprint Clintonville 3 Project 1; to appropriate funds within the Sanitary Revolving Loan Fund; to make this ordinance cont

    columbus · outcomes

    Published · Accessed

    Supporting evidence (1)
    • Columbus City Council voted 8-0 on Nov. 23 to approve a $10.4 million construction contract with BLD Services, LLC to line residential sewer laterals in southern Clintonville.

      Read supporting passage
      Recorded action: Approved A motion was made by Christopher Wyche, seconded by Nancy Day-Achauer, that this Ordinance be Approved. The motion carried by the following vote: Result: Pass · Mover: Christopher Wyche · Seconder: Nancy Day-Achauer Nicholas Bankston: Affirmative Lourdes Barroso De Padilla: Affirmative Nancy Day-Achauer: Affirmative Rob Dorans: Affirmative Melissa Green: Affirmative Emmanuel V. Remy: Affirmative Tiara Ross: Affirmative Christopher Wyche: Affirmative Shannon G. Hardin: Absent {Body=Columbus City Council, Content type=Outcomes, Document coverage=API text and document metadata; linked PDF bytes are not retained, Local time=5:00 PM, Location=City Council Chambers, Rm 231, Meeting date=2026-11-23T00:00:00, Municipality=columbus}
  2. 2913-2026 · To authorize the Director of Columbus Water and Power to enter into a construction contract with BLD Services, LLC, for the Later Lining - Blueprint Clintonville 3 Project 1; to appropriate funds within the Sanitary Revolving Loan Fund; to make this ordinance contingent upon the Ohio Wat

    columbus · legislation

    Published · Accessed

    Supporting evidence (9)
    • Columbus City Council voted 8-0 on Nov. 23 to approve a $10.4 million construction contract with BLD Services, LLC to line residential sewer laterals in southern Clintonville.

      Read supporting passage
      This ordinance authorizes the Director of Columbus Water and Power to enter into a construction contract with BLD Services, LLC for Water Reclamation (Sanitary Sewers) for the Lateral Lining- Blueprint Clintonville 3 Project 1, CIP #650872-139001, in an amount up to $10,405,206.90; and to encumber funds with the Columbus Power & Water for construction administration and inspection (prevailing wage) services in an amount up to $2,000.00, for a total expenditure of $10,407,206.90. This project will install and/or repair lateral liners and sanitary services in residential areas.
    • The project will line lateral sewer lines to houses in the neighborhood to reduce storm and groundwater inflow into city mains, cutting sewer backups into residential homes and the Olentangy River.

      Read supporting passage
      This project will provide lining of lateral sewer lines to houses within the indicated area. By lining the service, storm and groundwater inflow into City main will reduce overflow. This reduction of inflow reduces sewer backups into residential homes and the Olentangy River.
    • Columbus Water and Power advertised the project for competitive bidding from Sept. 14 through Oct. 7, according to council records.

      Read supporting passage
      An Invitation for Bids for the Water Reclamation (Sanitary Sewers) for Lateral Lining - Blueprint Clintonville 3 Project 1 was advertised on the Vendor Services and Bid Express websites from 9/14/26 through10/07/26. Two bids were received for the project and were opened on 10/7/26.
    • The city opened two bids on Oct. 7, deeming BLD Services the lowest responsive bidder at $10,405,206.90 over Performance Pipelining, Inc., which bid $11,358,360.

      Read supporting passage
      Two bids were received for the project and were opened on 10/7/26. The following companies submitted a bid: Company Bid Amount Compliance Number ODI Status BLD Services, LLC $10,405,206.90 CC019505 MAJ Performance Pipelining, Inc. $11,358,360.00 CC045405 MAJ BLD Services, LLC bid was deemed the lowest, best, most responsive and responsible bid in the amount of $10,405,206.90.
    • Council authorized up to $10,407,206.90, adding $2,000 for prevailing wage services.

      Read supporting passage
      Cost summary: Original Contract $ 10,405,206.90 Future Anticipated Needs $ 0.00 Prevailing Wage Services $ 2,000.00 CONTRACT TOTAL $ 10,407,206.90
    • BLD Services listed JLD Construction of Columbus, certified as a minority business enterprise, as a subcontractor for the project.

      Read supporting passage
      BLD Services, LLC listed the following company as subcontractor for this project: Company Name City/State ODI Certification Status JLD Construction Columbus, Ohio MBE
    • Under contract terms, the contractor must reach substantial completion within 600 days of receiving a formal notice to proceed, with final project acceptance within 700 days.

      Read supporting passage
      TIMELINE: Contract work is required to be Substantially Complete in a manner acceptable to the City within 600 days from the date that a Notice To Proceed (NTP) is given by the City. Final Acceptance shall be achieved within 700 days of NTP.
    • Construction of the lateral-lining project is anticipated to be financed with a loan from the Water Pollution Control Loan Fund, authorized by City Council in December 2025.

      Read supporting passage
      The construction portion of this project is anticipated to be financed with a loan from the Water Pollution Control Loan Fund (WPCLF), a program jointly administered by the Ohio EPA's Division of Environmental and Financial Assistance and the Ohio Water Development Authority (OWDA). City Council authorized this loan application and acceptance of funding via Ordinance 3119-2025, passed by Council on 12/15/25.
    • The contract legislation is contingent upon the loan being approved by the Ohio Water Development Authority at its December board meeting.

      Read supporting passage
      This loan is expected to be approved at the OWDA December Board meeting. This ordinance is contingent upon the loan being approved by OWDA.
  3. https://blueprintneighborhoods.com/neighborhoods/clintonville-3/

    blueprintneighborhoods.com

    Accessed

    Supporting evidence (2)
    • Columbus City Council voted 8-0 on Nov. 23 to approve a $10.4 million construction contract with BLD Services, LLC to line residential sewer laterals in southern Clintonville.

      Read supporting passage
      Clintonville 3 is the southernmost section of Clintonville. It has been identified as a Blueprint priority area due to high numbers of basement backup incidences and sanitary sewer overflows that discharge into the Walhalla Ravine and the Olentangy River.
    • Clintonville 3 is identified as a Blueprint priority area due to high numbers of basement backup incidences and sanitary sewer overflows that discharge into the Walhalla Ravine and the Olentangy River.

      Read supporting passage
      Clintonville 3 is the southernmost section of Clintonville. It has been identified as a Blueprint priority area due to high numbers of basement backup incidences and sanitary sewer overflows that discharge into the Walhalla Ravine and the Olentangy River.
  4. https://blueprintneighborhoods.com/the-four-pillars/lateral-lining/

    blueprintneighborhoods.com

    Accessed

    Supporting evidence (6)
    • According to program guidelines, crew members install a resin-filled liner from the city's main sewer through the home's lateral line to the cleanout, filling it with hot water so the material hardens in place to leave behind a new pipe.

      Read supporting passage
      Crew members install a resin-filled liner from the City’s main sewer, through the home’s lateral line, to the cleanout. The liner is filled with hot water so the liner can harden in place, leaving behind a new pipe.
    • Homeowners face no direct costs for the installation, which is paid for with revenue from city sewer bills.

      Read supporting passage
      There are no direct costs to the homeowner. Blueprint Columbus is a solution to a problem that affects the entire community and is being paid for with revenue from City sewer bills.
    • Once completed, a newly lined lateral carries an estimated life expectancy of 50 years, though property owners remain responsible for ongoing pipe maintenance.

      Read supporting passage
      A newly lined lateral has a life expectancy of 50 years, and the homeowner remains responsible for its maintenance.
    • Yard cleanouts: When crews need to install a cleanout near a house, they dig a 2-foot-by-2-foot hole down as far as the sewer lateral and install a PVC pipe from the surface to the lateral.

      Read supporting passage
      When crews need to install a cleanout near your house, a 2’ x 2’ hole will be dug down as far as the sewer lateral. A PVC pipe will be installed from the surface to the lateral.
    • Crews then restore the yard, often with the original turf, and the cleanout pipe can be level with the yard so it does not interfere with mowing.

      Read supporting passage
      Your yard will be restored, often with the original turf. The cleanout pipe can be level with the yard so it does not interfere with mowing.
    • Water pauses: During the lining process, residents are asked not to use water for up to four hours, including flushing toilets, laundry and showers.

      Read supporting passage
      The only interruption you may experience is during the actual lining process. You will be asked to not use any water for up to four hours (this includes flushing toilets, laundry, showers, etc.).
  5. 2918-2026 · To authorize the Director of Public Utilities to enter into a contract modification for Construction Administration and Inspection Services with Hatch Associates Consultants, Inc., for the Lateral Lining - Blueprint Clintonville 3 Project 1; to authorize the appropriation and expenditure

    columbus · legislation

    Published · Accessed

    Supporting evidence (2)
    • Legislation authorizes a contract modification of up to $1,560,000 with Hatch Associates Consultants, Inc. for construction administration and inspection services on the project.

      Read supporting passage
      To authorize the Director of Public Utilities to enter into a contract modification for Construction Administration and Inspection Services with Hatch Associates Consultants, Inc., for the Lateral Lining - Blueprint Clintonville 3 Project 1; to authorize the appropriation and expenditure of up to $1,560,000.00 from the Water Pollution Control Loan Fund for the contract; and to make the loan funded portion of this ordinance contingent upon the Ohio Water Development Authority approving a loan for the project. ($1,560,000.00)
    • Hatch Associates Consultants plans to subcontract with Resource International, Inc., Ascension Construction Solutions and Smoot Construction Company of Ohio.

      Read supporting passage
      Hatch Associates Consultants, Inc. plans to subcontract with the following companies: Name City/State Status Resource International, Inc. Columbus/OH WBE Ascension Construction Solutions Columbus/OH MBE Smoot Construction Company of Ohio Columbus/OH MBE
  6. Columbus Authorizes State Loan Pipeline for 61 Sewer and Stormwater Projects

    Published · Accessed

    Supporting evidence (1)
    • Previously, Pique Media reported that Columbus authorized a state loan pipeline for 61 sewer and stormwater projects.

      Read supporting passage
      Columbus Authorizes State Loan Pipeline for 61 Sewer and Stormwater Projects
  7. Columbus City Council Meeting

    City of Columbus on YouTube

    Published · Accessed

Take Pique with you

Your city. In your pocket.

Read local stories, watch the videos and explore the details in Pique.

QR code for Pique Media on the App Store

Get Pique for iPhone and iPad

Scan the code with your phone’s camera.

View on the App Store

Share this story