City Council approved a $99,984.57 renewal, bringing the total authorized contract amount to $749,984.57, to extend support for Columbus Water & Power's Work and Asset Management system through 2027 while a replacement remains years away.

How we know this

The sources and records behind this story, with the facts they support.

  1. 2961-2026 · To authorize the Director of Columbus Water & Power to renew the contract with Resource International, Inc. for Work and Asset Management (WAM) database and system administrative support; to authorize the transfer of $99,984.57 from within the Electricity, Water, Sanitary Sewer, and Stor

    columbus · legislation

    Published · Accessed

    Supporting evidence (16)
    • This ordinance authorizes the fourth renewal of the contract, adding $99,984.57 in funding and extending the agreement through Dec. 31, 2027.

      Read supporting passage
      This ordinance authorizes the fourth renewal of the contract, adding $99,984.57 of funding and extending the contract through December 31st, 2027, and is being submitted in accordance with the relevant provisions of Chapter 329 of City Code.
    • Columbus Water & Power has used a Work and Asset Management system since 2005, provided by Synergen, SPL, and then Oracle to manage and track maintenance, work, assets, and materials.

      Read supporting passage
      Since 2005, Columbus Water & Power (CWP) has been utilizing a Work and Asset Management system (WAM) provided by Synergen, SPL, and then Oracle to manage and track maintenance, work, assets and materials.
    • All of the department's divisions utilize the system, with the Department of Technology responsible for system oversight, centralized information technology functions, hardware and software support, and citywide integrations.

      Read supporting passage
      All of CWP’s divisions utilize the system, but the Department of Technology (DOT) is responsible for oversight and administration of the system, including centralized Information Technology (IT) functions, hardware and software support, email, security, and system integrations citywide.
    • The legislation authorizes an expenditure and transfer of $99,984.57 split among operating funds for Electricity, Water, Sanitary Sewer, and Stormwater.

      Read supporting passage
      to authorize the transfer of $99,984.57 from within the Electricity, Water, Sanitary Sewer, and Stormwater Operating Funds; and to authorize the expenditure of $99,984.57 split between the Electricity, Water, Sanitary Sewer, and Stormwater Operating Funds.
    • A project is in the works to replace the existing Oracle WAM system, but municipal records state that implementing a replacement could take several years, making continued use and support necessary.

      Read supporting passage
      A project is in the works to replace our existing Oracle WAM system. It could be several years before a new system is implemented so continued use and support is still necessary for our existing system.
    • The modification brings the total contract amount to $749,984.57.

      Read supporting passage
      Total contract amount including this modification is $749,984.57.
    • The ordinance authorizes the utility director to renew the agreement with Resource International, Inc. for database and system administrative support.

      Read supporting passage
      This ordinance authorizes the Director of Columbus Water & Power to renew an existing contract with Resource International, Inc. for Work and Asset Management database and system administrative support.
    • The explanation says the contract provides that support on an "as-needed" basis, and the services include maintenance and upkeep of hardware and software.

      Read supporting passage
      The purpose of this contract is to provide WAM database and system administration support for CWP on an “as-needed” basis. These services will include but are not limited to maintenance and upkeep of both hardware and software as suggested by CWP in collaboration with the DOT and Oracle.
    • Woolpert, Inc. is listed as the subcontractor.

      Read supporting passage
      Subcontractor: Woolpert, Inc.
    • Fiscal records show that $184,903.76 was spent in 2024.

      Read supporting passage
      Fiscal Impact: $99,984.57 is available from within Columbus Water & Power's funds to meet the financial obligations of this contract. A transfer of appropriation between object classes is required. $191,086.40 was spent in 2025 $184,903.76 was spent in 2024
    • In addition, records show that $191,086.40 was spent in 2025.

      Read supporting passage
      $191,086.40 was spent in 2025
    • The contract originated from a late 2021 solicitation when Columbus Water & Power solicited competitive proposals and received one responsive bid.

      Read supporting passage
      Columbus Water & Power solicited competitive proposals through Vendor Services and Bonfire from November 15th, 2021, to December 17th, 2021, for Work and Asset Management database and system administrative support in accordance with the relevant provisions of Chapter 329 of City Code, RFQ020377. One bid was received and was deemed responsive.
    • An evaluation committee selected Resource International after determining it offered the strongest proposal based on team experience and departmental needs.

      Read supporting passage
      The evaluation committee determined that Resource International, Inc. submitted the strongest proposal because of the relevant experience of its project team, its understanding of the Department’s needs, and presented a tailored approach to address those needs.
    • Council authorized an initial $250,000 contract through May 31, 2023, with options for four annual renewals.

      Read supporting passage
      The original term of the contract was for a period of one-year from the date of execution by the City of Columbus, up to and including May 31st, 2023, with yearly renewal options for an additional four years, for a maximum approved contract length of five years, on a year-by-year basis, authorized by Ordinance 0743-2022. The contract amount authorized was $250,000.00.
    • Subsequent council action added $300,000 in 2023 to align renewals with the calendar year, followed by an unfunded second renewal and a $100,000 third renewal for 2026.

      Read supporting passage
      Ordinance 2937-2023 authorized the first modification increasing the funding allocations by $300,000.00 and extending the contract through December 31st, 2024, allowing future renewals or modifications to be on a calendar-year cycle. Ordinance 2863-2024 authorized the second renewal option, without funding, extending the contract through December 31st, 2025. Ordinance 3141-2025 authorized the third renewal option, increasing funding allocations by $100,000.00 and extending the contract through December 31st, 2026.
    • The ordinance authorizes a transfer of $99,984.57 between object classes within the Public Utilities Operating Fund, split among the Electricity, Water, Sanitary Sewer, and Stormwater Operating Funds.

      Read supporting passage
      SECTION 5. That the transfer of $99,984.57 or so much thereof as may be needed, is hereby authorized between object classes within the Public Utilities Operating Fund, split among the Electricity, Water, Sanitary Sewer, and Stormwater Operating Funds, per the accounting codes in the attachment to this ordinance.

Take Pique with you

Your city. In your pocket.

Read local stories, watch the videos and explore the details in Pique.

QR code for Pique Media on the App Store

Get Pique for iPhone and iPad

Scan the code with your phone’s camera.

View on the App Store

Share this story