Columbus Advances $2.16 Million Jackson Pike Roof Contract Over Plant Failure Risk
Columbus City Council moved the 30-day contract measure with Harold J. Becker Company to second reading after utility officials warned roof leaks could disable the wastewater plant.
Columbus City Council on Nov. 16 held a first reading on a $2.16 million ($2,155,200) construction contract with Harold J. Becker Company, Inc. for roof replacements at the Jackson Pike Water Reclamation Plant. The 30-day ordinance now sits at second reading in the Public Utilities and Sustainability Committee and also sets aside $2,000 for prevailing wage services, bringing total planned spending to $2,157,200.
Aerial view of the Jackson Pike Wastewater Treatment Plant along the Scioto River corridor in Columbus, Ohio. (David E. Lucas / Wikimedia Commons)
Credit: David E. Lucas / Wikimedia Commons Image source
The project covers the Skimmings Concentration and Sludge Control buildings at the Far South facility, where city filings report the roof is showing signs of failure and must be replaced along with edge metal and lightning protection. Columbus Water & Power warned in the ordinance that water intrusion impacting the Sludge Control Building's server room and electrical gear would disable the entire facility, creating substantial environmental impacts for Columbus residents. Construction must finish within 390 days of the city's notice to proceed.
City officials advertised the project from Aug. 6 through Sept. 30 and opened two bids on Sept. 30. Harold J. Becker Company, of 1776 Lone Eagle St. in Columbus, submitted the $2,155,200 winning bid, which includes a 20% construction contingency. Columbus-based General Maintenance & Engineering Co. submitted the other of the two bids at $2,337,600.
Harold J. Becker's city contract compliance status runs through Aug. 31, 2028, and federal exclusion and state recovery searches turned up no findings against the company. The contractor meets city prequalification rules, while its proposed subcontractor, Columbus-based Robert Service Group, applied for construction prequalification on Oct. 22 and is expected to receive approval before the contract is signed. City records note no community outreach was completed during project development.
Contract funding relies on a reimbursement loan from the Ohio Water Development Authority's Direct Loan Program, under borrowing authority City Council approved in March, with approval expected at the state board's December meeting. Under that program, Columbus Water & Power will pay contractor invoices first and seek state reimbursement. OWDA lists its next board meeting for Dec. 10 at 10:30 a.m. at 480 S. High St. in Columbus.
Previously, Pique Media reported on Nov. 16 that Columbus advanced $4.44 million in oversight contracts for Jackson Pike clarifier upgrades.
Pique’s reporting on the same events, newest first.
Far South Latest You are reading
Columbus Advances $2.16 Million Jackson Pike Roof Contract Over Plant Failure Risk
Southwest
Columbus Advances $4.44 Million in Oversight Contracts for Jackson Pike Clarifier Upgrades
City Council moved engineering and construction-management measures to second reading alongside a $32.17 million construction contract, bringing proposed spending to $36.61 million while state loan timelines diverge.
How we know this
The sources and records behind this story, with the facts they support.
https://webapi.legistar.com/v1/columbus/matters/138982/histories
Supporting evidence (1)
Columbus City Council on Nov. 16 held a first reading on a $2.16 million ($2,155,200) construction contract with Harold J. Becker Company, Inc. for roof replacements at the Jackson Pike Water Reclamation Plant.
Read supporting passage
"MatterHistoryActionDate" : "2026-11-16T17:00:00", "MatterHistoryActionId" : 5, "MatterHistoryActionName" : "Read for the First Time", "MatterHistoryActionText" : "Read for the First Time", "MatterHistoryActionBodyId" : 27, "MatterHistoryActionBodyName" : "Columbus City Council"
https://webapi.legistar.com/v1/columbus/matters/138982/texts/138589
Supporting evidence (21)
Columbus City Council on Nov. 16 held a first reading on a $2.16 million ($2,155,200) construction contract with Harold J. Becker Company, Inc. for roof replacements at the Jackson Pike Water Reclamation Plant.
Read supporting passage
This ordinance authorizes the Director of Columbus Water & Power to enter into a construction contract with Harold J. Becker Company, Inc. for the Jackson Pike Water Reclamation Plant Skimmings Concentration and Sludge Control Buildings Roof Replacement project, CIP #650234-100203, in an amount up to $2,155,200.00
The 30-day ordinance now sits at second reading in the Public Utilities and Sustainability Committee and also sets aside $2,000 for prevailing wage services, bringing total planned spending to $2,157,200.
Read supporting passage
to encumber funds with the Department of Public Service for prevailing wage services in an amount up to $2,000.00, for a total expenditure of $2,157,200.00.
The project covers the Skimmings Concentration and Sludge Control buildings at the Far South facility, where city filings report the roof is showing signs of failure and must be replaced along with edge metal and lightning protection.
Read supporting passage
Planning Area - 64 Far South
The project covers the Skimmings Concentration and Sludge Control buildings at the Far South facility, where city filings report the roof is showing signs of failure and must be replaced along with edge metal and lightning protection.
Read supporting passage
The roof of the Sludge Control and Skimmings Buildings house which stores critical equipment for the successful operation of Jackson Pike Water Reclamation Plant is exhibiting signs of failure and requires replacement. The project will replace the roof, edge metal, and lightning protection on the Jackson Pike WRP Sludge Control and Skimmings Concentration Buildings to ensure the plant remains operational.
Columbus Water & Power warned in the ordinance that water intrusion impacting the Sludge Control Building's server room and electrical gear would disable the entire facility, creating substantial environmental impacts for Columbus residents.
Read supporting passage
This ordinance authorizes the Director of Columbus Water & Power to enter into a construction contract with Harold J. Becker Company, Inc. for the Jackson Pike Water Reclamation Plant Skimmings Concentration and Sludge Control Buildings Roof Replacement project, CIP #650234-100203, in an amount up to $2,155,200.00
Columbus Water & Power warned in the ordinance that water intrusion impacting the Sludge Control Building's server room and electrical gear would disable the entire facility, creating substantial environmental impacts for Columbus residents.
Read supporting passage
The entire Jackson Pike Water Reclamation Plant would fail to function if the server room and electrical gear located in the Sludge Control Building were impacted by water intrusion, so the environmental impacts of failing to execute this work are substantial for the citizens of Columbus.
Construction must finish within 390 days of the city's notice to proceed.
Read supporting passage
Contract work is required to be completed in a manner acceptable to the City within 390 days from the date that a Notice to Proceed (NTP) is given by the City.
City officials advertised the project from Aug. 6 through Sept. 30 and opened two bids on Sept. 30.
Read supporting passage
This project was formally advertised on the Vendor Services and Bid Express websites from 8/6/2026 through 9/30/2026. Two bids were received:
City officials advertised the project from Aug. 6 through Sept. 30 and opened two bids on Sept. 30.
Read supporting passage
two bids for the Jackson Pike Water Reclamation Plant Skimmings Concentration and Sludge Control Buildings Roof Replacement project were received and opened on 9/30/2026
Harold J. Becker Company, of 1776 Lone Eagle St. in Columbus, submitted the $2,155,200 winning bid, which includes a 20% construction contingency.
Read supporting passage
Harold J. Becker Company, Inc.,1776 Lone Eagle Street, Columbus, OH 43228
Harold J. Becker Company, of 1776 Lone Eagle St. in Columbus, submitted the $2,155,200 winning bid, which includes a 20% construction contingency.
Read supporting passage
Harold J. Becker Company, Inc’s bid was deemed the lowest, best, most responsive and responsible bid in the amount of $2,155,200.00
Harold J. Becker Company, of 1776 Lone Eagle St. in Columbus, submitted the $2,155,200 winning bid, which includes a 20% construction contingency.
Read supporting passage
The bid amount and proposed award amount is $2,155,200.00 including a 20% construction contingency amount that will be utilized to fund needed and approved changes in the work.
Columbus-based General Maintenance & Engineering Co. submitted the other of the two bids at $2,337,600.
Read supporting passage
General Maintenance & Engineering Co.\t$2,337,600.00\t\tColumbus, OH\t\tMAJ
Columbus-based General Maintenance & Engineering Co. submitted the other of the two bids at $2,337,600.
Read supporting passage
This project was formally advertised on the Vendor Services and Bid Express websites from 8/6/2026 through 9/30/2026. Two bids were received:
Harold J. Becker's city contract compliance status runs through Aug. 31, 2028, and federal exclusion and state recovery searches turned up no findings against the company.
Read supporting passage
Harold J. Becker Company, Inc.’s contract compliance number is CC004161 and expires 8/31/2028.
Harold J. Becker's city contract compliance status runs through Aug. 31, 2028, and federal exclusion and state recovery searches turned up no findings against the company.
Read supporting passage
Searches in the Excluded Party List System (Federal) and the Findings for Recovery list (State) produced no findings against Harold J. Becker Company, In.
The contractor meets city prequalification rules, while its proposed subcontractor, Columbus-based Robert Service Group, applied for construction prequalification on Oct. 22 and is expected to receive approval before the contract is signed.
Read supporting passage
Harold J. Becker Company, Inc. have met code requirements with respect to pre-qualification, pursuant to relevant sections of Columbus City Code Chapter 329. Robert Service Group application for construction prequalification was submitted October 22, 2026 and should be approved prior to execution of contract.
The contractor meets city prequalification rules, while its proposed subcontractor, Columbus-based Robert Service Group, applied for construction prequalification on Oct. 22 and is expected to receive approval before the contract is signed.
Read supporting passage
Robert Service Group\t\t\t\tColumbus, Ohio\t\tWBE
City records note no community outreach was completed during project development.
Read supporting passage
No community outreach was completed during development of this replacement project.
Contract funding relies on a reimbursement loan from the Ohio Water Development Authority's Direct Loan Program, under borrowing authority City Council approved in March, with approval expected at the state board's December meeting.
Read supporting passage
Funding for the construction contract will be obtained through the Ohio Water Development Authority (OWDA) Direct Loan Program. City Council authorized this loan application and acceptance of loan funding via Ordinance 0341-2026, passed by Council on 3/2/2026. This ordinance is contingent upon the approval of this loan. This loan is expected to be approved at the OWDA December Board meeting.
Under that program, Columbus Water & Power will pay contractor invoices first and seek state reimbursement.
Read supporting passage
Columbus Water & Power will need to pay invoices directly to Harold J. Becker Company, Inc. and then submit reimbursement requests based upon these paid invoices to OWDA for OWDA to reimburse Columbus Water & Power
https://webapi.legistar.com/v1/columbus/matters/138982
Supporting evidence (2)
The 30-day ordinance now sits at second reading in the Public Utilities and Sustainability Committee and also sets aside $2,000 for prevailing wage services, bringing total planned spending to $2,157,200.
Read supporting passage
"MatterReference" : "30-Days"
The 30-day ordinance now sits at second reading in the Public Utilities and Sustainability Committee and also sets aside $2,000 for prevailing wage services, bringing total planned spending to $2,157,200.
Read supporting passage
"MatterStatusName" : "Second Reading", "MatterBodyId" : 283, "MatterBodyName" : "Public Utilities & Sustainability Committee"
Supporting evidence (1)
OWDA lists its next board meeting for Dec. 10 at 10:30 a.m. at 480 S. High St. in Columbus.
Read supporting passage
Thursday, December 10, 2026, at 10:30 a.m. at the Ohio Water Development Authority, 480 South High Street, Columbus, Ohio.
Columbus Advances $4.44 Million in Oversight Contracts for Jackson Pike Clarifier Upgrades
Supporting evidence (1)
Previously, Pique Media reported on Nov. 16 that Columbus advanced $4.44 million in oversight contracts for Jackson Pike clarifier upgrades.
Read supporting passage
Columbus Advances $4.44 Million in Oversight Contracts for Jackson Pike Clarifier Upgrades