Columbus Advances $4.44 Million in Oversight Contracts for Jackson Pike Clarifier Upgrades
City Council moved engineering and construction-management measures to second reading alongside a $32.17 million construction contract, bringing proposed spending to $36.61 million while state loan timelines diverge.
At its Nov. 16 regular meeting, Columbus City Council took up on first reading three Jackson Pike ordinances—for Wade Trim, Inc., Ascension Construction Solutions, LLC and Kenmore Construction Co., Inc.—which now sit at second reading in the Public Utilities and Sustainability Committee, including Ascension's measure. The two oversight contracts total $4,441,376.10 ($4.44 million)—$2,378,384.05 for engineering services with Wade Trim, Inc. and $2,062,992.05 for construction management with Ascension Construction Solutions, LLC—for the Jackson Pike Wastewater Treatment Plant secondary clarifier electrical upgrades in southwest Columbus, where Ascension's scope covers the same project. Alongside those two contracts, the $32,167,000 ordinance ($32.17 million) at second reading authorizes a construction contract with Kenmore Construction Co., Inc. for the Jackson Pike A-Plant secondary clarifier electrical upgrades.
Treatment basins and catwalks at the City of Columbus Jackson Pike Wastewater Treatment Plant in southwest Columbus. (Burgess & Niple)
Credit: Burgess & Niple Image source
Adding the $32,167,000 Kenmore Construction, $2,378,384.05 Wade Trim and $2,062,992.05 Ascension measures totals $36,608,376.10 ($36.61 million) in proposed Jackson Pike spending across the three 30-day ordinances at second reading in the Public Utilities and Sustainability Committee, including Ascension's measure. Wade Trim's earlier contracts for the project added $766,156.05 for preliminary design and $1,741,676.74 for detailed design, bringing Wade Trim's total engineering contract to $4,886,216.84. Adding the $4,886,216.84 Wade Trim total, $32,167,000 construction ordinance and $2,062,992.05 Ascension modification brings total proposed Jackson Pike clarifier spending to $39,116,208.89 ($39.12 million).
Contract and cost breakdown
- Construction ($32,167,000): City legislation authorizes a contract up to $32,165,000 with Akron-based Kenmore Construction Co., Inc., including a 10% construction contingency, plus up to $2,000 from the Sanitary Bond Fund for Department of Public Service prevailing wage services. Kenmore submitted the sole bid when proposals opened Sept. 30 after a solicitation advertised from Aug. 10 through Sept. 30, and its city contract compliance certification expired Nov. 4 after being in good standing at bid award.
- Construction-phase engineering ($2,378,384.05): A planned modification with Wade Trim, Inc. funds Step 3 engineering services during construction, with a proposed fee of $2,378,384.05 including a 10% contingency that brings the firm's cumulative contract total to $4,886,216.84. Wade Trim's work includes interpreting contract documents, reviewing contractor submittals and change requests, condemning nonconforming work and supporting plant startup and commissioning.
- Construction management ($2,062,992.05): A seventh modification with Columbus-based Ascension Construction Solutions covers construction inspection, coordination, budgeting, scheduling and document tracking to provide quality control and minimize construction claims.
Why clarifier electrical upgrades matter
Aerial view of the Jackson Pike Wastewater Treatment Plant complex showing circular secondary clarifiers and rectangular treatment basins along the Scioto River corridor. (David E. Lucas / Wikimedia Commons)
Credit: David E. Lucas / Wikimedia Commons Image source
Secondary clarification is one of the final steps in treating the wet wastewater stream at Jackson Pike, removing biological settleable solids before treated water leaves the plant. According to Columbus Water & Power legislation, equipment failure would stop collection of settleable solids in the secondary clarifiers, causing tanks to fill and overflow solids into the plant's final effluent and risking a violation and potential hazards.
The upgrades are also intended to curb corrosion and odor tied to the existing secondary treatment equipment. Construction will require substantial completion within 1,095 calendar days and final completion within 1,125 calendar days—roughly three years—of a notice to proceed anticipated around January 2027.
How the management contract grew
Columbus Water & Power manages construction oversight for its wastewater plants through a four-year rolling contract with Ascension Construction Solutions covering fiscal years 2025 through 2028. Because future construction projects were not known when the original $1,000,000 contract was put into place in 2025, the city assigns projects through planned contract modifications.
Across seven modifications—six earlier 2026 additions ranging from $337,305.36 to $1,989,574.00 plus the seventh modification of $2,062,992.05 for the Jackson Pike clarifier project—the contract's proposed total has reached $11,178,638.97.
Pending state loans and filing discrepancies
All three ordinances rely on loans from the Water Pollution Control Loan Fund, a program jointly administered by the Ohio EPA and the Ohio Water Development Authority under a Dec. 15, 2025 borrowing authorization from City Council. Each measure states that the ordinance is contingent upon OWDA board approval of the loan.
However, the three filings state divergent timelines for when the state board will approve those loans:
- October 2026 cited for engineering: The Wade Trim ordinance states its loan is expected to be approved at the October OWDA board meeting. Yet OWDA's public summary for its Oct. 29 meeting reports over $42.3 million in Fresh Water Loan Fund awards across seven Ohio projects, including two Columbus waterline loans in the Kent and Fairwood and Yale Avenue service areas. OWDA's October summary lists those two Columbus waterline projects alongside awards for Forest, the Mahoning Valley Sanitary District, Rittman, South Zanesville and Tuscarawas County. OWDA's Board Meeting Materials page posts January 2026 and September 2026 Board Minutes and notes that the board approves minutes from the previous month's board meeting each month.
- December 2026 cited for construction: The Kenmore Construction ordinance anticipates loan approval at the OWDA December meeting, which OWDA has scheduled for Thursday, Dec. 10 in Columbus, with meeting materials expected the week of Dec. 7.
- January 2027 cited for management: The Ascension modification states its loan is expected to go before the OWDA board in January 2027, the same month Columbus Water & Power anticipates issuing the construction notice to proceed.
The Wade Trim legislation also contains an internal scope discrepancy: while the explanation section states that preliminary and detailed design are already complete and that the $2.38 million modification funds Step 3 construction-phase services, one recital in the ordinance body states the additional funding is needed "to fund detailed design of the project."
Previously, Pique Media reported on Nov. 13 that Columbus is considering a $32.2 million contract for Jackson Pike clarifier upgrades.
Pique’s reporting on the same events, newest first.
Far South Latest
Columbus Advances $2.16 Million Jackson Pike Roof Contract Over Plant Failure Risk
Columbus City Council moved the 30-day contract measure with Harold J. Becker Company to second reading after utility officials warned roof leaks could disable the wastewater plant.
Far East
Columbus Council Advances Eminent Domain Measure for East Broad Street Phase 2
Monday's first reading moves an ordinance authorizing up to $492,052 and eminent domain complaints across 10 parcel groups east of I-270 to second reading.
Southwest You are reading
Columbus Advances $4.44 Million in Oversight Contracts for Jackson Pike Clarifier Upgrades
Columbus
Certification, 2027 Filing Rules and Redistricting Next for Columbus City Council
Unofficial Nov. 3 returns show voters approved both Issues 8 and 9, putting a two-stage expansion to 13 seats, updated 2027 candidate rules and a March 1 redistricting deadline ahead for Columbus.
Columbus
Columbus Considers $32.2 Million Contract for Jackson Pike Clarifier Upgrades
Legislation authorizing a sole-bid award to Kenmore Construction would modernize secondary clarifier electrical systems to protect river water quality.
How we know this
The sources and records behind this story, with the facts they support.
https://columbus.legistar.com/View.ashx?M=AADA&ID=1462557&GUID=4710A3EC-24ED-4643-ACA5-0F9C833E0D69
Supporting evidence (3)
At its Nov. 16 regular meeting, Columbus City Council took up on first reading three Jackson Pike ordinances—for Wade Trim, Inc., Ascension Construction Solutions, LLC and Kenmore Construction Co., Inc.
Read supporting passage
REGULAR MEETING NO. 51 OF COLUMBUS CITY COUNCIL, NOVEMBER 16, 2026
At its Nov. 16 regular meeting, Columbus City Council took up on first reading three Jackson Pike ordinances—for Wade Trim, Inc., Ascension Construction Solutions, LLC and Kenmore Construction Co., Inc.
Read supporting passage
FR FIRST READING OF 30-DAY LEGISLATION
Adding the $32,167,000 Kenmore Construction, $2,378,384.05 Wade Trim and $2,062,992.05 Ascension measures totals $36,608,376.10 ($36.61 million) in proposed Jackson Pike spending across the three 30-day ordinances at second reading in the Public Utilities and Sustainability Committee, including Ascension's measure.
Read supporting passage
FR FIRST READING OF 30-DAY LEGISLATION
Supporting evidence (19)
At its Nov. 16 regular meeting, Columbus City Council took up on first reading three Jackson Pike ordinances—for Wade Trim, Inc., Ascension Construction Solutions, LLC and Kenmore Construction Co., Inc.
Read supporting passage
To authorize the Director of Columbus Water & Power to enter into a construction contract with Kenmore Construction Co., Inc. for the Jackson Pike A-Plant Secondary Clarifier Electrical Upgrades project; to authorize the appropriation and expenditure of $32,165,000.00 within the Sanitary Revolving Loan Fund to pay for the contract; to make this ordinance contingent upon the Ohio Water Development Authority approving a loan for this project; and to authorize the expenditure of up to $2,000.00 from the Sanitary Bond Fund to pay the Department of Public Service for prevailing wage services. ($32,167,000.00)
—which now sit at second reading in the Public Utilities and Sustainability Committee, including Ascension's measure.
Read supporting passage
{Body=Public Utilities & Sustainability Committee, Content type=Legislation, Document coverage=API text and document metadata; linked PDF bytes are not retained, File=2941-2026, Legislation type=Ordinance, Municipality=columbus, Status=Second Reading, Text version=1}
Alongside those two contracts, the $32,167,000 ordinance ($32.17 million) at second reading authorizes a construction contract with Kenmore Construction Co., Inc. for the Jackson Pike A-Plant secondary clarifier electrical upgrades.
Read supporting passage
To authorize the Director of Columbus Water & Power to enter into a construction contract with Kenmore Construction Co., Inc. for the Jackson Pike A-Plant Secondary Clarifier Electrical Upgrades project; to authorize the appropriation and expenditure of $32,165,000.00 within the Sanitary Revolving Loan Fund to pay for the contract; to make this ordinance contingent upon the Ohio Water Development Authority approving a loan for this project; and to authorize the expenditure of up to $2,000.00 from the Sanitary Bond Fund to pay the Department of Public Service for prevailing wage services. ($32,167,000.00)
Alongside those two contracts, the $32,167,000 ordinance ($32.17 million) at second reading authorizes a construction contract with Kenmore Construction Co., Inc. for the Jackson Pike A-Plant secondary clarifier electrical upgrades.
Read supporting passage
{Body=Public Utilities & Sustainability Committee, Content type=Legislation, Document coverage=API text and document metadata; linked PDF bytes are not retained, File=2941-2026, Legislation type=Ordinance, Municipality=columbus, Status=Second Reading, Text version=1}
Adding the $32,167,000 Kenmore Construction, $2,378,384.05 Wade Trim and $2,062,992.05 Ascension measures totals $36,608,376.10 ($36.61 million) in proposed Jackson Pike spending across the three 30-day ordinances at second reading in the Public Utilities and Sustainability Committee, including Ascension's measure.
Read supporting passage
To authorize the Director of Columbus Water & Power to enter into a construction contract with Kenmore Construction Co., Inc. for the Jackson Pike A-Plant Secondary Clarifier Electrical Upgrades project; to authorize the appropriation and expenditure of $32,165,000.00 within the Sanitary Revolving Loan Fund to pay for the contract; to make this ordinance contingent upon the Ohio Water Development Authority approving a loan for this project; and to authorize the expenditure of up to $2,000.00 from the Sanitary Bond Fund to pay the Department of Public Service for prevailing wage services. ($32,167,000.00)
Adding the $32,167,000 Kenmore Construction, $2,378,384.05 Wade Trim and $2,062,992.05 Ascension measures totals $36,608,376.10 ($36.61 million) in proposed Jackson Pike spending across the three 30-day ordinances at second reading in the Public Utilities and Sustainability Committee, including Ascension's measure.
Read supporting passage
{Body=Public Utilities & Sustainability Committee, Content type=Legislation, Document coverage=API text and document metadata; linked PDF bytes are not retained, File=2941-2026, Legislation type=Ordinance, Municipality=columbus, Status=Second Reading, Text version=1}
Adding the $4,886,216.84 Wade Trim total, $32,167,000 construction ordinance and $2,062,992.05 Ascension modification brings total proposed Jackson Pike clarifier spending to $39,116,208.89 ($39.12 million).
Read supporting passage
To authorize the Director of Columbus Water & Power to enter into a construction contract with Kenmore Construction Co., Inc. for the Jackson Pike A-Plant Secondary Clarifier Electrical Upgrades project; to authorize the appropriation and expenditure of $32,165,000.00 within the Sanitary Revolving Loan Fund to pay for the contract; to make this ordinance contingent upon the Ohio Water Development Authority approving a loan for this project; and to authorize the expenditure of up to $2,000.00 from the Sanitary Bond Fund to pay the Department of Public Service for prevailing wage services. ($32,167,000.00)
Construction ($32,167,000): City legislation authorizes a contract up to $32,165,000 with Akron-based Kenmore Construction Co., Inc., including a 10% construction contingency, plus up to $2,000 from the Sanitary Bond Fund for Department of Public Service prevailing wage services.
Read supporting passage
To authorize the Director of Columbus Water & Power to enter into a construction contract with Kenmore Construction Co., Inc. for the Jackson Pike A-Plant Secondary Clarifier Electrical Upgrades project; to authorize the appropriation and expenditure of $32,165,000.00 within the Sanitary Revolving Loan Fund to pay for the contract; to make this ordinance contingent upon the Ohio Water Development Authority approving a loan for this project; and to authorize the expenditure of up to $2,000.00 from the Sanitary Bond Fund to pay the Department of Public Service for prevailing wage services. ($32,167,000.00)
Construction ($32,167,000): City legislation authorizes a contract up to $32,165,000 with Akron-based Kenmore Construction Co., Inc., including a 10% construction contingency, plus up to $2,000 from the Sanitary Bond Fund for Department of Public Service prevailing wage services.
Read supporting passage
That the Director of Columbus Water & Power is hereby authorized to enter into a construction contract for the Jackson Pike A-Plant Secondary Clarifier Electrical Upgrades project with Kenmore Construction Co., Inc, 700 Home Rd. Akron, OH 44310; in an amount up $32,165,000.00
Construction ($32,167,000): City legislation authorizes a contract up to $32,165,000 with Akron-based Kenmore Construction Co., Inc., including a 10% construction contingency, plus up to $2,000 from the Sanitary Bond Fund for Department of Public Service prevailing wage services.
Read supporting passage
The bid amount and proposed award amount is $32,165,000.00, including a 10% construction contingency amount that will be utilized to fund needed and approved changes in the work.
Kenmore submitted the sole bid when proposals opened Sept. 30 after a solicitation advertised from Aug. 10 through Sept. 30, and its city contract compliance certification expired Nov. 4 after being in good standing at bid award.
Read supporting passage
An Invitation for Bids for the Jackson Pike A-Plant Secondary Clarifier Electrical Upgrades project was advertised on the Vendor Services and Bid Express websites from August 10, 2026, through September 30, 2026. One bid was received for the project and opened on September 30, 2026.
Kenmore submitted the sole bid when proposals opened Sept. 30 after a solicitation advertised from Aug. 10 through Sept. 30, and its city contract compliance certification expired Nov. 4 after being in good standing at bid award.
Read supporting passage
Kenmore Construction Co., Inc.’s contract compliance number is CC006456 and expires 11/4/2026.
Kenmore submitted the sole bid when proposals opened Sept. 30 after a solicitation advertised from Aug. 10 through Sept. 30, and its city contract compliance certification expired Nov. 4 after being in good standing at bid award.
Read supporting passage
The certification of Kenmore Construction Co., Inc. was in good standing at the time the bid was awarded.
According to Columbus Water & Power legislation, equipment failure would stop collection of settleable solids in the secondary clarifiers, causing tanks to fill and overflow solids into the plant's final effluent and risking a violation and potential hazards.
Read supporting passage
To authorize the Director of Columbus Water & Power to enter into a construction contract with Kenmore Construction Co., Inc. for the Jackson Pike A-Plant Secondary Clarifier Electrical Upgrades project; to authorize the appropriation and expenditure of $32,165,000.00 within the Sanitary Revolving Loan Fund to pay for the contract; to make this ordinance contingent upon the Ohio Water Development Authority approving a loan for this project; and to authorize the expenditure of up to $2,000.00 from the Sanitary Bond Fund to pay the Department of Public Service for prevailing wage services. ($32,167,000.00)
Construction will require substantial completion within 1,095 calendar days and final completion within 1,125 calendar days—roughly three years—of a notice to proceed anticipated around January 2027.
Read supporting passage
TIMELINE: All work shall be substantially complete within 1095 calendar days of Notice to Proceed, with final completion to occur within 1125 calendar days. The City anticipates issuing a Notice to Proceed on or about January 2027.
All three ordinances rely on loans from the Water Pollution Control Loan Fund, a program jointly administered by the Ohio EPA and the Ohio Water Development Authority under a Dec. 15, 2025 borrowing authorization from City Council.
Read supporting passage
The construction portion of this project is anticipated to be financed with a loan from the Water Pollution Control Loan Fund (WPCLF), a program jointly administered by the Ohio EPA's Division of Environmental and Financial Assistance and the Ohio Water Development Authority (OWDA). City Council authorized this loan application and acceptance of funding via Ordinance 3119-2025, passed by Council on 12/15/25. This loan is expected to be approved at the OWDA December Board meeting. This ordinance is contingent upon the loan being approved by OWDA.
Each measure states that the ordinance is contingent upon OWDA board approval of the loan.
Read supporting passage
The construction portion of this project is anticipated to be financed with a loan from the Water Pollution Control Loan Fund (WPCLF), a program jointly administered by the Ohio EPA's Division of Environmental and Financial Assistance and the Ohio Water Development Authority (OWDA). City Council authorized this loan application and acceptance of funding via Ordinance 3119-2025, passed by Council on 12/15/25. This loan is expected to be approved at the OWDA December Board meeting. This ordinance is contingent upon the loan being approved by OWDA.
December 2026 cited for construction: The Kenmore Construction ordinance anticipates loan approval at the OWDA December meeting, which OWDA has scheduled for Thursday, Dec. 10 in Columbus, with meeting materials expected the week of Dec. 7.
Read supporting passage
The construction portion of this project is anticipated to be financed with a loan from the Water Pollution Control Loan Fund (WPCLF), a program jointly administered by the Ohio EPA's Division of Environmental and Financial Assistance and the Ohio Water Development Authority (OWDA). City Council authorized this loan application and acceptance of funding via Ordinance 3119-2025, passed by Council on 12/15/25. This loan is expected to be approved at the OWDA December Board meeting. This ordinance is contingent upon the loan being approved by OWDA.
January 2027 cited for management: The Ascension modification states its loan is expected to go before the OWDA board in January 2027, the same month Columbus Water & Power anticipates issuing the construction notice to proceed.
Read supporting passage
TIMELINE: All work shall be substantially complete within 1095 calendar days of Notice to Proceed, with final completion to occur within 1125 calendar days. The City anticipates issuing a Notice to Proceed on or about January 2027.
Supporting evidence (23)
At its Nov. 16 regular meeting, Columbus City Council took up on first reading three Jackson Pike ordinances—for Wade Trim, Inc., Ascension Construction Solutions, LLC and Kenmore Construction Co., Inc.
Read supporting passage
BE IT ORDAINED BY THE COUNCIL OF THE CITY OF COLUMBUS:
At its Nov. 16 regular meeting, Columbus City Council took up on first reading three Jackson Pike ordinances—for Wade Trim, Inc., Ascension Construction Solutions, LLC and Kenmore Construction Co., Inc.
Read supporting passage
This ordinance authorizes the Director of Columbus Water & Power to enter into a planned contract modification for professional engineering services with Wade Trim, Inc. for the Jackson Pike Wastewater Treatment Plant (JPWWTP) A-Plant Secondary Clarifier Electrical Upgrades & Miscellaneous Improvements, CIP #650245-100002, in an amount up to $2,378,384.05.
—which now sit at second reading in the Public Utilities and Sustainability Committee, including Ascension's measure.
Read supporting passage
{Body=Public Utilities & Sustainability Committee, Content type=Legislation, Document coverage=API text and document metadata; linked PDF bytes are not retained, File=2965-2026, Legislation type=Ordinance, Municipality=columbus, Status=Second Reading, Text version=1}
The two oversight contracts total $4,441,376.10 ($4.44 million)—$2,378,384.05 for engineering services with Wade Trim, Inc. and $2,062,992.05 for construction management with Ascension Construction Solutions, LLC—for the Jackson Pike Wastewater Treatment Plant secondary clarifier electrical upgrades in southwest Columbus, where Ascension's scope covers the same project.
Read supporting passage
This ordinance authorizes the Director of Columbus Water & Power to enter into a planned contract modification for professional engineering services with Wade Trim, Inc. for the Jackson Pike Wastewater Treatment Plant (JPWWTP) A-Plant Secondary Clarifier Electrical Upgrades & Miscellaneous Improvements, CIP #650245-100002, in an amount up to $2,378,384.05.
The two oversight contracts total $4,441,376.10 ($4.44 million)—$2,378,384.05 for engineering services with Wade Trim, Inc. and $2,062,992.05 for construction management with Ascension Construction Solutions, LLC—for the Jackson Pike Wastewater Treatment Plant secondary clarifier electrical upgrades in southwest Columbus, where Ascension's scope covers the same project.
Read supporting passage
The community planning area for this project is 59 - Southwest
Adding the $32,167,000 Kenmore Construction, $2,378,384.05 Wade Trim and $2,062,992.05 Ascension measures totals $36,608,376.10 ($36.61 million) in proposed Jackson Pike spending across the three 30-day ordinances at second reading in the Public Utilities and Sustainability Committee, including Ascension's measure.
Read supporting passage
This ordinance authorizes the Director of Columbus Water & Power to enter into a planned contract modification for professional engineering services with Wade Trim, Inc. for the Jackson Pike Wastewater Treatment Plant (JPWWTP) A-Plant Secondary Clarifier Electrical Upgrades & Miscellaneous Improvements, CIP #650245-100002, in an amount up to $2,378,384.05.
Adding the $32,167,000 Kenmore Construction, $2,378,384.05 Wade Trim and $2,062,992.05 Ascension measures totals $36,608,376.10 ($36.61 million) in proposed Jackson Pike spending across the three 30-day ordinances at second reading in the Public Utilities and Sustainability Committee, including Ascension's measure.
Read supporting passage
{Body=Public Utilities & Sustainability Committee, Content type=Legislation, Document coverage=API text and document metadata; linked PDF bytes are not retained, File=2965-2026, Legislation type=Ordinance, Municipality=columbus, Status=Second Reading, Text version=1}
Wade Trim's earlier contracts for the project added $766,156.05 for preliminary design and $1,741,676.74 for detailed design, bringing Wade Trim's total engineering contract to $4,886,216.84.
Read supporting passage
negotiated fee for Step 1 - Preliminary Design was $766,156.05, including a 10% contingency amount. The negotiated fee for Step 2 - Detailed Design was $1,741,676.74 including a 10% contingency amount that will be utilized to fund needed and approved changes in the work. The negotiated and proposed fee for Step 3 - Engineering Services During Construction is $2,378,384.05 including a 10% contingency amount
Wade Trim's earlier contracts for the project added $766,156.05 for preliminary design and $1,741,676.74 for detailed design, bringing Wade Trim's total engineering contract to $4,886,216.84.
Read supporting passage
Original Contract (ORD 1942-2023; PO405624) $ 766,156.05 Modification #1 (ORD 2066-2024; PO469605) $1,741,676.74 Modification #2 (Current) $2,378,384.05 CONTRACT TOTAL $4,886,216.84
Adding the $4,886,216.84 Wade Trim total, $32,167,000 construction ordinance and $2,062,992.05 Ascension modification brings total proposed Jackson Pike clarifier spending to $39,116,208.89 ($39.12 million).
Read supporting passage
Original Contract (ORD 1942-2023; PO405624) $ 766,156.05 Modification #1 (ORD 2066-2024; PO469605) $1,741,676.74 Modification #2 (Current) $2,378,384.05 CONTRACT TOTAL $4,886,216.84
Construction-phase engineering ($2,378,384.05): A planned modification with Wade Trim, Inc. funds Step 3 engineering services during construction, with a proposed fee of $2,378,384.05 including a 10% contingency that brings the firm's cumulative contract total to $4,886,216.84.
Read supporting passage
This ordinance authorizes the Director of Columbus Water & Power to enter into a planned contract modification for professional engineering services with Wade Trim, Inc. for the Jackson Pike Wastewater Treatment Plant (JPWWTP) A-Plant Secondary Clarifier Electrical Upgrades & Miscellaneous Improvements, CIP #650245-100002, in an amount up to $2,378,384.05.
Construction-phase engineering ($2,378,384.05): A planned modification with Wade Trim, Inc. funds Step 3 engineering services during construction, with a proposed fee of $2,378,384.05 including a 10% contingency that brings the firm's cumulative contract total to $4,886,216.84.
Read supporting passage
Work performed to date includes the Preliminary Design and Detailed Design that have been completed under the Step 1 & Step 2 contracts. This contract is for Step 3 Services, Engineering Services During Construction.
Construction-phase engineering ($2,378,384.05): A planned modification with Wade Trim, Inc. funds Step 3 engineering services during construction, with a proposed fee of $2,378,384.05 including a 10% contingency that brings the firm's cumulative contract total to $4,886,216.84.
Read supporting passage
negotiated fee for Step 1 - Preliminary Design was $766,156.05, including a 10% contingency amount. The negotiated fee for Step 2 - Detailed Design was $1,741,676.74 including a 10% contingency amount that will be utilized to fund needed and approved changes in the work. The negotiated and proposed fee for Step 3 - Engineering Services During Construction is $2,378,384.05 including a 10% contingency amount
Construction-phase engineering ($2,378,384.05): A planned modification with Wade Trim, Inc. funds Step 3 engineering services during construction, with a proposed fee of $2,378,384.05 including a 10% contingency that brings the firm's cumulative contract total to $4,886,216.84.
Read supporting passage
Original Contract (ORD 1942-2023; PO405624) $ 766,156.05 Modification #1 (ORD 2066-2024; PO469605) $1,741,676.74 Modification #2 (Current) $2,378,384.05 CONTRACT TOTAL $4,886,216.84
Wade Trim's work includes interpreting contract documents, reviewing contractor submittals and change requests, condemning nonconforming work and supporting plant startup and commissioning.
Read supporting passage
This phase of the contract will include all activities necessary to furnish interpretations and clarifications of the construction contract documents, responding to requests for information regarding the application of Project requirements, reviewing submittals from the contractor to determine compliance with the requirements of the Project, reviewing requests for variations from the requirements of the project, preparing Work Change Directives/Field Orders/Requests for Proposals (RFPs), attending project meetings, condemning non-conforming work, providing evaluation reports and acceptance recommendations pursuant to acceptance of the completed construction, supporting start-up and commissioning activities, and generally supporting the City and its PCM to verify the construction contractor's compliance with the technical requirements of the project.
Secondary clarification is one of the final steps in treating the wet wastewater stream at Jackson Pike, removing biological settleable solids before treated water leaves the plant.
Read supporting passage
This project will include improvements that will help address corrosion and odor associated with the current process, as well as upgrade equipment and overall rehabilitate an outdated system. The Secondary process is a crucial process in treating wastewater and keeping our community and rivers clean. The process is one of the final steps in the treatment process for the wet stream and removes biological settle-able solids to reduce harmful parameters in the plants final effluent.
According to Columbus Water & Power legislation, equipment failure would stop collection of settleable solids in the secondary clarifiers, causing tanks to fill and overflow solids into the plant's final effluent and risking a violation and potential hazards.
Read supporting passage
Failure of this equipment would cease collection of the settle-able solids in the secondary clarifiers, which would then fill with solids that would overflow from the secondary tanks and eventually end up in the effluent, ultimately resulting in a violation and potential hazards.
The upgrades are also intended to curb corrosion and odor tied to the existing secondary treatment equipment.
Read supporting passage
This project will include improvements that will help address corrosion and odor associated with the current process, as well as upgrade equipment and overall rehabilitate an outdated system. The Secondary process is a crucial process in treating wastewater and keeping our community and rivers clean. The process is one of the final steps in the treatment process for the wet stream and removes biological settle-able solids to reduce harmful parameters in the plants final effluent.
All three ordinances rely on loans from the Water Pollution Control Loan Fund, a program jointly administered by the Ohio EPA and the Ohio Water Development Authority under a Dec. 15, 2025 borrowing authorization from City Council.
Read supporting passage
Funding for this contract will be obtained through the Water Pollution Control Loan Fund (WPCLF), a program jointly administered by the Ohio EPA's Division of Environmental and Financial Assistance and the Ohio Water Development Authority (OWDA). City Council authorized this loan application and acceptance of funding via Ordinance 3119-2025, passed by Council on 12/15/25. This loan is expected to be approved at the October OWDA Board meeting. This ordinance is contingent upon the loan being approved by OWDA.
Each measure states that the ordinance is contingent upon OWDA board approval of the loan.
Read supporting passage
Funding for this contract will be obtained through the Water Pollution Control Loan Fund (WPCLF), a program jointly administered by the Ohio EPA's Division of Environmental and Financial Assistance and the Ohio Water Development Authority (OWDA). City Council authorized this loan application and acceptance of funding via Ordinance 3119-2025, passed by Council on 12/15/25. This loan is expected to be approved at the October OWDA Board meeting. This ordinance is contingent upon the loan being approved by OWDA.
October 2026 cited for engineering: The Wade Trim ordinance states its loan is expected to be approved at the October OWDA board meeting.
Read supporting passage
Funding for this contract will be obtained through the Water Pollution Control Loan Fund (WPCLF), a program jointly administered by the Ohio EPA's Division of Environmental and Financial Assistance and the Ohio Water Development Authority (OWDA). City Council authorized this loan application and acceptance of funding via Ordinance 3119-2025, passed by Council on 12/15/25. This loan is expected to be approved at the October OWDA Board meeting. This ordinance is contingent upon the loan being approved by OWDA.
The Wade Trim legislation also contains an internal scope discrepancy: while the explanation section states that preliminary and detailed design are already complete and that the $2.38 million modification funds Step 3 construction-phase services, one recital in the ordinance body states the additional funding is needed "to fund detailed design of the project."
Read supporting passage
Work performed to date includes the Preliminary Design and Detailed Design that have been completed under the Step 1 & Step 2 contracts. This contract is for Step 3 Services, Engineering Services During Construction.
The Wade Trim legislation also contains an internal scope discrepancy: while the explanation section states that preliminary and detailed design are already complete and that the $2.38 million modification funds Step 3 construction-phase services, one recital in the ordinance body states the additional funding is needed "to fund detailed design of the project."
Read supporting passage
WHEREAS, it is necessary to authorize a modification to the contract to increase the dollar amount of the contract to fund detailed design of the project;
Supporting evidence (19)
At its Nov. 16 regular meeting, Columbus City Council took up on first reading three Jackson Pike ordinances—for Wade Trim, Inc., Ascension Construction Solutions, LLC and Kenmore Construction Co., Inc.
Read supporting passage
This ordinance authorizes the Director of Columbus Water & Power to enter into a planned contract modification for professional construction management services with Ascension Construction Solutions, LLC for the WWTFs Professional Construction Management Services #4 project, CIP 650261-104000, in an amount up to $2,062,992.05.
—which now sit at second reading in the Public Utilities and Sustainability Committee, including Ascension's measure.
Read supporting passage
{Body=Public Utilities & Sustainability Committee, Content type=Legislation, Document coverage=API text and document metadata; linked PDF bytes are not retained, File=2968-2026, Legislation type=Ordinance, Municipality=columbus, Status=Second Reading, Text version=1}
The two oversight contracts total $4,441,376.10 ($4.44 million)—$2,378,384.05 for engineering services with Wade Trim, Inc. and $2,062,992.05 for construction management with Ascension Construction Solutions, LLC—for the Jackson Pike Wastewater Treatment Plant secondary clarifier electrical upgrades in southwest Columbus, where Ascension's scope covers the same project.
Read supporting passage
This ordinance authorizes the Director of Columbus Water & Power to enter into a planned contract modification for professional construction management services with Ascension Construction Solutions, LLC for the WWTFs Professional Construction Management Services #4 project, CIP 650261-104000, in an amount up to $2,062,992.05.
The two oversight contracts total $4,441,376.10 ($4.44 million)—$2,378,384.05 for engineering services with Wade Trim, Inc. and $2,062,992.05 for construction management with Ascension Construction Solutions, LLC—for the Jackson Pike Wastewater Treatment Plant secondary clarifier electrical upgrades in southwest Columbus, where Ascension's scope covers the same project.
Read supporting passage
The contract provides construction administration and management services including construction inspection, coordination, reporting, budgeting, scheduling, document tracking, and related tasks associated with a multi-project program. This agreement provides scope and funding for the Jackson Pike A-Plant Secondary Clarifier Electrical Upgrades & Miscellaneous Improvements project, PCM Modification 7, CIP 650245-100002.
Adding the $32,167,000 Kenmore Construction, $2,378,384.05 Wade Trim and $2,062,992.05 Ascension measures totals $36,608,376.10 ($36.61 million) in proposed Jackson Pike spending across the three 30-day ordinances at second reading in the Public Utilities and Sustainability Committee, including Ascension's measure.
Read supporting passage
This ordinance authorizes the Director of Columbus Water & Power to enter into a planned contract modification for professional construction management services with Ascension Construction Solutions, LLC for the WWTFs Professional Construction Management Services #4 project, CIP 650261-104000, in an amount up to $2,062,992.05.
Adding the $32,167,000 Kenmore Construction, $2,378,384.05 Wade Trim and $2,062,992.05 Ascension measures totals $36,608,376.10 ($36.61 million) in proposed Jackson Pike spending across the three 30-day ordinances at second reading in the Public Utilities and Sustainability Committee, including Ascension's measure.
Read supporting passage
The contract provides construction administration and management services including construction inspection, coordination, reporting, budgeting, scheduling, document tracking, and related tasks associated with a multi-project program. This agreement provides scope and funding for the Jackson Pike A-Plant Secondary Clarifier Electrical Upgrades & Miscellaneous Improvements project, PCM Modification 7, CIP 650245-100002.
Adding the $32,167,000 Kenmore Construction, $2,378,384.05 Wade Trim and $2,062,992.05 Ascension measures totals $36,608,376.10 ($36.61 million) in proposed Jackson Pike spending across the three 30-day ordinances at second reading in the Public Utilities and Sustainability Committee, including Ascension's measure.
Read supporting passage
{Body=Public Utilities & Sustainability Committee, Content type=Legislation, Document coverage=API text and document metadata; linked PDF bytes are not retained, File=2968-2026, Legislation type=Ordinance, Municipality=columbus, Status=Second Reading, Text version=1}
Adding the $4,886,216.84 Wade Trim total, $32,167,000 construction ordinance and $2,062,992.05 Ascension modification brings total proposed Jackson Pike clarifier spending to $39,116,208.89 ($39.12 million).
Read supporting passage
This ordinance authorizes the Director of Columbus Water & Power to enter into a planned contract modification for professional construction management services with Ascension Construction Solutions, LLC for the WWTFs Professional Construction Management Services #4 project, CIP 650261-104000, in an amount up to $2,062,992.05.
Adding the $4,886,216.84 Wade Trim total, $32,167,000 construction ordinance and $2,062,992.05 Ascension modification brings total proposed Jackson Pike clarifier spending to $39,116,208.89 ($39.12 million).
Read supporting passage
The contract provides construction administration and management services including construction inspection, coordination, reporting, budgeting, scheduling, document tracking, and related tasks associated with a multi-project program. This agreement provides scope and funding for the Jackson Pike A-Plant Secondary Clarifier Electrical Upgrades & Miscellaneous Improvements project, PCM Modification 7, CIP 650245-100002.
Construction management ($2,062,992.05): A seventh modification with Columbus-based Ascension Construction Solutions covers construction inspection, coordination, budgeting, scheduling and document tracking to provide quality control and minimize construction claims.
Read supporting passage
The contract provides construction administration and management services including construction inspection, coordination, reporting, budgeting, scheduling, document tracking, and related tasks associated with a multi-project program. This agreement provides scope and funding for the Jackson Pike A-Plant Secondary Clarifier Electrical Upgrades & Miscellaneous Improvements project, PCM Modification 7, CIP 650245-100002.
Construction management ($2,062,992.05): A seventh modification with Columbus-based Ascension Construction Solutions covers construction inspection, coordination, budgeting, scheduling and document tracking to provide quality control and minimize construction claims.
Read supporting passage
The performance of professional contract management services for the subject construction contracts will help to prevent or reduce the number of construction claims, provide quality control for construction, and minimize any unavoidable claims.
Columbus Water & Power manages construction oversight for its wastewater plants through a four-year rolling contract with Ascension Construction Solutions covering fiscal years 2025 through 2028.
Read supporting passage
This is a four-year contract for fiscal years 2025 - 2028 for which modifications were anticipated pursuant to the original authorizing legislation under Ordinance 2336-2025 to account for future construction projects being assigned to Ascension Construction Solutions, LLC for Professional Construction Management. Those future construction projects were not known when the contract was put into place.
Because future construction projects were not known when the original $1,000,000 contract was put into place in 2025, the city assigns projects through planned contract modifications.
Read supporting passage
This is a four-year contract for fiscal years 2025 - 2028 for which modifications were anticipated pursuant to the original authorizing legislation under Ordinance 2336-2025 to account for future construction projects being assigned to Ascension Construction Solutions, LLC for Professional Construction Management. Those future construction projects were not known when the contract was put into place.
Because future construction projects were not known when the original $1,000,000 contract was put into place in 2025, the city assigns projects through planned contract modifications.
Read supporting passage
Original Contract (ORD 2336-2025 PO531316 & PO531319) $1,000,000.00 Modification No.1 (ORD 0033-2026 PO555824) $1,989,574.00 Modification No.2 (ORD 0247-2026 PO562153) $1,429,878.03 Modification No.3 (ORD 2302-2026 PO TBD) $337,305.36 Modification No.4 (ORD 2324-2026 PO TBD) $1,000,000.00 Modification No.5 (ORD 2775-2026 PO TBD) $1,394,071.18 Modification No.6 (ORD 2882-2026 PO TBD) $1,964,818.35 Modification No.7 (Current) $2,062,992.05 CURRENT PROPOSED TOTAL $11,178,638.97
Across seven modifications—six earlier 2026 additions ranging from $337,305.36 to $1,989,574.00 plus the seventh modification of $2,062,992.05 for the Jackson Pike clarifier project—the contract's proposed total has reached $11,178,638.97.
Read supporting passage
Original Contract (ORD 2336-2025 PO531316 & PO531319) $1,000,000.00 Modification No.1 (ORD 0033-2026 PO555824) $1,989,574.00 Modification No.2 (ORD 0247-2026 PO562153) $1,429,878.03 Modification No.3 (ORD 2302-2026 PO TBD) $337,305.36 Modification No.4 (ORD 2324-2026 PO TBD) $1,000,000.00 Modification No.5 (ORD 2775-2026 PO TBD) $1,394,071.18 Modification No.6 (ORD 2882-2026 PO TBD) $1,964,818.35 Modification No.7 (Current) $2,062,992.05 CURRENT PROPOSED TOTAL $11,178,638.97
Across seven modifications—six earlier 2026 additions ranging from $337,305.36 to $1,989,574.00 plus the seventh modification of $2,062,992.05 for the Jackson Pike clarifier project—the contract's proposed total has reached $11,178,638.97.
Read supporting passage
The contract provides construction administration and management services including construction inspection, coordination, reporting, budgeting, scheduling, document tracking, and related tasks associated with a multi-project program. This agreement provides scope and funding for the Jackson Pike A-Plant Secondary Clarifier Electrical Upgrades & Miscellaneous Improvements project, PCM Modification 7, CIP 650245-100002.
All three ordinances rely on loans from the Water Pollution Control Loan Fund, a program jointly administered by the Ohio EPA and the Ohio Water Development Authority under a Dec. 15, 2025 borrowing authorization from City Council.
Read supporting passage
Funding for this contract will be obtained through the Water Pollution Control Loan Fund (WPCLF), a program jointly administered by the Ohio EPA's Division of Environmental and Financial Assistance and the Ohio Water Development Authority (OWDA). City Council authorized this loan application and acceptance of funding via Ordinance 3119-2025, passed by Council on 12/15/25. This loan is expected to be approved at the January 2027 OWDA Board meeting. This ordinance is contingent upon the loan being approved by OWDA.
Each measure states that the ordinance is contingent upon OWDA board approval of the loan.
Read supporting passage
Funding for this contract will be obtained through the Water Pollution Control Loan Fund (WPCLF), a program jointly administered by the Ohio EPA's Division of Environmental and Financial Assistance and the Ohio Water Development Authority (OWDA). City Council authorized this loan application and acceptance of funding via Ordinance 3119-2025, passed by Council on 12/15/25. This loan is expected to be approved at the January 2027 OWDA Board meeting. This ordinance is contingent upon the loan being approved by OWDA.
January 2027 cited for management: The Ascension modification states its loan is expected to go before the OWDA board in January 2027, the same month Columbus Water & Power anticipates issuing the construction notice to proceed.
Read supporting passage
Funding for this contract will be obtained through the Water Pollution Control Loan Fund (WPCLF), a program jointly administered by the Ohio EPA's Division of Environmental and Financial Assistance and the Ohio Water Development Authority (OWDA). City Council authorized this loan application and acceptance of funding via Ordinance 3119-2025, passed by Council on 12/15/25. This loan is expected to be approved at the January 2027 OWDA Board meeting. This ordinance is contingent upon the loan being approved by OWDA.
Supporting evidence (9)
Yet OWDA's public summary for its Oct. 29 meeting reports over $42.3 million in Fresh Water Loan Fund awards across seven Ohio projects, including two Columbus waterline loans in the Kent and Fairwood and Yale Avenue service areas.
Read supporting passage
The Ohio Water Development Authority (OWDA) approved over $42.3 million in low interest loans on Thursday, October 29, 2026, for seven projects in Ohio to improve wastewater and drinking water infrastructure and make water quality improvements for Ohioans. The following projects for Ohio communities received OWDA Board approval for funding through the Fresh Water Loan Fund Program for improvements and to replace aging infrastructure:
Yet OWDA's public summary for its Oct. 29 meeting reports over $42.3 million in Fresh Water Loan Fund awards across seven Ohio projects, including two Columbus waterline loans in the Kent and Fairwood and Yale Avenue service areas.
Read supporting passage
The City of Columbus in Franklin County is approved to receive a loan for $4,324,432.88 at 4.72% for 20 years for the construction of 5,400 feet of waterline within the Kent and Fairwood service area to replace aging waterlines.
Yet OWDA's public summary for its Oct. 29 meeting reports over $42.3 million in Fresh Water Loan Fund awards across seven Ohio projects, including two Columbus waterline loans in the Kent and Fairwood and Yale Avenue service areas.
Read supporting passage
The City of Columbus in Franklin County is approved to receive a loan for $7,125,592.93 at 4.72% for 20 years for the construction of 10,600 feet of waterline in the Yale Avenue service area to replace aging waterlines.
OWDA's October summary lists those two Columbus waterline projects alongside awards for Forest, the Mahoning Valley Sanitary District, Rittman, South Zanesville and Tuscarawas County.
Read supporting passage
The Village of Forest in Hardin County is approved to receive a loan for $954,830.00 at 4.72% for five years for the design of wastewater treatment plant improvements, including rehabilitation of the lagoon treatment system, disinfection upgrades, and a new lift station with force main to achieve compliance with permit limits.
OWDA's October summary lists those two Columbus waterline projects alongside awards for Forest, the Mahoning Valley Sanitary District, Rittman, South Zanesville and Tuscarawas County.
Read supporting passage
The Mahoning Valley Sanitary District is approved to receive three separate 20-year loans for the construction of upgrades to the Mineral Ridge Dam to improve operations, enhance safety, and protect the water supply for residents in Mahoning and Trumbull counties.
OWDA's October summary lists those two Columbus waterline projects alongside awards for Forest, the Mahoning Valley Sanitary District, Rittman, South Zanesville and Tuscarawas County.
Read supporting passage
The Village of Rittman in Wayne County is approved to receive a loan for $641,933.20 at 4.46% for 30 years for the construction of 1,800 feet of waterline along South Main Street to replace aging waterlines.
OWDA's October summary lists those two Columbus waterline projects alongside awards for Forest, the Mahoning Valley Sanitary District, Rittman, South Zanesville and Tuscarawas County.
Read supporting passage
The Village of South Zanesville in Muskingum County is approved to receive a loan for $200,700.00 at 4.72% for five years for the design of 21,000 feet of waterline, upgrades to a pressure regulating station, improvements to the Clay Street storage tank, and a new pump station to replace aging waterlines and improve operations.
OWDA's October summary lists those two Columbus waterline projects alongside awards for Forest, the Mahoning Valley Sanitary District, Rittman, South Zanesville and Tuscarawas County.
Read supporting passage
Tuscarawas County is approved to receive a loan for $118,000.00 at 4.13% for 20 years for the replacement of 23 aging sanitary manholes in the Villages of Midvale and Barnhill.
December 2026 cited for construction: The Kenmore Construction ordinance anticipates loan approval at the OWDA December meeting, which OWDA has scheduled for Thursday, Dec. 10 in Columbus, with meeting materials expected the week of Dec. 7.
Read supporting passage
The next scheduled Board Meeting is Thursday, December 10, 2026, at 10:30 a.m. at the Ohio Water Development Authority, 480 South High Street, Columbus, Ohio.
https://www.owda.org/board-meeting-materials
Supporting evidence (5)
OWDA's Board Meeting Materials page posts January 2026 and September 2026 Board Minutes and notes that the board approves minutes from the previous month's board meeting each month.
Read supporting passage
Board Meeting Materials
OWDA's Board Meeting Materials page posts January 2026 and September 2026 Board Minutes and notes that the board approves minutes from the previous month's board meeting each month.
Read supporting passage
BOARD MINUTESJanuary 2026 Board Minutes
OWDA's Board Meeting Materials page posts January 2026 and September 2026 Board Minutes and notes that the board approves minutes from the previous month's board meeting each month.
Read supporting passage
September 2026 Board Minutes
OWDA's Board Meeting Materials page posts January 2026 and September 2026 Board Minutes and notes that the board approves minutes from the previous month's board meeting each month.
Read supporting passage
Note: The OWDA Board approves minutes from the previous month's Board meeting each month.
December 2026 cited for construction: The Kenmore Construction ordinance anticipates loan approval at the OWDA December meeting, which OWDA has scheduled for Thursday, Dec. 10 in Columbus, with meeting materials expected the week of Dec. 7.
Read supporting passage
The agenda for the upcoming Thursday, December 10, 2026, board meeting will be available the week of December 7, 2026.
Columbus Considers $32.2 Million Contract for Jackson Pike Clarifier Upgrades
Supporting evidence (1)
Previously, Pique Media reported on Nov. 13 that Columbus is considering a $32.2 million contract for Jackson Pike clarifier upgrades.
Read supporting passage
Columbus Considers $32.2 Million Contract for Jackson Pike Clarifier Upgrades