Politics Government · Transportation & infrastructure

Gahanna Considers Emergency Easement for Columbia Gas Pipeline Upgrade

The proposed 7,369-square-foot utility easement on Johnstown Road would allow Columbia Gas of Ohio to build a lateral line for a 19,000-foot pipeline project.

Gahanna

Watch the video

Gahanna's proposed Ordinance ORD-0048-2026 authorizes the mayor to enter into an easement agreement with Columbia Gas of Ohio, Inc., for the Agler NCHP pipeline project.

The proposed easement encompasses approximately 7,369.38 square feet of municipal property. County records identify the parcel as city-owned land along Johnstown Road in Gahanna.

Columbia Gas requested the permanent easement to construct, operate, and maintain a lateral pipeline connection associated with its Agler North Columbus High Pressure pipeline project. The initiative involves replacing approximately 19,000 feet of natural gas pipeline, with construction scheduled for 2027.

Schematic street map showing the Agler Road pipeline route across Sunbury Road, Cassady Avenue, Stelzer Road, and I-270, color-coded for 2025 and 2027 completion.

A Columbia Gas schematic route map details the Agler Road North Columbus High Pressure pipeline project corridor across northeast Franklin County and Gahanna.

Credit: Columbia Gas of Ohio Image source

The Gahanna administration requested waiver of the second reading and emergency passage to coordinate with the upcoming Columbia Gas construction project. Under the ordinance provisions, emergency adoption would allow the measure to take effect immediately upon passage by City Council and approval by the mayor, rather than waiting through customary reading intervals.

Previously, Pique Media reported on 2027 pipeline work planned by Columbia Gas in Gahanna and along Agler Road. In that briefing on Monday, Oct. 19, Columbia Gas detailed plans for the North Columbus High Pressure pipeline project extending through Gahanna and along Agler Road.

Installing the replacement facilities is required under federal pipeline safety mandates enforced by the Pipeline and Hazardous Materials Safety Administration. Construction along Agler Road between Gatewood Road and Big Walnut Creek is scheduled to proceed through 2027.

According to utility disclosures, construction within road rights-of-way will require temporary street and lane closures, while no service interruptions are planned for natural gas customers during the work.

Video Watch video 0:27

More on this story

Pique’s reporting on the same events, newest first.

  1. Gahanna Latest

    Gahanna Weighs Emergency Pipeline Easements Across Veterans Memorial Park

    Proposed terms for Columbia Gas include protections for the adjacent memorial and future recreational use of parkland along Big Walnut Creek.

  2. Gahanna You are reading

    Gahanna Considers Emergency Easement for Columbia Gas Pipeline Upgrade

  3. Ohio

    Columbia Gas Outlines 2027 Pipeline Work in Gahanna and Along Agler Road

    Plans presented to Gahanna City Council cover high-pressure natural gas lines serving thousands of Columbus-area customers.

How we know this

The sources and records behind this story, with the facts they support.

  1. ORD-0048-2026 · AN ORDINANCE AUTHORIZING THE MAYOR TO ENTER INTO AN EASEMENT AGREEMENT WITH COLUMBIA GAS OF OHIO, INC., FOR THE AGLER NCHP PIPELINE PROJECT; WAIVING SECOND READING; AND DECLARING AN EMERGENCY

    gahanna · legislation

    Published · Accessed

    Supporting evidence (6)
    • Gahanna's proposed Ordinance ORD-0048-2026 authorizes the mayor to enter into an easement agreement with Columbia Gas of Ohio, Inc., for the Agler NCHP pipeline project.

      Read supporting passage
      ORD-0048-2026 · AN ORDINANCE AUTHORIZING THE MAYOR TO ENTER INTO AN EASEMENT AGREEMENT WITH COLUMBIA GAS OF OHIO, INC., FOR THE AGLER NCHP PIPELINE PROJECT; WAIVING SECOND READING; AND DECLARING AN EMERGENCY
    • The proposed easement encompasses approximately 7,369.38 square feet of municipal property.

      Read supporting passage
      WHEREAS, the proposed easement encompasses approximately 7,369.38 square feet of City-owned property, as depicted in the attached easement agreement; and
    • Columbia Gas requested the permanent easement to construct, operate, and maintain a lateral pipeline connection associated with its Agler North Columbus High Pressure pipeline project.

      Read supporting passage
      WHEREAS, Columbia Gas of Ohio, Inc., has requested a permanent easement across certain City-owned property for the construction, operation, and maintenance of a lateral pipeline associated with the project; and
    • The initiative involves replacing approximately 19,000 feet of natural gas pipeline, with construction scheduled for 2027.

      Read supporting passage
      WHEREAS, Columbia Gas of Ohio, Inc., is undertaking the Agler NCHP (North Columbus High Pressure) Pipeline Project, which involves the replacement of approximately 19,000 feet of natural gas pipeline, with construction anticipated in 2027; and
    • The Gahanna administration requested waiver of the second reading and emergency passage to coordinate with the upcoming Columbia Gas construction project.

      Read supporting passage
      WHEREAS, the Administration has requested waiver of second reading and emergency passage to coordinate with the upcoming Columbia Gas construction project.
    • Under the ordinance provisions, emergency adoption would allow the measure to take effect immediately upon passage by City Council and approval by the mayor, rather than waiting through customary reading intervals.

      Read supporting passage
      Section 3. That, for the reasons set forth in the preamble hereto, this Ordinance is declared an emergency measure necessary for the immediate preservation of the public peace, health, safety, and welfare of the City of Gahanna, and shall be in full force and effect immediately upon passage by Council and approval by the Mayor.
  2. Page 2

    www.columbiagasohio.com

    Accessed

    Supporting evidence (1)
    • County records identify the parcel as city-owned land along Johnstown Road in Gahanna.

      Read supporting passage
      025-000834 EXEMPT PROPERTY OWNED BY CITIES JOHNSTOWN RD GAHANNA 43230 CITY OF GAHANNA 200 S HAMILTON RD GAHANNA OH 43230-2996
  3. Columbia Gas Outlines 2027 Pipeline Work in Gahanna and Along Agler Road

    Published · Accessed

    Supporting evidence (6)
    • Previously, Pique Media reported on 2027 pipeline work planned by Columbia Gas in Gahanna and along Agler Road.

      Read supporting passage
      Columbia Gas Outlines 2027 Pipeline Work in Gahanna and Along Agler Road
    • In that briefing on Monday, Oct. 19, Columbia Gas detailed plans for the North Columbus High Pressure pipeline project extending through Gahanna and along Agler Road.

      Read supporting passage
      Columbia Gas presented project plans to the Gahanna City Council on Monday, Oct. 19, for the North Columbus High Pressure pipeline project through Gahanna and along Agler Road.
    • Installing the replacement facilities is required under federal pipeline safety mandates enforced by the Pipeline and Hazardous Materials Safety Administration.

      Read supporting passage
      Installing new gas line facilities is required to comply with federal safety mandates under PHMSA’s Mega Rule.
    • Construction along Agler Road between Gatewood Road and Big Walnut Creek is scheduled to proceed through 2027.

      Read supporting passage
      The utility stated that the 2027 construction will occur on Agler Road between Gatewood Road and Big Walnut Creek.
    • According to utility disclosures, construction within road rights-of-way will require temporary street and lane closures, while no service interruptions are planned for natural gas customers during the work.

      Read supporting passage
      When work begins, the project will require temporary street and lane closures throughout construction.
    • According to utility disclosures, construction within road rights-of-way will require temporary street and lane closures, while no service interruptions are planned for natural gas customers during the work.

      Read supporting passage
      There are no scheduled service interruptions to Columbia Gas service as a result of the construction.

Take Pique with you

Your city. In your pocket.

Read local stories, watch the videos and explore the details in Pique.

QR code for Pique Media on the App Store

Get Pique for iPhone and iPad

Scan the code with your phone’s camera.

View on the App Store

Share this story