Video 0:27
Video
Gahanna considers emergency easement for Agler Road pipeline project
Read the full articleGahanna City Council is considering an emergency ordinance to grant Columbia Gas of Ohio a 7,369-square-foot utility easement on city property. The lateral connection supports a 19,000-foot pipeline replacement along Agler Road scheduled for 2027.
How we know this
The sources and records behind this story, with the facts they support.
Supporting evidence (6)
Gahanna's proposed Ordinance ORD-0048-2026 authorizes the mayor to enter into an easement agreement with Columbia Gas of Ohio, Inc., for the Agler NCHP pipeline project.
Read supporting passage
ORD-0048-2026 · AN ORDINANCE AUTHORIZING THE MAYOR TO ENTER INTO AN EASEMENT AGREEMENT WITH COLUMBIA GAS OF OHIO, INC., FOR THE AGLER NCHP PIPELINE PROJECT; WAIVING SECOND READING; AND DECLARING AN EMERGENCY
The proposed easement encompasses approximately 7,369.38 square feet of municipal property.
Read supporting passage
WHEREAS, the proposed easement encompasses approximately 7,369.38 square feet of City-owned property, as depicted in the attached easement agreement; and
Columbia Gas requested the permanent easement to construct, operate, and maintain a lateral pipeline connection associated with its Agler North Columbus High Pressure pipeline project.
Read supporting passage
WHEREAS, Columbia Gas of Ohio, Inc., has requested a permanent easement across certain City-owned property for the construction, operation, and maintenance of a lateral pipeline associated with the project; and
The initiative involves replacing approximately 19,000 feet of natural gas pipeline, with construction scheduled for 2027.
Read supporting passage
WHEREAS, Columbia Gas of Ohio, Inc., is undertaking the Agler NCHP (North Columbus High Pressure) Pipeline Project, which involves the replacement of approximately 19,000 feet of natural gas pipeline, with construction anticipated in 2027; and
The Gahanna administration requested waiver of the second reading and emergency passage to coordinate with the upcoming Columbia Gas construction project.
Read supporting passage
WHEREAS, the Administration has requested waiver of second reading and emergency passage to coordinate with the upcoming Columbia Gas construction project.
Under the ordinance provisions, emergency adoption would allow the measure to take effect immediately upon passage by City Council and approval by the mayor, rather than waiting through customary reading intervals.
Read supporting passage
Section 3. That, for the reasons set forth in the preamble hereto, this Ordinance is declared an emergency measure necessary for the immediate preservation of the public peace, health, safety, and welfare of the City of Gahanna, and shall be in full force and effect immediately upon passage by Council and approval by the Mayor.
Supporting evidence (1)
County records identify the parcel as city-owned land along Johnstown Road in Gahanna.
Read supporting passage
025-000834 EXEMPT PROPERTY OWNED BY CITIES JOHNSTOWN RD GAHANNA 43230 CITY OF GAHANNA 200 S HAMILTON RD GAHANNA OH 43230-2996
Columbia Gas Outlines 2027 Pipeline Work in Gahanna and Along Agler Road
Supporting evidence (6)
Previously, Pique Media reported on 2027 pipeline work planned by Columbia Gas in Gahanna and along Agler Road.
Read supporting passage
Columbia Gas Outlines 2027 Pipeline Work in Gahanna and Along Agler Road
In that briefing on Monday, Oct. 19, Columbia Gas detailed plans for the North Columbus High Pressure pipeline project extending through Gahanna and along Agler Road.
Read supporting passage
Columbia Gas presented project plans to the Gahanna City Council on Monday, Oct. 19, for the North Columbus High Pressure pipeline project through Gahanna and along Agler Road.
Installing the replacement facilities is required under federal pipeline safety mandates enforced by the Pipeline and Hazardous Materials Safety Administration.
Read supporting passage
Installing new gas line facilities is required to comply with federal safety mandates under PHMSA’s Mega Rule.
Construction along Agler Road between Gatewood Road and Big Walnut Creek is scheduled to proceed through 2027.
Read supporting passage
The utility stated that the 2027 construction will occur on Agler Road between Gatewood Road and Big Walnut Creek.
According to utility disclosures, construction within road rights-of-way will require temporary street and lane closures, while no service interruptions are planned for natural gas customers during the work.
Read supporting passage
When work begins, the project will require temporary street and lane closures throughout construction.
According to utility disclosures, construction within road rights-of-way will require temporary street and lane closures, while no service interruptions are planned for natural gas customers during the work.
Read supporting passage
There are no scheduled service interruptions to Columbia Gas service as a result of the construction.