Columbus approves $650,000 expansion for street and sidewalk water repairs
A 9-0 vote brings Decker Construction's 2026 restoration contract to $2.1 million through March 2027.
Columbus City Council voted 9-0 on its consent agenda on Monday, Nov. 16, to approve a $650,000 contract modification with Decker Construction Company for the 2026 Utility Cut Restoration Project.
The legislation adds funding for the Division of Water, bringing total contract spending to $2.1 million through March 31, 2027.
A Decker Construction crew rakes steaming asphalt during street utility cut pavement repair.
Credit: Decker Construction Co. Image source
Columbus City Council previously advanced the $650,000 utility cut restoration measure on first reading on Nov. 2. According to city filings explaining why additional funds were not foreseen, additional funds were not set up in its entirety, and funds will be used through the end of the contract. The city determined the modification amount based on estimated requirements for early 2026 using rates established under the existing contract.
Decker Construction Company, based on McKinley Avenue, secured the work after submitting the sole bid under RFQ023112, which the Director of Columbus Water and Power opened on May 6, 2026. City officials deemed Decker's proposal the lowest, most responsive, and responsible bid, adding a bid waiver to accommodate wording modifications made after vendor selection. Council approved the original contract on July 2, 2026, which covers a one-year term with options for up to three annual renewals.
Columbus Water and Power routinely outsources the restoration of pavement, curbs, and sidewalks following utility excavations in city rights-of-way and city-owned properties. Outsourced work includes wheelchair ramp installations, thermal bond heat weld repairs, full-width asphalt milling, and volumetric mixer delivery of controlled density fill.
The $650,000 addition is paid from Division of Water operating funds. City financial records show annual restoration spending varies: Columbus has expended $1,418,763 so far in 2026, compared to $1,876,351 in 2025 and $2,695,850 in 2024.
Previously, Pique Media reported the advance of a $650,000 expansion for street and sidewalk utility repairs and reported the approval of a $350,000 expansion for street and sidewalk utility repairs.
Video Watch video 0:47
Pique’s reporting on the same events, newest first.
Columbus Latest You are reading
Columbus approves $650,000 expansion for street and sidewalk water repairs
Columbus
Columbus approves $350,000 expansion for street and sidewalk utility repairs
The emergency measure doubles funding to $700,000 and extends Decker Construction Company's restoration work through October 2027 to prevent a service interruption.
Columbus
Columbus advances $650,000 expansion for street and sidewalk utility repairs
The addition brings Decker Construction's 2026 restoration contract to $2.1 million after utility officials acknowledged earlier funding was incomplete.
How we know this
The sources and records behind this story, with the facts they support.
Supporting evidence (2)
Columbus City Council voted 9-0 on its consent agenda on Monday, Nov. 16, to approve a $650,000 contract modification with Decker Construction Company for the 2026 Utility Cut Restoration Project.
Read supporting passage
This item was approved on the Consent Agenda. Result: Pass · Mover: Tiara Ross · Seconder: Nancy Day-Achauer Consent agenda vote (event item 648445): Nicholas Bankston: Affirmative Lourdes Barroso De Padilla: Affirmative Nancy Day-Achauer: Affirmative Rob Dorans: Affirmative Melissa Green: Affirmative Emmanuel V. Remy: Affirmative Tiara Ross: Affirmative Christopher Wyche: Affirmative Shannon G. Hardin: Affirmative {Body=Columbus City Council, Content type=Outcomes, Document coverage=API text and document metadata; linked PDF bytes are not retained, Local time=5:00 PM, Location=City Council Chambers, Rm 231, Meeting date=2026-11-16T00:00:00, Municipality=columbus}
Columbus City Council voted 9-0 on its consent agenda on Monday, Nov. 16, to approve a $650,000 contract modification with Decker Construction Company for the 2026 Utility Cut Restoration Project.
Read supporting passage
Columbus City Council · 2854-2026 · To authorize the Director of Columbus Water and Power to modify a contract for the 2026 Utility Cut Restoration Project with Decker Construction Company for the Division of Water; and to authorize the expenditure of $650,000.00 through March 31, 2027. ($650,000.00)
Supporting evidence (15)
The legislation adds funding for the Division of Water, bringing total contract spending to $2.1 million through March 31, 2027.
Read supporting passage
This contract is for additional funding only. Total amount is $2,100,000.00.
The legislation adds funding for the Division of Water, bringing total contract spending to $2.1 million through March 31, 2027.
Read supporting passage
To authorize the Director of Columbus Water and Power to modify a contract for the 2026 Utility Cut Restoration Project with Decker Construction Company for the Division of Water; and to authorize the expenditure of $650,000.00 through March 31, 2027. ($650,000.00)
According to city filings explaining why additional funds were not foreseen, additional funds were not set up in its entirety, and funds will be used through the end of the contract.
Read supporting passage
Reason additional funds were not foreseen: Additional funds were not set up in its entirety. Funds will be used through the end of the contract.
The city determined the modification amount based on estimated requirements for early 2026 using rates established under the existing contract.
Read supporting passage
How was cost determined: The modification is based upon estimated requirements for early 2026 at rates established in the existing contract.
Decker Construction Company, based on McKinley Avenue, secured the work after submitting the sole bid under RFQ023112, which the Director of Columbus Water and Power opened on May 6, 2026.
Read supporting passage
SECTION 1. That the Director of Columbus Water and Power be and hereby is authorized to modify to add funding to the contract for the 2026 Utility Cut Restoration Project with Decker Construction Company, 3040 McKinley Avenue, Columbus, Ohio 43204 ; in accordance with the terms and conditions of the contract on file in Columbus Water and Power.
Decker Construction Company, based on McKinley Avenue, secured the work after submitting the sole bid under RFQ023112, which the Director of Columbus Water and Power opened on May 6, 2026.
Read supporting passage
CONSTRUCTION CONTRACT AWARD: The Director of Columbus Water & Power publicly opened one bid (RFQ023112) on May 6, 2026 from Decker Construction Company.
City officials deemed Decker's proposal the lowest, most responsive, and responsible bid, adding a bid waiver to accommodate wording modifications made after vendor selection.
Read supporting passage
Decker Construction Company's bid was deemed the lowest, most responsive and responsible bid. A bid waiver was added to address the verbiage changes after the bidding process was complete and a vendor selected.
Council approved the original contract on July 2, 2026, which covers a one-year term with options for up to three annual renewals.
Read supporting passage
WHEREAS, Ordinance No. 1569-2026, passed by the Columbus City Council on July 2, 2026, authorized Columbus Water and Power, Division of Water, to enter into a contract with Decker Construction Company for the 2026 Utility Cut Restoration Project; and
Council approved the original contract on July 2, 2026, which covers a one-year term with options for up to three annual renewals.
Read supporting passage
Services under the original contract cover a one (1) year period from date of execution with the option to renew annually for an additional three (3) years on a year-to-year basis, or a portion thereof, based on mutual agreement of the parties, availability of budgeted funds and approval of Columbus City Council.
Columbus Water and Power routinely outsources the restoration of pavement, curbs, and sidewalks following utility excavations in city rights-of-way and city-owned properties.
Read supporting passage
Various types of utility excavations are performed within the City of Columbus' right-of-way and City owned properties by Columbus Water and Power. The restoration work typically involves repair of existing pavement, curbs, and sidewalks in a manner conforming to the City of Columbus, Construction and Material Specifications (CMSC). The Department routinely outsources this restoration work to a contractor that is equipped and trained to make these repairs.
Outsourced work includes wheelchair ramp installations, thermal bond heat weld repairs, full-width asphalt milling, and volumetric mixer delivery of controlled density fill.
Read supporting passage
Typical types of restoration work that require outsourcing involve the installation of wheelchair ramps, asphalt repair involving thermal bond heat weld repairs, asphalt milling machines capable of full width milling, and the delivery of flowable controlled density fill using volumetric mixer trucks.
The $650,000 addition is paid from Division of Water operating funds.
Read supporting passage
FISCAL IMPACT: $650,000.00 is available from within Columbus Water and Power, Division of Water Operating Funds to meet the financial obligations of this contract.
City financial records show annual restoration spending varies: Columbus has expended $1,418,763 so far in 2026, compared to $1,876,351 in 2025 and $2,695,850 in 2024.
Read supporting passage
$1,418,763.01 has been spent so far in 2026
City financial records show annual restoration spending varies: Columbus has expended $1,418,763 so far in 2026, compared to $1,876,351 in 2025 and $2,695,850 in 2024.
Read supporting passage
$1,876,351.19 was spent in 2025
City financial records show annual restoration spending varies: Columbus has expended $1,418,763 so far in 2026, compared to $1,876,351 in 2025 and $2,695,850 in 2024.
Read supporting passage
$2,695,850.41 was spent in 2024
Columbus advances $650,000 expansion for street and sidewalk utility repairs
Supporting evidence (2)
Columbus City Council previously advanced the $650,000 utility cut restoration measure on first reading on Nov. 2.
Read supporting passage
During its meeting on Monday, Nov. 2, Columbus City Council advanced a $650,000 contract modification with Decker Construction Company for city utility cut restorations.
Previously, Pique Media reported the advance of a $650,000 expansion for street and sidewalk utility repairs and reported the approval of a $350,000 expansion for street and sidewalk utility repairs.
Read supporting passage
Columbus advances $650,000 expansion for street and sidewalk utility repairs
Columbus approves $350,000 expansion for street and sidewalk utility repairs
Supporting evidence (1)
Previously, Pique Media reported the advance of a $650,000 expansion for street and sidewalk utility repairs and reported the approval of a $350,000 expansion for street and sidewalk utility repairs.
Read supporting passage
Columbus approves $350,000 expansion for street and sidewalk utility repairs