Politics Government · Transportation & infrastructure

Columbus approves $350,000 expansion for street and sidewalk utility repairs

The emergency measure doubles funding to $700,000 and extends Decker Construction Company's restoration work through October 2027 to prevent a service interruption.

Columbus

Watch the video

Columbus City Council voted 9-0 on its consent agenda on Monday, Nov. 16, to approve an emergency $350,000 contract modification with Decker Construction Company for roadway utility cut repairs.

The measure doubles contract funding from an initial $350,000 to $700,000 and extends work through Oct. 31, 2027, exercising the first of two possible one-year extension periods. City officials requested emergency action to prevent a service interruption and ensure the safety of the traveling public, as the existing agreement was scheduled to expire on Dec. 1, 2026.

Road repair crew spreading and raking steaming hot asphalt on a street surface patch.

Paving crew members spread steaming hot mix asphalt with rakes during pavement maintenance and patch repair.

Credit: Decker Construction Co. Image source

Under the contract, Decker Construction performs as-needed work in municipal rights-of-way following utility cuts, including excavation, grading, curb, sidewalk, ADA ramps, planing, street repair, and paving. The $350,000 expenditure is funded through the city's Street Construction Maintenance and Repair Fund. Decker Construction Company is based at 3040 McKinley Ave. in Columbus.

Previously, Pique Media reported that Columbus City Council advanced a $650,000 contract modification with Decker Construction Company for utility cut restorations following its Nov. 2 meeting.

Video Watch video 0:27

More on this story

Pique’s reporting on the same events, newest first.

  1. Columbus Latest

    Columbus approves $650,000 expansion for street and sidewalk water repairs

    A 9-0 vote brings Decker Construction's 2026 restoration contract to $2.1 million through March 2027.

  2. Columbus You are reading

    Columbus approves $350,000 expansion for street and sidewalk utility repairs

  3. Columbus

    Columbus advances $650,000 expansion for street and sidewalk utility repairs

    The addition brings Decker Construction's 2026 restoration contract to $2.1 million after utility officials acknowledged earlier funding was incomplete.

How we know this

The sources and records behind this story, with the facts they support.

  1. Columbus City Council · 2972-2026 · To authorize the Director of Public Service to enter into a contract modification with Decker Construction Company for the Roadway - Utility Cut and Repair program; to authorize the expenditure of up to $350,000.00 from the Street Construction Maintenance and Repa

    columbus · outcomes

    Published · Accessed

    Supporting evidence (2)
    • Columbus City Council voted 9-0 on its consent agenda on Monday, Nov. 16, to approve an emergency $350,000 contract modification with Decker Construction Company for roadway utility cut repairs.

      Read supporting passage
      This item was approved on the Consent Agenda. Result: Pass · Mover: Tiara Ross · Seconder: Nancy Day-Achauer Consent agenda vote (event item 648445): Nicholas Bankston: Affirmative Lourdes Barroso De Padilla: Affirmative Nancy Day-Achauer: Affirmative Rob Dorans: Affirmative Melissa Green: Affirmative Emmanuel V. Remy: Affirmative Tiara Ross: Affirmative Christopher Wyche: Affirmative Shannon G. Hardin: Affirmative {Body=Columbus City Council, Content type=Outcomes, Document coverage=API text and document metadata; linked PDF bytes are not retained, Local time=5:00 PM, Location=City Council Chambers, Rm 231, Meeting date=2026-11-16T00:00:00, Municipality=columbus}
    • Columbus City Council voted 9-0 on its consent agenda on Monday, Nov. 16, to approve an emergency $350,000 contract modification with Decker Construction Company for roadway utility cut repairs.

      Read supporting passage
      To authorize the Director of Public Service to enter into a contract modification with Decker Construction Company for the Roadway - Utility Cut and Repair program; to authorize the expenditure of up to $350,000.00 from the Street Construction Maintenance and Repair Fund; and to declare an emergency.
  2. 2972-2026 · To authorize the Director of Public Service to enter into a contract modification with Decker Construction Company for the Roadway - Utility Cut and Repair program; to authorize the expenditure of up to $350,000.00 from the Street Construction Maintenance and Repair Fund; and to declare

    columbus · legislation

    Published · Accessed

    Supporting evidence (8)
    • The measure doubles contract funding from an initial $350,000 to $700,000 and extends work through Oct. 31, 2027, exercising the first of two possible one-year extension periods.

      Read supporting passage
      The original contract amount: $350,000.00 (PO546106, Ord. 2991-2025) The total of modification 1: $350,000.00 (Ord. 2972-2026) The contract amount including all modifications: $700,000.00
    • The measure doubles contract funding from an initial $350,000 to $700,000 and extends work through Oct. 31, 2027, exercising the first of two possible one-year extension periods.

      Read supporting passage
      extend the contract for approximately one year to October 31, 2027, in the amount of $350,000.00 to pay for year two of the contract
    • The measure doubles contract funding from an initial $350,000 to $700,000 and extends work through Oct. 31, 2027, exercising the first of two possible one-year extension periods.

      Read supporting passage
      This ordinance authorizes the Director of Public Service to extend the contract for the first of two, possible periods of one year, and to add funds to pay for services provided in year two of the contract in the amount of $350,000.00.
    • City officials requested emergency action to prevent a service interruption and ensure the safety of the traveling public, as the existing agreement was scheduled to expire on Dec. 1, 2026.

      Read supporting passage
      to ensure payment for these services can continue to prevent a service interruption, for the immediate preservation of the public health, safety, property, and welfare
    • City officials requested emergency action to prevent a service interruption and ensure the safety of the traveling public, as the existing agreement was scheduled to expire on Dec. 1, 2026.

      Read supporting passage
      Emergency action is requested to continue the completion of the needed improvements at the earliest possible time to ensure the safety of the traveling public, as the current contract expires December 1, 2026.
    • Under the contract, Decker Construction performs as-needed work in municipal rights-of-way following utility cuts, including excavation, grading, curb, sidewalk, ADA ramps, planing, street repair, and paving.

      Read supporting passage
      The work performed to date for this project consists of as-requested work within the right-of-way, including excavation, grading, curb, sidewalk, ADA ramps, planing, street repair, paving, and other work as may be necessary to complete the contract in accordance with the plans and specifications set forth in the Bid Submittal Documents.
    • The $350,000 expenditure is funded through the city's Street Construction Maintenance and Repair Fund.

      Read supporting passage
      This is a budgeted item within Fund 2265, the Street Construction Maintenance and Repair Fund.
    • Decker Construction Company is based at 3040 McKinley Ave. in Columbus.

      Read supporting passage
      SECTION 1. That the Director of Public Service be and hereby is authorized to execute a contract modification for the Roadway - Utility Cut and Repair program with Decker Construction Company, of 3040 McKinley Avenue, Columbus, Ohio, 43204, for the Roadway - Utility Cut and Repair program in the amount of up to $350,000.00, and to extend the contract for approximately one year to October 31, 2027.
  3. Columbus advances $650,000 expansion for street and sidewalk utility repairs

    Published · Accessed

    Supporting evidence (2)
    • Previously, Pique Media reported that Columbus City Council advanced a $650,000 contract modification with Decker Construction Company for utility cut restorations following its Nov. 2 meeting.

      Read supporting passage
      Columbus advances $650,000 expansion for street and sidewalk utility repairs
    • Previously, Pique Media reported that Columbus City Council advanced a $650,000 contract modification with Decker Construction Company for utility cut restorations following its Nov. 2 meeting.

      Read supporting passage
      During its meeting on Monday, Nov. 2, Columbus City Council advanced a $650,000 contract modification with Decker Construction Company for city utility cut restorations.

Take Pique with you

Your city. In your pocket.

Read local stories, watch the videos and explore the details in Pique.

QR code for Pique Media on the App Store

Get Pique for iPhone and iPad

Scan the code with your phone’s camera.

View on the App Store

Share this story