US 22 Bridge Over Clear Creek Scheduled for October Completion

Published

Read the full article

The $1.8 million bridge replacement west of Amanda is scheduled to wrap up construction by Oct. 31, with ODOT targeting roadway reopening by Oct. 17. The crossing has been closed since May 26, directing traffic onto detours via SR 674, SR 188, and US 33.

How we know this

The sources and records behind this story, with the facts they support.

  1. Project · GIS_ID · 76506

    https://tims.dot.state.oh.us/ags/rest/services/Projects/Current_Projects_Points/MapServer/0

    Published · Accessed

    Supporting evidence (4)
    • Route 22 over Clear Creek in Amanda Township contractor award.

      Read supporting passage
      CONSTR_VENDOR_NME: Alan Stone Co., Inc.
    • State contracting records show the scheduled late-October deadline represents the final operational milestone for replacing the rural Fairfield County crossing project milestones.

      Read supporting passage
      AWARD_MILESTONE_DT: 2025-12-30
    • ODOT awarded the $1,795,146.40 contract for State Project 254032 to Alan Stone Co. on Dec. 30, 2025, tracking the initiative under Program Identification Number 115691 contract pricing.

      Read supporting passage
      EST_TOTAL_CONSTR_COST: 1795146.4
    • Formal contract records show preliminary construction began on April 1, 2026, setting the stage for on-site structural replacement that is scheduled to reach overall completion on Saturday, Oct. 31, 2026 project milestones.

      Read supporting passage
      AWARD_MILESTONE_DT: 2025-12-30
  2. Page 4

    www.morpc.org

    Accessed

    Supporting evidence (4)
    • Regional transportation planning records approved by the Central Ohio Rural Planning Organization show the project involves replacing the existing bridge structure, cataloged as SFN 2300095, with a new bridge structure, cataloged as SFN 2300096 replacement details.

      Read supporting passage
      Replacement of structure (SFN 2300095 FAI-22-0375) with new structure (SFN 2300096 FAI-22-0374).
    • The structure spans Clear Creek along Cincinnati-Zanesville Road, approximately 0.45 miles east of the intersection of U.S. 22 and Leist Road, where regional planning documents estimated total project costs at $1,717,794 project estimate.

      Read supporting passage
      0.45 miles east of US 22/Leist Road intersection $1,717,794
    • Fiscal programming adopted in the CORPO 2026–2029 Transportation Improvement Program allocated $1,610,000 in construction funding for fiscal year 2026 construction funding.

      Read supporting passage
      Total CO $ - $1,610,000 $ - $ - $ - $ - $1,610,000
    • That total combines $1,224,000 in dedicated bridge preservation funding, $306,000 in state revenue, and $80,000 in state labor costs, along with an additional $40,000 dedicated to right-of-way acquisition across previous and current fiscal schedules construction funding.

      Read supporting passage
      Total CO $ - $1,610,000 $ - $ - $ - $ - $1,610,000
  3. CINCINNATI-ZANESVILLE RD · eastbound · work zone

    Ohio Department of Transportation

    Accessed

    Supporting evidence (4)
    • While the overall contract completion milestone extends through Oct. 31, 2026, to allow for equipment removal and final site cleanup, the active roadway closure has severed U.S. 22 since May 26, 2026, when ODOT closed all lanes along the 0.12-mile work zone to begin bridge replacement full closure.

      Read supporting passage
      Starts=2026-05-26T04:00:00Z, Vehicle impact=all lanes closed
    • Automated state work zone tracking records currently list a target reopening date of Saturday, Oct. 17, 2026, for the roadway reopening target.

      Read supporting passage
      Ends=2026-10-17T03:59:00Z
    • Broader ODOT public travel advisories continue to project a general reopening window in late fall 2026 agency advisory.

      Read supporting passage
      United States Route 22 is closed to traffic west of Amanda over Clear Creek in Fairfield County for a bridge replacement project. The roadway is expected to reopen late fall 2026.
    • State work zone records classify the mid-October target as unverified because concrete curing and asphalt paving remain vulnerable to autumn temperature drops and rainfall agency advisory.

      Read supporting passage
      United States Route 22 is closed to traffic west of Amanda over Clear Creek in Fairfield County for a bridge replacement project. The roadway is expected to reopen late fall 2026.
  4. State Extends US 22 Bridge Closure West of Amanda Through Mid-October

    Published · Accessed

    Supporting evidence (1)
    • Route 22 west of Amanda through mid-October for ongoing bridge replacement work State Extends US 22 Bridge Closure West of Amanda Through Mid-October.

      Read supporting passage
      State Extends US 22 Bridge Closure West of Amanda Through Mid-October
  5. https://www.yahoo.com/news/us/articles/odot-updates-learn-current-projects-091137480.html

    www.yahoo.com

    Accessed

    Supporting evidence (2)
    • ODOT has maintained an official signed detour routing drivers along state highways detour route.

      Read supporting passage
      Detour: U.S. 22 to Ohio 674 to Ohio 188 to U.S. 33 to U.S. 22 and reverse.
    • Route 33, and return to U.S. 22, with eastbound traffic directed along the identical highway route in reverse detour route.

      Read supporting passage
      Detour: U.S. 22 to Ohio 674 to Ohio 188 to U.S. 33 to U.S. 22 and reverse.

Take Pique with you

Your city. In your pocket.

Read local stories, watch the videos and explore the details in Pique.

QR code for Pique Media on the App Store

Get Pique for iPhone and iPad

Scan the code with your phone’s camera.

View on the App Store