Video 0:27
Video
Columbus doubles Decker road repair contract to $700,000
Read the full articleColumbus City Council approved an emergency $350,000 contract modification with Decker Construction Company, doubling funding to $700,000 and extending utility cut roadway repairs through Oct. 31, 2027, to avoid a lapse before the agreement was set to expire Dec. 1.
How we know this
The sources and records behind this story, with the facts they support.
Supporting evidence (2)
Columbus City Council voted 9-0 on its consent agenda on Monday, Nov. 16, to approve an emergency $350,000 contract modification with Decker Construction Company for roadway utility cut repairs.
Read supporting passage
This item was approved on the Consent Agenda. Result: Pass · Mover: Tiara Ross · Seconder: Nancy Day-Achauer Consent agenda vote (event item 648445): Nicholas Bankston: Affirmative Lourdes Barroso De Padilla: Affirmative Nancy Day-Achauer: Affirmative Rob Dorans: Affirmative Melissa Green: Affirmative Emmanuel V. Remy: Affirmative Tiara Ross: Affirmative Christopher Wyche: Affirmative Shannon G. Hardin: Affirmative {Body=Columbus City Council, Content type=Outcomes, Document coverage=API text and document metadata; linked PDF bytes are not retained, Local time=5:00 PM, Location=City Council Chambers, Rm 231, Meeting date=2026-11-16T00:00:00, Municipality=columbus}
Columbus City Council voted 9-0 on its consent agenda on Monday, Nov. 16, to approve an emergency $350,000 contract modification with Decker Construction Company for roadway utility cut repairs.
Read supporting passage
To authorize the Director of Public Service to enter into a contract modification with Decker Construction Company for the Roadway - Utility Cut and Repair program; to authorize the expenditure of up to $350,000.00 from the Street Construction Maintenance and Repair Fund; and to declare an emergency.
Supporting evidence (8)
The measure doubles contract funding from an initial $350,000 to $700,000 and extends work through Oct. 31, 2027, exercising the first of two possible one-year extension periods.
Read supporting passage
The original contract amount: $350,000.00 (PO546106, Ord. 2991-2025) The total of modification 1: $350,000.00 (Ord. 2972-2026) The contract amount including all modifications: $700,000.00
The measure doubles contract funding from an initial $350,000 to $700,000 and extends work through Oct. 31, 2027, exercising the first of two possible one-year extension periods.
Read supporting passage
extend the contract for approximately one year to October 31, 2027, in the amount of $350,000.00 to pay for year two of the contract
The measure doubles contract funding from an initial $350,000 to $700,000 and extends work through Oct. 31, 2027, exercising the first of two possible one-year extension periods.
Read supporting passage
This ordinance authorizes the Director of Public Service to extend the contract for the first of two, possible periods of one year, and to add funds to pay for services provided in year two of the contract in the amount of $350,000.00.
City officials requested emergency action to prevent a service interruption and ensure the safety of the traveling public, as the existing agreement was scheduled to expire on Dec. 1, 2026.
Read supporting passage
to ensure payment for these services can continue to prevent a service interruption, for the immediate preservation of the public health, safety, property, and welfare
City officials requested emergency action to prevent a service interruption and ensure the safety of the traveling public, as the existing agreement was scheduled to expire on Dec. 1, 2026.
Read supporting passage
Emergency action is requested to continue the completion of the needed improvements at the earliest possible time to ensure the safety of the traveling public, as the current contract expires December 1, 2026.
Under the contract, Decker Construction performs as-needed work in municipal rights-of-way following utility cuts, including excavation, grading, curb, sidewalk, ADA ramps, planing, street repair, and paving.
Read supporting passage
The work performed to date for this project consists of as-requested work within the right-of-way, including excavation, grading, curb, sidewalk, ADA ramps, planing, street repair, paving, and other work as may be necessary to complete the contract in accordance with the plans and specifications set forth in the Bid Submittal Documents.
The $350,000 expenditure is funded through the city's Street Construction Maintenance and Repair Fund.
Read supporting passage
This is a budgeted item within Fund 2265, the Street Construction Maintenance and Repair Fund.
Decker Construction Company is based at 3040 McKinley Ave. in Columbus.
Read supporting passage
SECTION 1. That the Director of Public Service be and hereby is authorized to execute a contract modification for the Roadway - Utility Cut and Repair program with Decker Construction Company, of 3040 McKinley Avenue, Columbus, Ohio, 43204, for the Roadway - Utility Cut and Repair program in the amount of up to $350,000.00, and to extend the contract for approximately one year to October 31, 2027.
Columbus advances $650,000 expansion for street and sidewalk utility repairs
Supporting evidence (2)
Previously, Pique Media reported that Columbus City Council advanced a $650,000 contract modification with Decker Construction Company for utility cut restorations following its Nov. 2 meeting.
Read supporting passage
Columbus advances $650,000 expansion for street and sidewalk utility repairs
Previously, Pique Media reported that Columbus City Council advanced a $650,000 contract modification with Decker Construction Company for utility cut restorations following its Nov. 2 meeting.
Read supporting passage
During its meeting on Monday, Nov. 2, Columbus City Council advanced a $650,000 contract modification with Decker Construction Company for city utility cut restorations.